Laserfiche WebLink
ATTACHMENT 3 <br /> 60 ACRE WETLAND BRINE DISPOSAL FOR <br /> NORTH COUNTY WATER TREATMENT FACILITY <br /> PROJECT IMPLEMENTATION SCHEDULE <br /> The Utility Department is under pressure by the Florida Department of Environmental Protection to <br /> prepare the permit application and plans covered by the existing Work Order No . 1 and this Change <br /> Order No . 1 and make a submittal by September 6, 2005 . In order to meet this date, Masteller & Moler, <br /> Inc. is proceeding with design and preparation of Construction Plans in anticipation that Change Order <br /> No . 1 will be approved as soon as possible. Therefore, the implementation schedule is as follows : <br /> MILESTONE COMPLETION DATE <br /> Notice To Proceed August 2, 2005 <br /> Submittal to FDEP September 6, 2005 <br /> EHM/cab <br /> file #0544LA <br /> (Change Order Exhibits.doc) <br />