Project Schedule Task Time Total Time <br /> Subtask 110 Data Collection 2 months 2 months <br /> Subtask 210 Habitat Characterization and <br /> Wetlands Jurisdiction 2 month <br /> Subtask 220 Development of Wetland <br /> Mitigation Plan 2 months <br /> Subtask 230 Stormwater Management Plan 2 months <br /> Subtask 240 ERP Application Preparation 2 months <br /> Subtask 250 USACE Individual Permit Application 2 months <br /> Subtask 260 Respond to FDEP RAIs 2 months 6 months <br /> Subtask 310 Landfill Stormwater Conceptual <br /> Evaluation 2 months <br /> Subtask 320 C-5 Bypass Canal Additional <br /> Property Acquisition 4 months <br /> Subtask 330 Conceptual Design of the <br /> C-5 Bypass Canal 4 months <br /> Subtask 340 Meetings with IRC SWDD On oin 4 months <br /> The total time for this project is estimated to be 10 months for permitting. <br /> B- 8 rb4508.doc <br />