Change Order Number 2 <br /> Indian River County North County Water Treatment Plant Expansion Phase II <br /> Potential <br /> Change <br /> Order <br /> number Description Amount Explanation <br /> 24 Remove and Replace Unsuitable Soils / Grade $5,917.00 Removed roots under ground storage tank, <br /> front Retention pond additional grading and sod for front stormwater <br /> retention pond area to meet St. Johns <br /> stormwater volume requirements . <br /> 25 Electrical Permit Reimbursement $9,853 .00 Electrical Subcontractor erroneously paid for <br /> electrical permit fees, which were IRC Utilities <br /> responsibility in the Contract <br /> 27 Extend 30" Raw Water Line to north $29, 958. 00 Extends Raw Water Line to connect to new well <br /> field piping locations north of plant per IRC <br /> request. <br /> 30 Fence By Fair Ground $ 1 , 641 .00 Replaces fence north of entrance gate to <br /> maintain security of fairgrounds and well field <br /> 34 Additional 24" Raw water gate valve $6, 154.00 Additional Work at request of IRC Utilities to <br /> install a 24" gate valve in existing feed line to <br /> provide for an alternate parallel feed to the <br /> plant. This give credit for not removing existing <br /> feed line. <br /> 35 Easement for FPL Feed $ 1 ,766.00 Survey work required to dedicate easement for <br /> FPL power feed to plant. <br /> Total Amount Change Order No. 2 $288,824. 00 <br /> North County Water Treatment Plant Contract Times <br /> IRC Bid No. 2006012 <br /> Original Contract Milestones <br /> (a) Ground Storage Tank July 11 , 2007 180 days <br /> (b) One new Skid January 7, 2008 360 days <br /> (c) Substantial September 3 , 2008 600 days <br /> (d) Final Completion January 1 , 2009 720 days <br /> Note : Contract Times and Liquidated Damages are in Article 3 of Section 00530 <br /> Contract Milestones after Change Order No 2. <br /> (a) Ground Storage Tank October 24, 2007 180 + 105 Days <br /> (b) One new Skid April 21 , 2008 360 + 105 days <br /> (c) Substantial December 17, 2008 600 + 105 days <br /> (d) Final Completion January 1 , 2009 720 days <br /> IRC NCWTP PHASE II EXPANSION <br /> CHANGE ORDER NO. 2 Additional Work Summary 07-13-2007.x15 Page 2 of 140 <br />