Laserfiche WebLink
ARTICLE 3. CONTRACT TIME . <br /> 3. 1 The work will be completed in accordance with the following time frame. <br /> (a ) Within 30 calendar days from effective date of Notice to Proceed , Contractor <br /> shall complete the following tasks : <br /> 1 . Obtain all necessary permits. <br /> 2 . Receive approved shop drawings for all materials and equipment to be <br /> utilized in the job . <br /> 3 . Perform all photographic recording and documentation of conditions prior <br /> to construction . <br /> 4 . Locate all existing utilities in the area of work. <br /> 5 . Mobilize all labor, equipment, and materials . <br /> 6 . Deliver and store all equipment and materials to the job site. <br /> 7 . Notify all utilities and other affected parties prior to initiating construction . <br /> ( b) From 31 calendar days to 90 calendar days from the effective date of Notice to <br /> Proceed , the CONTRACTOR shall complete the following tasks : <br /> 1 . Install all pipe and appurtenant items. <br /> 2 . Perform all testing . <br /> 3 . Restore all disturbed areas to their pre-construction condition . <br /> 4. Correct all deficiencies noted by Engineer. <br /> Completion of all tasks outlined above ( i . e. , Subparagraphs a and b) constitutes <br /> Substantial Completion . <br /> (c) From 91 calendar days to 121 calendar days from the effective date of Notice to <br /> Proceed , the CONTRACTOR shall complete the following tasks : <br /> 1 . Clean up project area . <br /> 2. Remove all equipment and material from project site. <br /> 3 . Perform contract closeout procedures. <br /> Completion of all tasks outlined above ( i .e. , Subparagraphs a , b , and c) constitute Final <br /> Completion . <br /> 3. 2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the <br /> essence of this Agreement and that OWNER will suffer financial loss if the work is not <br /> completed within the times specified in Paragraph 3. 1 above, plus any extensions thereof <br /> allowed in accordance with Article 12 of the General Conditions. They also recognize the <br /> delays, expense and difficulties involved in proving in a legal preceding the actual loss <br /> suffered by OWNER if the work is not completed on time. Accordingly, instead of requiring <br /> any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay <br /> (but not as a penalty) CONTRACTOR shall pay OWNER four-hundred and fifty dollars <br /> ($450. 00) for each day that expires after the time specified in Paragraph 3. 1 for <br /> Substantial Completion , if CONTRACTOR shall neglect, refuse or fail to complete the <br /> remaining work within the Contract Time or any proper extension thereof granted by <br /> OWNER, CONTRACTOR shall pay OWNER four-hundred and fifty dollars ($450. 00) for <br /> each day that expires after the time specified in Paragraph 3. 1 for completion and <br /> readiness for final payment. <br /> 00530 EJCDC - Agreement between Owner and Contractor.doc <br /> 00530-2 <br /> FFAUlilitles\IITRITY - ENGINEERING\Projects - Assessment PMJec6\CRYSTAL SANDS WATER SERVICE - UCP#25D7\Englneerin9 Items\BID Summary. Evaluation 8 <br /> c v. ............ ._..._.. n...._. .,,.. r,.., .e..... n..,. <br />