<br /> CONSENT
<br /> INDIAN RIVER COUNTY, FLORIDA
<br /> MEMORANDUM
<br /> TO: Joseph A. Baird, County Administrator
<br /> THROUGH: Christopher R. Mora, P.E., Public Works Director CAI--
<br /> THROUGH: Christopher J. Kafer Jr., P.E., County Engine4-. 4e
<br /> FROM: Richard B. Szpyrka, P.E., Project Engineer
<br /> SUBJECT: AWARD OF BID
<br /> 87th Street and 911 Avenue Sidewalk Improvements
<br /> IRC Project No. 1205, Bid No. 2015036
<br /> DATE: July 1, 2015
<br /> DESCRIPTION AND CONDITIONS
<br /> On March 11, 2015, the Board of County Commissioners entered into a Local Agency Program (LAP)
<br /> Agreement FM #431728-1-58/68-01 with the Florida Department of Transportation (FDOT) for the
<br /> construction of 6-foot wide concrete sidewalks along the north right of way line of 87th Street from 10111
<br /> Avenue to CR510 and along the east right of way line of 911 Avenue from 79th Street to 87th Street,including
<br /> drainage improvements, Swale grading, pavement markings and sodding of disturbed areas in Vero Lake
<br /> Estates. Also included in the grant amount are Construction, Engineering and Inspection (CEI) services.
<br /> The bid opening for the project was held on May 20, 2015. Seven (7) bids were received and opened. A
<br /> detailed bid tabulation is on file and available for viewing in the County Engineering Division. Bid totals are
<br /> as follows:
<br /> i
<br /> Blue Goose Construction, LLC Ft. Pierce, Florida $1,013,267.71
<br /> Kerns Construction & Property Mgmt. Inc. Ft. Pierce, Florida $1,084,854.00
<br /> Timothy Rose Contracting, Inc. Vero Beach, Florida $1,325,094.51
<br /> Douglas N. Higgins, Inc. Ann Arbor, Michigan $1,341,389.90
<br /> Sunshine Land Design, Inc. Stuart, Florida $1,465,010.41 *
<br /> Johnson-Davis, Inc. Lantana, Florida $1,490,406.00
<br /> Engecon Construction, Inc. Lake Worth, Florida $1,565,310.15 *
<br /> i
<br /> *Denotes mathematical errors were found and bid amounts corrected.
<br /> Blue Goose Construction, LLC., failed to submit a complete bid package by omitting the required Equal
<br /> Opportunity Office form. In addition, per the Contract Documents, Instructions to Bidders Article 3,
<br /> Qualification of Bidders: Article 3.01 A requires bidders to have "at least five years" experience in
<br /> construction of similar projects of this size and larger. Article 3.01 B requires bidders to have"successfully
<br /> constructed, as prime CONTRACTOR, at least three projects similar in scope to this project."The projects
<br /> listed by Blue Goose Construction, LLC.,include utility type improvements with no mention of sidewalk work
<br /> thus it does not appear that,they have successfully constructed at least three similar project as the prime
<br /> CONTRACTOR. Therefore the next lowest bidder Kerns Construction & Property Mgmt. Inc. has been
<br /> selected this project.The FDOT concurs with this selection.