Attachment 3 <br />(Time Schedule) <br />Time of Performance <br />Work Order No. 4 — Original Contract <br />The estimated time frame for completion of services from the approval of the original <br />Work Order is as follows: <br />1. Surveying, Base Map and Preparation, Geotechnical <br />Evaluation, Engineering Hydraulic Analysis <br />2. Engineering Design & Preparation of Construction <br />Plans, specifications and Bid Documents <br />3. Submittal of Permit Applications and Receipt of permits <br />4. Bidding, Contract Award & Project Construction <br />Amendment No. 1 — Additional Water Main <br />2 Months (Completed) <br />2 Months (Completed) <br />1 '/z Months (Pending) <br />9 Months (Pending) <br />The estimated time frame for completion of services from the approval of the amended <br />Work Order is as follows: <br />1. Surveying, Base Map and Preparation, Geotechnical 3 Weeks <br />Evaluation, Engineering Hydraulic Analysis <br />2. Engineering Design & Preparation of Construction 2 Weeks <br />Plans, specifications and Bid Documents <br />3. Submittal of Permit Applications and Receipt of permits 5 Weeks <br />4. Bidding, Contract Award & Project Construction No Change From <br />Original <br />Attachment 3 <br />Work Order No.4 with Schulke, Bittle & Stoddard, LL.C. <br />