Laserfiche WebLink
SC -14. 09 Waiver of Claims <br /> SC- 14 . 09 Delete paragraph GC44. 09.A in its entirety and insert the following paragraph in <br /> its place: <br /> A. Acceptance of Final Payment as Release. The acceptance by the <br /> CONTRACTOR of final payment shall be and shall operate as a release to the <br /> OWNER from all claims and all liability to the CONTRACTOR other than claims <br /> in stated amounts as may be specifically excepted by the CONTRACTOR for all <br /> things done or furnished in connection with this Work and for every act and <br /> ' neglect of the OWNER and others relating to or arising out of this Work. Any <br /> payment , however, final or otherwise , shall not release the CONTRACTOR or his <br /> sureties from any obligations under the Contract Documents or the Payment and <br /> ' Performance Bonds . <br /> SC -15 . 01 OWNER May Suspend Work <br /> SC- 15 . 01 .A Delete the last sentence in paragraph GC- 15. 01 .A and insert the following in its <br /> place: <br /> CONTRACTOR shall be allowed an extension of the Contract Times , directly attributable <br /> to any such suspension if CONTRACTOR makes a Claim for an extension as provided in <br /> paragraph 10 . 05 . CONTRACTOR shall not be allowed an adjustment of the Contract <br /> Price and CONTRACTOR shall not be paid on account of loss of anticipated profits or <br /> revenue or other economic loss arising out of or resulting from such Work suspension . <br /> ' SC -15 . 02 OWNER May Terminate For Cause <br /> SC- 15 . 02 . A. 5 and SC- 15 . 02 . A. 6 Add the following new paragraphs immediately after <br /> paragraph GC45. 02. A . 4: <br /> 5. . CONTRACTOR�s violation of Section 02225 - " Erosion Control` and Treatment; of <br /> Dewatering Water From the ConstructionSite." <br /> 6 . CONTRACTOR's failure to make payment to Subcontractors or Suppliers for <br /> materials or labor in accordance with the respective agreements between the <br /> CONTRACTOR and the Subcontractors or Suppliers . <br /> SC- 15 . 02 . 13 Delete the third sentence in paragraph GC- 15. 02. 8 and insert the following in its <br /> ' place: <br /> If the unpaid balance of the Contract Price exceeds all claims , costs , losses , and damages <br /> (including but not limited to all fees and charges of engineers , architects , attorneys , and <br /> other professionals and dispute resolution or litigation costs ) sustained by OWNER arising <br /> out of or relating to completing the Work, CONTRACTOR will be paid for acceptable <br /> earned Work that is fully completed or partially completed , and executed in accordance <br /> with the Contract Documents , prior to the effective date of termination . <br /> ' SC- 15 . 02 . D Add the following new paragraph immediately after paragraph GC45. 02. C: <br /> D . CONTRACTOR shall not be paid on account of loss of anticipated profits or <br /> revenue or other economic loss arising out of or resulting from such termination . <br /> SC -15.03 OWNER May Terminate For Convenience <br /> 0219-00800 - Supplementary conditions <br /> 0080011 <br /> FAEngineering\Capital Projects\0219-Kitching Station Trailhesd\0219 Kitching-Contract Docs\0219-00800 • Supplementary Condifions.doc Rev. 05/01 <br />