Laserfiche WebLink
SECTION 01025 <br /> ' MEASUREMENT AND PAYMENT — REVISED APRIL 29 , 2003 <br /> ' 1 . 1 DESCRIPTION <br /> ' A . The items listed below, beginning with Paragraph 1 . 4 , refer to and are the same pay <br /> items listed in the Bid Form . They constitute all of the pay items for the completion <br /> of the Work. Furnish and install any items shown or omitted that are required for a <br /> ' complete installation , at no additional cost to the OWNER . No direct or separate <br /> payments will be made for providing miscellaneous temporary or accessory works , <br /> plant , services , CONTRACTOR' s or ENGINEER's field offices , repair or <br /> ' replacement of existing utilities , job signs , sanitary requirements , testing , safety <br /> devices , replacement of unpaved roads , clean-up , protection of the Work and <br /> property, field verification or location of buried utilities , water supplies , power, <br /> ' maintaining traffic , removal of waste , watchmen , and all other similar requirements <br /> of the General Conditions , Supplementary Conditions , General Requirements , and <br /> the Specifications . Compensation for all such services , things , and materials shall <br /> ' be included in the prices stipulated for the lump sum or unit price pay items , as <br /> applicable , listed herein . <br /> ' B . Each lump sum and unit bid price will be deemed to include an amount considered <br /> by CONTRACTOR to be adequate to cover CONTRACTOR' s overhead and profit <br /> for each separately identified item . <br /> C . Note that many of the descriptions for payment of the bid items listed below <br /> may <br /> include the words "including but not limited to , " followed by a list of specific items <br /> that are included in the bid item . The use of "included but not limited to , " or similar <br /> words , means that other items may be included in the bid item , but they have not <br /> been listed by the ENGINEER . If a list is provided , it is intended only as an aid to <br /> ' the CONTRACTOR and it shall not limit the actual items that are included in the bid <br /> item . <br /> 1 . 2 ENGINEER' S ESTIMATE OF QUANTITIES <br /> A. ENGINEER' s estimated quantities for unit bid prices , as listed in the Bid Form , are <br /> ' approximate only and are included solely for the purpose of comparing Bids . <br /> OWNER does not expressly or by implication agree that the nature of the materials <br /> encountered or the actual quantities of material encountered or required will <br /> ' correspond therewith . OWNER reserves the right to increase or decrease any <br /> quantity or to eliminate any quantity as OWNER may deem necessary. <br /> CONTRACTOR will not be entitled to any adjustment in a unit bid price as a result <br /> Last revised 4/29/03 01025- 1 EAST GIFFORD <br /> F:\Public Works\KeithM\Storm%eter Projects\Efford East\Construction Contract\Technical Specifications\Final Specifications\Division <br /> 1 \01025 - Measurement and Paynent - Revised April 29, 2003.doc <br />