ADDENDUM #1 <br />Contract. Test all pavement lanes where the width is constant using a rolling straightedge and <br />document all deficiencies on a form approved by the Engineer. Notify the Engineer of the location <br />and time of all straightedge testing a minimum of 48 hours before beginning testing. <br />334-5.10.3.1.2 Rolling Straightedge Exceptions: Testing with the <br />rolling straightedge will not be required in the following areas: intersections, tapers, crossovers, <br />parking lots and similar areas. In addition, testing with the rolling straightedge will not be performed <br />on the following areas when they are less than 50 feet in length: turn lanes, acceleration/deceleration <br />lanes and side streets. However, correct any individual surface irregularity in these areas that <br />deviates from the plan grade in excess of 3/8 inch as determined by a 15 foot manual straightedge, <br />and that the Engineer deems to be objectionable, in accordance with 334-5.10.4. The Engineer may <br />waive or modify straightedging requirements if no milling, leveling, overbuild or underlying <br />structural layer was placed on the project and the underlying layer was determined to be <br />exceptionally irregular. <br />334-5.10.3.1.3 Final Type SP Structural Layer: Straightedge the <br />final Type SP structural layer with a rolling straightedge behind the final roller of the paving train or <br />as a separate operation. Address all deficiencies in excess of 3/16 inch in accordance with 334- <br />5.10.4.2. If the Type SP layer is to be the final surface, corrections may be waived by the Engineer. <br />Retest the corrected areas. <br />334-5.10.3.1.4 Friction Course Layer: Where a friction course is <br />called for in the Contract, at the completion of all paving operations, straightedge the friction course <br />either behind the final roller of the paving train or as a separate operation. Address all deficiencies <br />in excess of 3/16 inch in accordance with 334-5.10.4.3, unless waived by the Engineer. Retest all <br />corrected areas. <br />334-5.10.3.2 Asphalt Work Categories 1 and 2: If required by the Engineer, <br />straightedge the final structural layer with a rolling straightedge, either behind the final roller of the <br />paving train or as a separate operation. Correct all deficiencies in excess of 5/16 inch in accordance <br />with 334-5.10.4.2. Retest all corrected areas. If the Engineer determines that the deficiencies on a <br />bicycle path are due to field geometrical conditions, the Engineer will waive <br />corrections with <br />corrections11V <br />deduction to the pay item quantity. <br />334-5.10.4 Correcting Unacceptable Pavement: <br />334-5.10.4.1 General: Correct all areas of unacceptable pavement at no <br />additional cost. <br />334-5.10.4.2 Structural Layers: Correct deficiencies in the Type SP <br />structural layer by one of the following methods: <br />a. Remove and replace the full depth of the layer, extending a <br />minimum of 50 feet on both sides of the defective area for the full width of the paving lane. <br />b. Mill the pavement surface to a depth and width that is <br />adequate to remove the deficiency. (This option only applies if the structural layer is not the final <br />surface layer.) <br />334-5.10.4.3 Friction Course: Correct deficiencies in the friction course <br />layer by removing and replacing the full depth of the layer, extending a minimum of 50 feet on both <br />sides of the defective area for the full width of the paving lane. <br />334-6 Acceptance of the Mixture. <br />334-6.1 General: The asphalt mixture will be accepted based on the Asphalt Work Category <br />as defined below: <br />1) Asphalt Work Category 1 — Certification by the Contractor as defined in 334-6.2. <br />01025-41 Technical Specifications <br />F \Public Works\ENGINEERING DIVISION PROJECTS\1205-Vero Lake Estates Swk-87th St 101st Ave to CR510 <br />1LAP)Wdmim\ADDENDUMS\ADDENDUM 1\Technical Specifications Addendum #1 doc <br />