My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2006-141
CBCC
>
Official Documents
>
2000's
>
2006
>
2006-141
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
7/28/2016 2:51:26 PM
Creation date
9/30/2015 9:40:35 PM
Metadata
Fields
Template:
Official Documents
Official Document Type
Agreement
Approved Date
05/02/2006
Control Number
2006-141
Agenda Item Number
7.Q.
Entity Name
Sheltra & Son Construction Co, Inc.
Subject
Wabasso Water Main Extension Project
Supplemental fields
SmeadsoftID
5609
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
7
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
readiness for final payment. <br />ARTICLE 4. CONTRACT PRICE. <br />4.1 OWNER shall pay <br />CONTRACTOR <br />for <br />completion of the work in accordance with the <br />Contract Documents in <br />current funds in <br />the <br />amount of <br />$575,000.00. <br />ARTICLE 5. PAYMENT PROCEDURES. <br />5.1. Progress Payments. The Owner shall make progress payments to the Contractor on <br />the basis of the approved partial payment request as recommended by Engineer in <br />accordance with the provisions of the Local Government Prompt Payment Act, <br />Florida Statutes section 218.70 at. seq. <br />5.1.1. The Owner shall retain ten percent (10%) of the payment amounts due to the <br />Contractor until fifty percent (50%) completion of the Work. After fifty percent <br />(50%) completion of the Work is attained as certified to Owner by Engineer in <br />writing, Owner shall retain five percent (5%) of the payment amount due to <br />Contractor until final completion and acceptance of all Work to be performed <br />by Contractor under the Contract Documents. Pursuant to Florida Statutes <br />section 218.735(8)(b), fifty percent (50%) completion means the point at <br />which the County as Owner has expended fifty percent (50%) of the total <br />cost of the construction services Work purchased under the Contract <br />Documents, together with all costs associated with existing change orders <br />and other additions or modifications to the construction services Work <br />provided under the Contract Documents. <br />5.2. Pay Requests. Each request for a progress payment shall be submitted on the <br />application for payment form supplied by Owner and the application for payment <br />shall contain the Contractor's certification. All progress payments will be on the <br />basis of progress of the Work measured by the schedule of values established, or in <br />the case of unit price work based on the number of units completed. After fifty <br />percent (50%) completion, and pursuant to Florida Statutes section 218.735(8)(d), <br />the Contractor may submit a pay request to the County as Owner for up to one half <br />(1/2) of the retainage held by the County, and the County shall promptly make <br />payment to the Contractor unless such amounts are the subject of a good faith <br />dispute; the subject of a claim pursuant to Florida Statutes section 255.05(2005); or <br />otherwise the subject of a claim or demand by the County or the Contractor. The <br />Contractor acknowledges that where such retainage is attributable to the labor, <br />services, or materials supplied by one or more subcontractors or suppliers, the <br />Contractor shall timely remit payment of such retainage to those subcontractors and <br />suppliers. Pursuant to Florida Statutes section 218.735(8)(c)(2005), Contractor <br />further acknowledges and agrees that: 1) the County shall receive immediate written <br />notice of all decisions made by Contractor to withhold retainage on any <br />subcontractor at greater than five percent (5%) after fifty percent (50%) completion; <br />and 2) Contractor will not seek release from the County of the withheld retainage <br />until the final pay request. <br />5.3 Paragraphs <br />5.1.1 and <br />5.2 do <br />not apply to.construction services Work purchased by <br />the County <br />as Owner <br />which are paid for, in whole <br />or in part, with federal funds and <br />are subject <br />to federal <br />grantor <br />laws and regulations <br />or requirements that are contrary <br />00530 EJCDC - Agreement between Owner and Contractocdoc <br />111IN910M <br />F Utit ies\UTILITY - ENGINEERING\Projects - Udity Construction Permits\IRC -West Wabasso Community Project - Gram\Engineering Mems\Bid Summary & <br />Recommendalion\00530 EJCDC -Agreement between Owner and Contramor.doc <br />
The URL can be used to link to this page
Your browser does not support the video tag.