• The survey area shall extend outside the entire permitted borrow site by a minimum of <br /> 500 feet. <br /> • Cross-sections of the borrow site shall be surveyed perpendicular to the long axis of the <br /> borrow site. <br /> • Cross-sections shall be surveyed at 250 foot intervals and shall extend a minimum of <br /> 500 feet beyond the boundaries of the borrow site. <br /> • All survey drawings shall be at a scale acceptable to the COUNTY. Final plan view <br /> drawings shall be submitted both with and without contours. <br /> • All drawings shall be submitted in an electronic format acceptable to the COUNTY. <br /> 34. PRE AND POST-CONSTRUCTION BEACH AND OFFSHORE SURVEYS <br /> The elevations indicated in the Plans are based on a survey conducted in August 2001 and may not <br /> represent accurate beach elevations at the time of construction. Therefore, the CONTRACTOR shall <br /> perform a beach profile survey prior to the initiation of construction. The surveys shall be conducted <br /> so that the COUNTY may adjust the fill volume as needed at the cross-sections and provide the <br /> CONTRACTOR with a template or pay volume change order if required. Pre-construction surveys <br /> shall be conducted by the CONTRACTOR no more than four (4) weeks prior to the commencement <br /> of dredging. These pre-construction surveys shall be provided to the COUNTY no less than two (2) <br /> weeks ( 14 calendar days) prior to the commencement of dredging so that the design templates may <br /> be adjusted by the COUNTY to reflect the pre-construction survey. Post-construction surveys shall <br /> be conducted no more than two (2) weeks following completion of dredging. <br /> 34. 1 Beach Surveys. Beach profiles shall be conducted by differential leveling techniques from <br /> the back beach or dune across the profile to approximately 40 feet seaward of the design fill <br /> section using laser distance measurement instrumentation or other method approved by the <br /> COUNTY. CONTRACTOR shall close all level loops and said closure shall be less than <br /> 0.04 feet. This survey work shall be documented in field books with copies supplied to the <br /> COUNTY. <br /> 34.2 Offshore Surveys. Offshore surveys shall be conducted by the CONTRACTOR using <br /> standard positioning and hydrographic surveying equipment and techniques . The <br /> CONTRACTOR shall utilize horizontal positioning equipment that has an accuracy of at <br /> least f3 feet. If range-range positioning system is used, shore stations must be set to ensure <br /> the accuracy of t3 feet. The location offshore control stations for the beach profiles must <br /> be approved by the COUNTY prior to the beach profile surveys. <br /> 34.3 Survey Points. A sufficient number of points shall be taken along each line to ensure <br /> adequate description of the profile. All topographic features, and major breaks in slope, <br /> including dunes, beach berms, foreshore, and bar and trough systems, shall be identified. <br /> On smoothly sloping sections a maximum elevation difference of approximately 1 foot <br /> between adjacent points shall be used to define this section of the profile. The design berm <br /> TECHNICAL AND ENVIRONMENTAL SPECIFICATIONS TS-33 <br />