Times, or both, directly attributable to any such
<br />15.02 OWNER May Terminate for Cause
<br />A. The occurrence of any one or more of the
<br />following events will justify termination for cause:
<br />1. CONTRACTOR's persistent failure
<br />to perform the Work in accordance with the
<br />Contract Documents (including, but not limited
<br />to, failure to supply sufficient skilled workers or
<br />suitable materials or equipment or failure to
<br />adhere to the progress schedule established
<br />under paragraph 2.07 as adjusted from time to
<br />time pursuant to paragraph 6.04);
<br />2. CONTRACTOR's disregard of Laws
<br />or Regulations of any public body having
<br />jurisdiction;
<br />3. CONTRACTOR's disregard of the
<br />authority of ENGINEER; or
<br />4. CONTRACTOR's violation in any
<br />substantial way of any provisions of the
<br />Contract Documents.
<br />B. If one or more of the events identified in
<br />paragraph 15.02.A occur, OWNER may, after giving
<br />CONTRACTOR (and the surety, if any) seven days
<br />written notice, terminate the services of
<br />CONTRACTOR, exclude CONTRACTOR from the
<br />Site, and take possession of the Work and of all
<br />CONTRACTOR's tools, appliances, construction
<br />equipment, and machinery at the Site, and use the
<br />same to the full extent they could be used by
<br />CONTRACTOR (without liability to CONTRACTOR for
<br />trespass or conversion), incorporate in the Work all
<br />materials and equipment stored at the Site or for
<br />which OWNER has paid CONTRACTOR but which
<br />are stored elsewhere, and finish the Work as OWNER
<br />may deem expedient. In such case, CONTRACTOR
<br />shall not be entitled to receive any further payment
<br />until the Work is finished. If the unpaid balance of the
<br />Contract Price exceeds all claims, costs, losses, and
<br />damages (including but not limited to all fees and
<br />charges of engineers, architects, attorneys, and other
<br />professionals and all court or arbitration or other
<br />dispute resolution costs) sustained by OWNER arising
<br />out of or relating to completing the Work, such excess
<br />will be paid to CONTRACTOR. If such claims, costs,
<br />losses, and damages exceed such unpaid balance,
<br />CONTRACTOR shall pay the difference to OWNER.
<br />Such claims, costs, losses, and damages incurred by
<br />OWNER will be reviewed by ENGINEER as to their
<br />reasonableness and, when so approved by
<br />ENGINEER, incorporated in a Change Order. When
<br />exercising any rights or remedies under this
<br />paragraph OWNER shall not be required to obtain the
<br />lowest price for the Work performed.
<br />C. Where CONTRACTOR's services have been
<br />so terminated by OWNER, the termination will not
<br />affect any rights or remedies of OWNER against
<br />CONTRACTOR then existing or which may thereafter
<br />accrue. Any retention or payment of moneys due
<br />CONTRACTOR by OWNER will not release CON-
<br />TRACTOR from liability.
<br />15.03 OWNER May Terminate For Convenience
<br />A. Upon seven days written notice to CON-
<br />TRACTOR and ENGINEER, OWNER may, without
<br />cause and without prejudice to any other right or
<br />remedy of OWNER, elect to terminate the Contract.
<br />In such case, CONTRACTOR shall be paid (without
<br />duplication of any items):
<br />1. for completed and acceptable Work
<br />executed in accordance with the Contract
<br />Documents prior to the effective date of
<br />termination, including fair and reasonable sums
<br />for overhead and profit on such Work;
<br />2. for expenses sustained prior to the
<br />effective date of termination in performing
<br />services and furnishing labor, materials, or
<br />equipment as required by the Contract
<br />Documents in connection with uncompleted
<br />Work, plus fair and reasonable sums for
<br />overhead and profit on such expenses;
<br />3. for all claims, costs, losses, and
<br />damages (including but not limited to all fees
<br />and charges of engineers, architects, attorneys,
<br />and other professionals and all court or
<br />arbitration or other dispute resolution costs) in-
<br />curred in settlement of terminated contracts
<br />with Subcontractors, Suppliers, and others; and
<br />4. for reasonable expenses directly
<br />attributable to termination.
<br />B. CONTRACTOR shall not be paid on account
<br />of loss of anticipated profits or revenue or other eco-
<br />nomic loss arising out of or resulting from such
<br />termination.
<br />15.04 CONTRACTOR May Stop Work or
<br />Terminate
<br />00700 - General Conditions REV 5-10-13
<br />00700 - 43
<br />F:\Public Works\ENGINEERING DIVISION PROJECTS\1317-85th St Milling_91 st Ave to 101st Ave \Admin\bid documents\Master Contract Documents\00700 - General Conditions REV 5-
<br />10-13.doc
<br />
|