Laserfiche WebLink
SECTION 01300 - SUBMITTALS <br /> ' j <br /> J PART 1 - GENERAL <br /> 1 .01 GENERAL <br /> The provisions of this section apply to required submittals, related to units of work, not to <br /> administrative submittals such as payment requests, insurance certificates and progress <br /> reports. In addition to specific provisions of General and Supplementary Conditions <br /> related to submittals, individual specification sections of Divisions 2 through 16 contain <br /> submittal requirements, specific requirements in other sections have precedence over <br /> general requirements of this section . <br /> PART 2 - PRODUCTS <br /> 2 . 01 PROCEDURAL REQUIREMENTS <br /> A. General : Coordinate submittals with progress schedule and actual progress of work; <br /> allow ten ( 10) working days for Architect ' s and Engineer ' s processing of submittals <br /> requiring review and approval - Use transmittal form to establish complete record or <br /> submittals. Provide copies required by governing authorities, which are in addition to <br /> copies specified for submittal to the Architect. <br /> 1 B . Shop drawings: shall be submitted for manufactured or fabricated materials as called <br /> for in the separate specification section. Drawings shall be fully identifiable with <br /> project name, location, supplier' s name, date, drawing number, specifications section <br /> reference, etc. . . The Contractor shall submit, with such promptness as to cause no <br /> delay in his work or in that of any Subcontractor, four (4) copies of all shop <br /> drawings and schedules required for the work of the various trades to the <br /> Architect for approval and (1) one copy of the shop drawings to the Owner's <br /> representative for review and comment. The Contractor shall make no deviation <br /> from the approved shop drawings and/or the changes made thereto by the Architect, if <br /> any. Additional prints, as may be required by the Contractor or a Subcontractor. shall <br /> be supplied by the Contractor. <br /> C. It shall be the responsibility of the Contractor to properly schedule the submission of <br /> shop drawings for approval, to allow adequate time for the checking of drawings, <br /> manufacturer/fabrication of items, and the shipment of items to the job site in <br /> sufficient time so as to prevent any delay in the Progress Schedule. <br /> D. It shall also be the responsibility of the Contractor to coordinate the preparation of <br /> shop drawings of those items which will be furnished by more than one manufacturer, <br /> but are designed to interface with the overall project when installed. <br /> 01300-1 <br />