CONTRACTOR shall be allowed an extension of the Contract Times , directly attributable <br /> to any such suspension if CONTRACTOR makes a Claim for an extension as provided in <br /> paragraph 10 . 05 . CONTRACTOR shall not be allowed an adjustment of the Contract <br /> Price and CONTRACTOR shall not be paid on account of loss of anticipated profits or <br /> revenue or other economic loss arising out of or resulting from such Work suspension . <br /> SC-15.02 OWNER May Terminate For Cause <br /> SC- 15 . 02 .A. 5 and SC- 15. 02 .A. 6 Add the following new paragraphs immediately after <br /> paragraph GC- 15. 02.A . 4: <br /> 5. CONTRACTOR's violation of Section 02225 — " Erosion Control and Treatment of <br /> Dewatering Water From the Construction Site. " <br /> 6 . CONTRACTOR's failure to make payment to Subcontractors or Suppliers for <br /> materials or labor in accordance with the respective agreements between the <br /> CONTRACTOR and the Subcontractors or Suppliers. <br /> SC- 15 . 02. 13 Delete the third sentence in paragraph GC- 15. 02. B and insert the following in its <br /> place: <br /> If the unpaid balance of the Contract Price exceeds all claims, costs, losses , and damages <br /> (including but not limited to all fees and charges of engineers , architects, attorneys, and <br /> other professionals and dispute resolution or litigation costs) sustained by OWNER arising <br /> out of or relating to completing the Work, CONTRACTOR will be paid for acceptable <br /> earned Work that is fully completed or partially completed , and executed in accordance <br /> with the Contract Documents, prior to the effective date of termination . <br /> SC- 15. 02. D Add the following new paragraph immediately after paragraph GC- 15. 02. C.- <br /> D. <br /> C- 15. 02. C:D. CONTRACTOR shall not be paid on account of loss of anticipated profits or <br /> revenue or other economic loss arising out of or resulting from such termination . <br /> SC-15.03 OWNER May Terminate For Convenience <br /> SC- 15 . 03.A. 3 Delete paragraph GC- 15. 03.A. 3 in its entirety. <br /> SC-15.04 CONTRACTOR May Stop Work or Terminate <br /> SC- 15. 04 Delete the following text from the first sentence of paragraph GC- 15. 04.A: <br /> . n1Afli faun Fnr 30 days Inn y GONTRAGTORRRY m fi Rall • d8teFrRiRe ! In be .� <br /> SC-15.04 Delete the following text from the second sentence of paragraph GC- 15. 04.A: <br /> i OWNER hAr f iled fiaF 30 days to pay CONTRACTOR any surn finally determined to be <br /> due-, <br /> SC-16 DISPUTE RESOLUTION <br /> SC- 16 . 01 .A. Delete paragraph GC- 16. 01 .A in its entirety and insert the following paragraph in its <br /> place: <br /> 00800 - Supplementary Conditions 2006041 <br /> 00800 13 <br /> FiPublic Works\Capital Projec slOslo Roin&Oslo Widening, Old Dixie to 27th Ave1CONTRACT DOCOMENT00900 - Supplementary Conditions 2006061 doc Rev. 05/01 <br />