Laserfiche WebLink
ARTICLE 4 . CONTRACT PRICE. <br /> 4. 1 OWNER shall pay CONTRACTOR for completion of the work in accordance with the <br /> Contract Documents in current funds in the amount of $ 4502 0 .00 . <br /> ARTICLE 5. PAYMENT PROCEDURES . <br /> 5. 1 . Progress Payments . The Owner shall make progress payments to the Contractor on <br /> the basis of the approved partial payment request as recommended by Engineer in <br /> accordance with the provisions of the Local Government Prompt Payment Act, <br /> Florida Statutes section 218 . 70 et. seq . <br /> 5 . 1 . 1 . The Owner shall retain ten percent ( 10%) of the payment amounts due to the <br /> Contractor until fifty percent (50% ) completion of the Work. After fifty percent <br /> (50%) completion of the Work is attained as certified to Owner by Engineer in <br /> writing , Owner shall retain five percent (5%) of the payment amount due to <br /> Contractor until final completion and acceptance of all Work to be performed <br /> by Contractor under the Contract Documents . Pursuant to Florida Statutes <br /> section 218 . 735(8 )( b ) , fifty percent (50% ) completion means the point at <br /> which the County as Owner has expended fifty percent (50%) of the total <br /> cost of the construction services Work purchased under the Contract <br /> Documents , together with all costs associated with existing change orders <br /> and other additions or modifications to the construction services Work <br /> provided under the Contract Documents. <br /> 5 . 2. Pay Requests . Each request for a - progress payment shall be submitted on the <br /> application for payment form supplied by Owner and the application for payment <br /> shall contain the Contractor's certification . All progress payments will be on the <br /> basis of progress of the Work measured by the schedule of values established , or in <br /> the case of unit price work based on the number of units completed . After fifty <br /> percent (50% ) completion , and pursuant to Florida Statutes section 218 . 735(8)(d ) , <br /> the Contractor may submit a pay request to the County as Owner for up to one half <br /> ( 1 (2) of the retainage held by the County, and the County shall promptly make <br /> payment to the Contractor unless such amounts are the subject of a good faith <br /> dispute ; the subject of a claim pursuant to Florida Statutes section 255 . 05(2005 ) ; or <br /> otherwise the subject of a claim or demand by the County or the Contractor. The <br /> Contractor acknowledges that where such retainage is attributable to the labor, <br /> services , or materials supplied by one or more subcontractors or suppliers , the <br /> Contractor shall timely remit payment of such retainage to those subcontractors and <br /> suppliers . Pursuant to Florida Statutes section 218 . 735(8) (c)(2005) , Contractor <br /> further acknowledges and agrees that : 1 ) the County shall receive immediate written <br /> notice of all decisions made by Contractor to withhold retainage on any <br /> subcontractor at greater than five percent (5% ) after fifty percent (50% ) completion ; <br /> and 2) Contractor will not seek release from the County of the withheld retainage <br /> until the final pay request. <br /> 5 . 3 Paragraphs 5 . 1 . 1 and 5 . 2 do not apply to construction services Work purchased by <br /> the County as Owner which are paid for, in whole or in part, with federal funds and <br /> are subject to federal grantor laws and regulations or requirements that are contrary <br /> to any provision of the Local Government Prompt Payment Act. In such event, <br /> payment and retainage provisions shall be governed by the applicable grant <br /> requirements and guidelines . <br /> 00530 EJCDC - Agreement between Owner and Contractor <br /> 00530-3 <br /> O:tDOCUME-ttgordons0.0CAL5-HTempt00530 EJCDC - Agreement between Owner and Contractor Doc <br />