The Indian River County Department of Public Works subsequently requested that several additional <br />directional bores be added to the project at existing driveways that were originally proposed to be open�ut and <br />restored. Meetings were held in the field at the project site with representatives of Public Works, Utilities, Felix <br />Equities and Masteller & Moler, the consulting Project Construction Services firm. This meeting resulted in a total of <br />six (6) additional bores. <br />Masteller & Meier negotiated a price for the additional bores based on the bid prices of similar bores in the <br />contract. Felix Equities agreed to the prices and submitted Change Order No. 1 (see attached change order <br />transmitted to Gordon Sparks by Masteller & Moler by letter dated November 21, 2001), which results in a <br />$29,078.00 increase to the project. This amount was determined by taking the total costs of the proposed directional <br />bores and deducting the total bid costs for PVC main that they will be replacing in the field. <br />ANALYSIS• <br />The overall Change Order increase of $29,078.00 results in a 2.36% overall increase to the originally <br />approved contFact amount and adjusts the contract amount to $1,263,108.00. The Utilities Department has budgeted <br />a total of $1,400,000.00 for this project_ <br />RECOMMENDATION: <br />The staff of the Department of Utility Services recommends that the Board Of County Commissioners <br />approve Change Order No. 1 and authorize the Chairman to execute same, as presented. <br />ON MOTION by Commissioner Tippin, <br />SECONDED by Commissioner Adams, the Board <br />unanimously approved Change Order No. I with <br />Felix Equities and Masteller and Moler, as <br />recommended by staff. <br />CHANGE ORDER IS ON FILE IN THE <br />OFFICE OF THE CLERK TO THE BOARD <br />DECEMBER 18, 2001 <br />-1 g- <br />�: <br />