may be, shall be certified by the Architect, upon application, and this obligation for payment shall survive <br /> termination of the Contract. <br /> § 14.3 SUSPENSION BY THE OWNER FOR CONVENIENCE <br /> § 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend , delay or interrupt the Work in <br /> whole or in part for such period of time as the Owner may determine . <br /> § 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by <br /> suspension, delay or interruption as described in Section 14 .3 . 1 . Adjust if any . Any adjustment of the Contract <br /> Sum shall include profit. No adjustment shall be made to the extent: <br /> .1 that performance is, was or would have been so suspended, delayed or interrupted by another cause <br /> for which the Contractor is responsible; or <br /> .2 that an equitable adjustment is made or denied under another provision of the Contract. <br /> § 14.4 TERMINATION BY THE OWNER FOR CONVENIENCE <br /> § 14.4.1 The Owner may, at any time, terminate the Contract for the Owner' s convenience and without cause . <br /> § 14.4.2 Upon receipt of written notice from the Owner of such termination for the Owner' s convenience, the <br /> Contractor shall: <br /> . 1 cease operations as directed by the Owner in the notice; <br /> .2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work; <br /> and <br /> .3 except for Work directed to be performed prior to the effective date of termination stated in the <br /> notice, terminate all existing subcontracts and purchase orders and enter into no further subcontracts <br /> and purchase orders . <br /> § 14.4.3 In case of such termination for the Owner ' s convenience, the Contractor shall be entitled to receive payment <br /> for Work exeeuted executed in accordance with the Contract Documents and costs incurred by reason of such <br /> termination, along with reasonable overhead and profit on the Work not executed . thereon . <br /> AIA Document A201TM — 1997. Copyright ® 1911 , 1915, 1918, 1925, 1937, 1951 , 1958, 1961 , 1963, 1966, 1967, 19709 1976, 1987 and 1997 <br /> by The <br /> American Institute of Architects. All rights reserved. WARNING : This AIA® Document Is protected by U.S. Copyright Law and International Treaties. <br /> 42 <br /> Unauthorized reproduction or distribution of this AIA* <br /> Document, or any portion of It, may result In severe civil and criminal penalties, and will be <br /> prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 17:14:54 on 05/25/2005 under Order <br /> No. 1000126313_1 which expires on 6/29/2005, and is not for resale. <br /> User Notes: (3418817618) <br />