Laserfiche WebLink
EXHIBIT 3 <br /> SCHEDULE <br /> Work Order 15 <br /> Vero Beach, FL <br /> Upon approval of the Work Order, it is anticipated that Geosyntec will prepare design drawings <br /> for the fueling area and perform the Phase I ESA and NEPA Evaluation in June 2008 . Upon <br /> completion of the design drawings and construction permitting, it is anticipated that the fueling <br /> area construction activities will be completed in July/August 2008 . Upon completion of the <br /> fueling area concrete pad, the AST will be re-located from the Gifford Road site in August 2008 <br /> and the steel AST located at the IRC landfill will be closed in August/September 2008 <br />. <br /> Geosyntec anticipates that the Tank Closure Assessment Report documenting the closure of the <br /> steel AST located at the IRC landfill will be submitted by October 2008 . <br /> XR08051 R/CCR08045R. DOC <br /> engineers I scientists I innovators <br />