fe7fa23e-3f6d-42ce-gd52-86d8a51ead21 <br />a legal proceeding the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, <br />instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay <br />(but not as a penalty), CONTRACTOR shall pay OWNER $ 80.00 for each calendar day that expires after the <br />time specified in paragraph 3.02 for completion and readiness for final payment until the Work is completed <br />and ready for final payment. <br />ARTICLE d - CONTRACT PRICE <br />4.01 OWNER shall pay CONTRACTOR for completion of the Work an amount in current funds equal to the <br />sum of the amounts determined pursuant to paragraph 4.o1.A and summarized in paragraph 4.oi.B, below: <br />A. For all Work, at the prices stated in CONTRACTOR's Bid, attached hereto as Exhibit 1. <br />B. THE CONTRACT SUM subject to additions and deductions provided in the Contract Documents: <br />Numerical Amount: $ <br />Written Amount: <br />ARTICLE.r; - PAYMENT PROCEDURES <br />5.01 Progress Payments. <br />A. The OWNER shall make progress payments to the CONTRACTOR on the basis of the approved <br />partial payment request as recommended by ENGINEER in accordance with the provisions of the Local <br />Government Prompt Payment Act, Florida Statutes section 218.7o et. seq. The OWNER shall retain five <br />percent (5%) of the payment amount due to CONTRACTOR until substantial completion and acceptance of <br />all work to be performed by CONTRACTOR under the Contract Documents. <br />B. For construction projects less than $10 million, at the time the Owner is in receipt of the Certificate <br />of Substantial Completion, the Owner shall have 30 calendar days to provide a list to the Contractor of <br />items to be completed and the estimated cost to complete each item on the list. Owner and Contractor <br />agree that the Contractor's itemized bid shall serve as the basis for determining the cost of each item on <br />the list. For projects in excess of $10 million, owner shall have up to 45 calendar days following receipt of <br />Certificate of Substantial Completion of the project to provide contractor with said list. <br />C. Within 20 business days following the creation of the list, Owner shall pay Contractor the <br />remaining contract balance including all retainage previously withheld by Owner except for an amount <br />equal to 150% of the estimated cost to complete all of the items on the list. <br />D. Upon completion of all items on the list, the Contractor may submit a payment request for the <br />amount of the 150% retainage held by the Owner. If a good faith dispute exists as to whether one or more <br />of the items have been finished, the owner may continue to withhold the 150% of the total cost to complete <br />such items. The owner shall provide Contractor written reasons for disputing completion of the list. <br />5.02 Pay Requests. <br />2 <br />172 <br />