Laserfiche WebLink
Work Order 14 Amendment 4 <br />EXHIBIT A <br />SCOPE OF WORK, FEES, AND SCHEDULE <br />PID # 21.23.503 <br />SCOPE OF WORK <br />Task 4a — Project Risk Management <br />Bowman shall work with Utilities Staff to develop a Project Risk Register (PRR) for the 24" Force Main Replacement <br />project. This task shall include a meeting with IRCDUS staff to review the plans and identify schedule and cost <br />risks that may impact that project. Bowman will incorporate the risks into a register that assigns ownership, <br />response and financial or time value. <br />Task 4a shall commence upon Notice to Proceed (NTP) with the work to be completed within 45 days. <br />Task 7a — Additional Construction Services <br />In addition to the construction observation services described in Work Order 14, Task 7 Bowman will provide <br />Variance Analysis Report and Project Action Item services during the construction phase of the project. Using the <br />construction schedule provided by the contractor, Bowman will develop a construction and earned value schedule <br />to be used as a project baseline. <br />During construction, Bowman will conduct progress meetings with the contractor and IRCDUS PM. The <br />contractor's schedule will be compared to actual construction progress, and project construction progress for the <br />following two-week period. Bowman will prepare a variance analysis report (VAR) based in the meeting minutes. <br />The VAR will include recommendations to bring the project back on schedule if necessary. As part of this task <br />Bowman will review the PRR at each progress meeting and maintain a list of project action items (PAI). <br />Task 7a will commence and proceed with the construction schedule. The fee for this task includes up to five (5) <br />monthly meetings based on substantial construction completion at 120 -days. <br />FEE SCHEDULE <br />Bowman will provide the services described above for the following lump sum fees: <br />Task 4a — Project Risk Management $ 8,030.00 <br />Task 7a — Additional Construction Services $ 21,075.00 <br />Total Amendment 4: $ 29,105.00 <br />