SECTION 01311 <br /> CONSTRUCTION SCHEDULES <br /> PART 1 -- GENERAL <br /> 1 . 01 REQUIREMENTS INCLUDED <br /> A. Promptly after award of the Contract, Contractor shall prepare and <br /> submit to the Engineer estimated construction progress for the <br /> Work , with sub-schedules of related activities that are essential to <br /> its progress . <br /> B . Coordinate the work and scheduling with and around other <br /> contractors and individual trades performing work on the Project . <br /> C . Submit revised progress schedules with each application for <br /> payment . <br /> D . Progress Schedule shall become part of Contract Documents after <br /> approval by Engineer. <br /> 1 . 02 RELATED REQUIREMENTS <br /> A . In other parts of the Contract Documents : <br /> 1 , General Conditions : <br /> a . Articles 2 and 6 — Schedules , Reports , and <br /> Records <br /> b . Sections 6 . 1 and 6 . 2 — Supervision by Contractor <br /> C' Article 15 — Supervision of Work, Termination , and <br /> Delay <br /> B . Specified in other sections : <br /> 1 . Section 01000 : Summary of Work <br /> 2 , Section 01201 : Preconstruction Conference <br /> 3 . Section 01340 : Shop Drawings , Product Data , and <br /> Samples <br /> 1 . 03 FORM OF SCHEDULES <br /> A . Prepare schedules in the form of a horizontal bar chart as follows : <br /> 1 . Provide separate horizontal bar for each trade or operation <br /> 2 . Horizontal time scale : Identify the first work day of each <br /> week . <br /> • 01311 - 1 <br /> F:\Utilities\UTILITY - ENGINEERING\Projects - Assessment Projects\West Side Subdivision - UCP#2177\Bid docs\specs\01311 <br /> Construction Schedules.doc <br />