Laserfiche WebLink
EXHIBIT `C' <br />TIME SCHEDULE <br />WORK ORDER No. <br />Time of Performance <br />The estimated time frame for completion of services from the approval of this Work Authorization <br />is as follows: <br />1. NTP Start Day 1 <br />2. Geotechnical Consultant work Complete Day 30 <br />3. Land Surveyor Complete Day 75 <br />4. Preliminary Plan Review and Evaluations Complete Day 120 <br />5. Submit Permit Applications On and After Day <br />150 <br />6. Engineering Design & Preparation of Construction Plans Complete Day 180 <br />7. Receipt of Permits and Bidding/Contract Award (Done Complete Day 240 <br />Concurrently) <br />8. Construction Start Day 270 <br />- Remainder of Page Intentionally Left Blank - <br />Page 6 of 6 <br />