■ FDEP required a permit to construct the plant process and site improvements. The <br /> original plant process permit had been on hold pending approval of the separate <br /> industrial discharge permit being prepared by others. CDM was directed to prepare <br /> and apply for a construction permit to allow for plant modifications for components that <br /> do not impact the required industrial discharge permit in an effort to expedite <br /> construction aspects. This permitting effort was not anticipated in the original scope of <br /> work. <br /> ■ FDEP will require a Construction and Operations permit to allow the new water <br /> production unit processes to be installed when the industrial discharge permit has been <br /> issued. This secondary submittal will be required prior to achieving the substantial <br /> completion milestones for the construction phase. <br /> ■ CDM will prepare a minor modification to the site plan permit issued by the IRC <br /> Planning and Zoning Department for a change to the entrance gate to reduce the <br /> number of gate operators and reduce the capital cost of the facility. No request for <br /> additional information is anticipated in this effort. <br /> Task 4. 0 Bidding Assistance Services (No Changes in this Amendment) <br /> Task 5.0 Contract Administration/PeriodicField Representation <br /> Membrane procurement for the project has required additional general services during <br /> construction to negotiate and retain the price quoted by the membrane manufacturer. IRC <br /> contracted directly with the membrane manufacturer, in lieu of through the Contractor, <br /> avoiding sales taxes resulting in a $44,432 savings to IRC. CDM assisted IRC in this membrane <br /> procurement effort which was Change Order Number One to the construction contract. <br /> Change Order Two to the construction contract has added 105 days to the substantial <br /> completion dates. The final completion date has not changed. CDM will work with IRC staff <br /> to minimize any extension in services during this construction period. CDM reserves the right <br /> to seek additional compensation for time that may be necessary to provide the oversight for <br /> certifying the construction complete and/ or time dependent engineering services associated <br /> with this extension. CDM will notify IRC Staff prior to potential scope or budge impact. <br /> Task 6.0 Additional Engineering Design Services <br /> This task is added to delineate additional engineering effort required to accommodate minor <br /> changes in the plant configuration by incorporating features, and changing or upgrading <br /> existing facilities. The following items are addressed under this task. <br /> Subtask 6.1 Large Yard Piping Modification: <br /> Raw water is pumped from the well field at the fairgrounds adjacent to the North County plant. <br /> Recent changes in the location of some new wells have required a change to the large yard <br /> piping plan for the plant. This task is for supplementary engineering services to accommodate <br /> these changes in the well field piping. Additional effort is included to negotiate the necessary <br /> change order to the construction contract for this modification. This effort affects both the yard <br /> A-3 jb1414.dx <br />