Laserfiche WebLink
ARTICLE 3. CONTRACT TIME. <br /> 3 . 1 The work will be completed in accordance with the following time frame. <br /> (a) Within 30 calendar days from effective date of Notice to Proceed , Contractor <br /> shall complete the following tasks: <br /> 1 . Obtain all necessary permits . <br /> 2. Receive approved shop drawings for all materials and equipment to be <br /> utilized in the job . <br /> 3 . Perform all photographic recording and documentation of conditions prior <br /> to construction . <br /> 4 . Locate all existing utilities in the area of work. <br /> 5 . Mobilize all labor, equipment, and materials. <br /> 6. Deliver and store all equipment and materials to the job site. <br /> 7. Notify all utilities and other affected parties prior to initiating construction . <br /> (b) From 30 calendar days to 210 calendar days from the effective date of Notice to <br /> Proceed , the CONTRACTOR shall complete the following tasks: <br /> 1 . Install all pipe and appurtenant items . <br /> 2 . Perform all testing . <br /> 3 . Restore all disturbed areas to their pre-construction condition . <br /> 4 . Correct all deficiencies noted by Engineer. <br /> Completion of all tasks outlined above (i .e . , Subparagraphs a and b) constitutes <br /> Substantial Completion . <br /> (c) From 210 calendar days to 240 calendar days from the effective date of Notice <br /> to Proceed, the CONTRACTOR shall complete the following tasks: <br /> 1 . Clean up project area. <br /> 2 . Remove all equipment and material from project site. <br /> 3. Perform contract closeout procedures. <br /> Completion of all tasks outlined above (i . e. , Subparagraphs a , b , and c) constitute Final <br /> Completion . <br /> 3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the <br /> essence of this Agreement and that OWNER will suffer financial loss if the work is not <br /> completed within the times specified in Paragraph 3. 1 above, plus any extensions thereof <br /> allowed in accordance with Article 12 of the General Conditions. They also recognize the <br /> delays, expense and difficulties involved in proving in a legal proceeding the actual loss <br /> suffered by OWNER if the work is not completed on time. Accordingly, instead of <br /> requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages <br /> for delay (but not as a penalty) CONTRACTOR shall pay OWNER four-hundred and fifty <br /> dollars ($450 .00) for each day that expires after the time specified in Paragraph 3. 1 for <br /> Substantial Completion , if CONTRACTOR shall neglect, refuse or fail to complete the <br /> remaining work within the Contract Time or any proper extension thereof granted by <br /> OWNER, CONTRACTOR shall pay OWNER four-hundred and fifty dollars ($450 .00) for <br /> each day that expires after the time specified in Paragraph 3. 1 for completion and <br /> readiness for final payment. <br /> 00530 EJCDC - Agreement between Owner and Contractor <br /> 00530-2 <br /> C: wur nts and SetlingsVgackson\Lmal Settings\Temporary Intemet Files\OLK1 E\005W EJCDC - Agreement between Owner and Contractordm <br />