by the Owner as described in Section 14 . 3 constitute in the aggregate more than 100 percent of the total number of <br /> days scheduled for completion , or 120 days in any 365-day period , whichever is less . <br /> § 14.1 .3 If one of the reasons described in Section 14 . 1 . 1 or 14 . 1 . 2 exists, the Contractor may, upon seven days ' <br /> written notice to the Owner and Architect, terminate the Contract and recover from the Owner payment for Work <br /> properly executed and for payment of reasonable costs directly related to Work thereafter performed by Contractor <br /> in terminating the Contract 9including reasonable documented demobilization and cancellation charges , and proven <br /> loss with respect to materials, equipment, tools, and construction equipment and machinery, including reasonable <br /> overhead, gverhead and profit and da %geTthereon. <br /> § 14. 1 .4 If all of the Work is stopped for a period of 60 consecutive days through no act or fault of the Contractor or <br /> a Subcontractor or their agents or employees or any other persons performing portions of the Work under contract <br /> with the Contractor because the Owner has persistently failed to fulfill the Owner' s obligations under the Contract <br /> Documents with respect to matters important to the progress of the Work, the Contractor may, upon seven additional <br /> days ' written notice to the Owner and the Architect, terminate the Contract and recover from the Owner as provided <br /> in Section 14 . 1 . 3 . <br /> § 14.2 TERMINATION BY THE OWNER FOR CAUSE <br /> § 14.2.1 The Owner may terminate the Contract if the Contractor: <br /> . 1 persistently or repeatedly refuses or fails to supply enough properly skilled workers or proper <br /> materials ; <br /> .2 fails to make payment to Subcontractors for materials or labor in accordance with the respective <br /> agreements between the Contractor and the Subcontractors ; <br /> .3 persistently disregards laws, ordinances, or rules, regulations or orders of a public authority having <br /> jurisdiction; or <br /> .4 otherwise is guilty of substantial breach of a material provision of the Contract Documents . <br /> § 14.2.2 When any of the above reasons exist, the Owner, upon certification by the Architect that sufficient cause <br /> exists to justify such action, may without prejudice to any other rights or remedies of the Owner and after giving the <br /> Contractor and the Contractor' s surety, if any, seven-fifteen ( 15 ) days ' written notice, terminate employment of the <br /> Contractor and may, subject to any prior rights of the surety : <br /> . 1 take possession of the site and of all materials , equipment, tools, and construction equipment and <br /> machinery thereon owned by the Contractor; <br /> .2 accept assignment of subcontracts pursuant to Section 5 .4 ; and <br /> .3 finish the Work by whatever reasonable method the Owner may deem expedient . Upon request of the <br /> Contractor, the Owner shall furnish to the Contractor a detailed an accounting of the casts incurred by <br /> the Owner in finishing the Work. <br /> § 14.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 14 . 2 . 1 , the Contractor shall <br /> not be entitled to receive further payment until the Work is finished. <br /> § 14.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for <br /> the Architect' s services and expenses made necessary thereby, and other damages incurred by the Owner and not <br /> expressly waived , such excess shall be paid to the Contractor. If such costs and damages exceed the unpaid balance, <br /> the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or Owner, as the case <br /> may be, shall be certified by the Architect, upon application, and this obligation for payment shall survive <br /> termination of the Contract. <br /> § 14.3 SUSPENSION BY THE OWNER FOR CONVENIENCE <br /> § 14.3. 1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in <br /> whole or in part for such period of time as the Owner may determine . <br /> § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by <br /> suspension, delay or interruption as described in Section 14 . 3 . 1 . Adjustftent-if any . Any ad * ustment of the Contract <br /> Sum shall include profit. No adjustment shall be made to the extent : <br /> .1 that performance is, was or would have been so suspended , delayed or interrupted by another cause <br /> for which the Contractor is responsible ; or <br /> AIA Document A201 TM — 1997. Copyright ® 1911 , 1915t 1918, 1925, 1937, 1951 , 1958, 1961 , 1963, 1966, 1970, 1976, 1987 and 1997 by The <br /> American <br /> Institute of Architects. All rights reserved. WARNING : This AIA ° Document Is protected by U.S. Copyright Law and International Treaties. 41 <br /> Unauthorized reproduction or distribution of this AIA` Document, or any portion of It, may result In severe civil and criminal penalties, and will <br /> be <br /> prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14 :50:06 on 08/10/2005 under Order <br /> No. 1000192296_1 which expires on 8/8/2006, and is not for resale. <br /> User Notes: (726890250) <br />