Exhibit C <br />Schedule <br />Work Order No. 10 <br />SCHEDULE <br />AtkinsRealis <br />The anticipated schedule shown below is based on the number of weeks after the formal issuance <br />of the signed Work Order and a Notice to Proceed by the County. <br />Task No. I Task Title <br />01 <br />Kick- Off Workshop <br />02 <br />Data Collection <br />03 <br />Define Flow Rates <br />04 <br />Hydraulic Modeling Coordination <br />05 <br />Draft Feasibility Report <br />Final Feasibility Report <br />05 <br />Duration from NTP <br />2 weeks <br />6 weeks <br />10 weeks <br />12 weeks <br />20 weeks <br />30 weeks <br />City of Sebastian Buildout of Septic to Sewer Conversion <br />Feasibility Study Page 12 of 12 <br />