Task 3 : Land Acquisition <br /> Description: The County will acquire the land necessary for project completion. <br /> Expected Results : Acquired land. <br /> Estimated Cost: Land acquisition cost is $ 194, 110 (this includes $40, 110 in-kind services by the County to clear <br /> abutting property, as part of the negotiated sale) . <br /> Estimated Schedule : Finish Month 1 . <br /> Deliverables : Acquired land. <br /> Task 4 : Prepare, Send, Receive, Evaluate and Award Construction Bid <br /> Description: The County will prepare, advertise for, send, receive, and evaluate bids for construction of the <br /> project. An award will be made, contracts signed and notice to proceed given. If needed, a separate notice to <br /> proceed for construction of the stormwater retention facility will be postponed until any required grant funding <br /> is received. <br /> Expected Results: A number of received competitive bids will be evaluated, a responsible low bid that is within <br /> budget will be selected. <br /> Estimated Cost: Administration of the bid process for the project is estimated to cost $3 ,000 and will be <br /> provided by the County as in-kind services to the project. <br /> Estimated Schedule: Start Month 2 , finish Month 5 . <br /> Deliverables : A construction contract with a notice to proceed given to the responsible low bidder. <br /> Task 5: Construction of Stormwater Retention Lake Facilities (Clearing and Excavation) <br /> Description: The County ' s selected contractor will clear and excavate the land for constmction of the <br /> stormwater treatment lake that is currently being designed and will be permitted by SJRWMD, FOOT, and. the <br /> Federal Aviation Administration. <br /> Expected Results : Clearing and excavation of the land. <br /> Estimated Cost : Clearing is estimated to cost $25,000 and excavation is estimated to cost $ 141 ,600 of which <br /> $ 111 ,600 is being requested from 319(h) for funding . <br /> Estimated Schedule : Clearing and excavation will begin in Month 8 and end in Month 15 . <br /> Deliverables : Clearing and excavation of the land. <br /> Task 6: Construction of Lake Control Structures for Water Quality Treatment & Outfall Pipe <br /> Description: The County ' s selected contractor will construct a lake control structure and outfall pipe system. <br /> The control structure will consist of a concrete inlet structure with a bleed-down orphie, and attenuation weir, <br /> and an emergency overflow. The bleed-down orifice will limit the discharge to improve water quality. The <br /> outfall pipe will route the discharge east along 41st Street and eventually discharge into the IRL via the existing <br /> 41 st Street ditch. <br /> Expected Results : Installation of lake control structures and outfall pipe at the stormwater treatment lake . <br /> Estimated Cost: Construction of the stormwater facility structures and outfall pipe are estimated to cost <br /> $ 57,400 which is entirely being requested from 319(h) for funding. <br /> Estimated Schedule: Start Month 18, finish Month 22 . <br /> Deliverables: Final lake structures and outfall pipe. <br /> Task 7 : Construction of Lake Inflow and Conveyance System <br /> Description: Simultaneous to the construction of the lake control structures and outfall pipe, the County' s <br /> selected contractor will construct a lake inflow and conveyance system for the project. The stormwater runoff <br /> will be routed to the lake using a combination of swale and pipe improvements. <br /> Expected Results : Final lake inflow and conveyance system. <br /> Estimated Cost: The lake inflow and conveyance system is estimated to cost $25,400, which is entirely being <br /> requested from 319(h) for funding. <br /> Estimated Schedule: Start Month 18, finish Month 22 . <br /> Deliverables : Final lake inflow and conveyance system. <br /> DEP Agreement No . WM836, Attachment A- 1 , Page 4 of I1 <br />