CONTRACTOR shall be allowed an extension of the Contract Times , directly attributable <br /> to any such suspension if CONTRACTOR makes a Claim for an extension as provided in <br /> paragraph 10 .05. CONTRACTOR shall not be allowed an adjustment of the Contract <br /> Price and CONTRACTOR shall not be paid on account of loss of anticipated profits or <br /> revenue or other economic loss arising out of or resulting from such Work suspension . <br /> SC-15.02 OWNER May Terminate For Cause <br /> SC- 15 . 02 .A. 5 and SC- 15 . 02.A. 6 Add the following new paragraphs immediately after <br /> paragraph GC- 15. 02. A. 4: <br /> 5 . CONTRACTOR's violation of Section 02225 — "Erosion Control and Treatment of <br /> Dewatering Water From the Construction Site . " <br /> 6 . CONTRACTOR's failure to make payment to Subcontractors or Suppliers for <br /> materials or labor in accordance with the respective agreements between the <br /> CONTRACTOR and the Subcontractors or Suppliers . <br /> SC- 15. 02 . 6 Delete the third sentence in paragraph GC- 15. 02. 8 and insert the following in its <br /> place: <br /> If the unpaid balance of the Contract Price exceeds all claims, costs, losses , and damages <br /> (including but not limited to all fees and charges of engineers , architects, attorneys , and <br /> other professionals and dispute resolution or litigation costs) sustained by OWNER arising <br /> out of or relating to completing the Work, CONTRACTOR will be paid for acceptable <br /> earned Work that is fully completed or partially completed , and executed in accordance <br /> with the Contract Documents, prior to the effective date of termination . <br /> SC- 15.02. D Add the following new paragraph immediately after paragraph GC- 15. 02. C: <br /> D. CONTRACTOR shall not be paid on account of loss of anticipated profits or <br /> revenue or other economic loss arising out of or resulting from such termination. <br /> SC-15.03 OWNER May Terminate For Convenience <br /> SC-15 .03.A.3 Delete paragraph GC- 15. 03.A. 3 in its entirety. <br /> SC -15.04 CONTRACTOR May Stop Work or Terminate <br /> SC-15 .04 Delete the following text from the first sentence of paragraph GC- 15. 04.A: <br /> SC-15. 04 Delete the following text from the second sentence of paragraph GC- 15. 04.A: <br /> CANNER has failed f 30 da to pay CONTRACTOR a surn finally determined to be <br /> dae- <br /> SC-16 DISPUTE RESOLUTION <br /> SC- 16 . 01 . A- Delete paragraph GC- 16. 01 . A in its entirety and insert the following paragraph in its <br /> place: <br /> 0201 -00800 - Supplementary Conditions <br /> 00800 11 <br /> F]Engineering\Capital Prolects10201 -03128­Indian River Drive Sidewalk-South-Highland Drive SM0201 Indian River Drive South Sidewalk - Contract DocsN0201 -00000 - <br /> Supplerriti Conditions.doc Rev. 0501 <br />