r <br /> Upon approval by Engineer and Owner as to any adjustments to the contract price and/or time for r <br /> changes performed under a CDD, such approval shall be recorded by the preparation of a change order. The <br /> Contractor shall not seek payment for work performed pursuant to a CDD until it has been converted to a <br /> change order. <br /> r <br /> The Engineer shall have the authority to order minor changes in the work which do not involve <br /> adjustment to the Contract price or time and which are not inconsistent with the intent of the contract <br /> documents . r <br /> A bond rider from the Surety shall be submitted to the City with each change order that increases the <br /> Contract price. <br /> r <br /> GC 38 USE OF COMPLETED PORTIONS. <br /> The Owner shall have the right to take possession of and use any substantially completed portions of <br /> the work. Such use by Owner shall not be construed as constituting final acceptance, and shall neither relieve r <br /> Contractor of any of its responsibilities under the Contract, nor act as a waiver by Owner of any contract <br /> provisions; provided that the Contractor shall not be liable for any repair or maintenance required due to <br /> ordinary wear and tear resulting from such use. However, if such use increases the cost or delays the <br /> completion of remaining portions of work, Contractor shall be entitled to an equitable adjustment under the <br /> contract. <br /> GC 39 CLEANING UP. r <br /> Upon completion of any portion of the work, the Contractor shall remove at his own expense from the <br /> Owner's property all temporary structures , equipment and surplus materials not required for later stages of <br /> work, rubbish, and waste materials resulting from his operations. Contractor shall make its own <br /> arrangements, at its own cost, for disposal of rubbish and waste materials. The Owner reserves the right to ■ <br /> retain any surplus or salvage materials . <br /> CG 40 BASIC REQUIREMENTS PRIOR TO SUBSTANTIAL COMPLETION r <br /> The following items shall be completed as a condition precedent to substantial completion and prior to <br /> a request by the Contractor for inspection for substantial completion. In the event the Contract does not define <br /> substantial completion, the following are also conditions for final completion and acceptance: <br /> 1 . All general construction completed and the project components shall be clean and all r <br /> systems fully functional . <br /> 2 . All mechanical and electrical work substantially complete, fixtures in place, connected, <br /> cleaned and ready for use. <br /> 3. Al[ electrical circuits shall be scheduled in panels and all panels and disconnect switches r <br /> properly labeled . <br /> 4. Issuance of all permits and certificates, inspections, and other approvals and releases by <br /> governing authorities required for Owner's occupancy and use of the project. r <br /> 5. Project site shall be cleared of Contractor's excess equipment and/or supplies and material . <br /> 6. All sets of operation and maintenance manuals for all equipment shall have been submitted , <br /> as referenced in the technical specifications . <br /> 7. Manufacturers' certifications and warranties shall be delivered to Owner. r <br /> 8. All operations and maintenance manuals for all equipment shall be delivered to Owner. <br /> 9 . All required spare parts, as well as any special devises and tools shall be delivered to Owner. <br /> 10. All keys and blanks shall have been provided . r <br /> it . Punch list of items required to render the construction services complete, satisfactory and <br /> acceptable to the Owner. If the Contract provides for a multi-phased or multi-structure project, a punch list <br /> must be developed for each phase or structure. <br /> r <br /> Contractor shall arrange a joint site and project inspection(s) with Engineer for inspection for <br /> substantial completion and development of a punch list for the completion of construction services. Said <br /> punch list shall be prepared not later than thirty (30) days after the inspection for substantial completion . r <br /> Punch list items recorded as a result of inspections for substantial completion shall be corrected by the <br /> Contractor prior to any request for final inspection and acceptance. <br /> r <br /> 39 <br /> 352CM 9.5429AM <br /> r <br />