r <br /> 6.05 Acceptance of Final Payment as Release. <br /> A. The acceptance by the CONTRACTOR of final payment shall be and shall operate <br /> as a release to the OWNER from all claims and all liability to the CONTRACTOR <br /> other than claims in stated amounts as may be specifically excepted by the <br /> CONTRACTOR for all things done or furnished in connection with the work <br /> under this Contract and for every act and neglect of the OWNER and others <br /> relating to or arising out of the work. Any payment, however, final or otherwise , <br /> shall not release the CONTRACTOR or its sureties from any obligations under <br /> the Contract Documents or the Payment and Performance Bonds . <br /> ARTICLE 7 - INDEMNIFICATION <br /> 7.01 CONTRACTOR shall indemnify OWNER, ENGINEER, and others in accordance with <br /> paragraph 6.20 (Indemnification) of the General Conditions to the Construction Contract. <br /> ARTICLE 8 - CONTRACTOR' S REPRESENTATIONS <br /> 8.01 In order to induce OWNER to enter into this Agreement CONTRACTOR makes the <br /> IN following representations: <br /> A. CONTRACTOR has examined and carefully studied the Contract Documents and the <br /> other related data identified in the Bidding Documents. <br /> B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the <br /> general, local , and Site conditions that may affect cost, progress, and performance of the <br /> Work. <br /> C. CONTRACTOR is familiar with and is satisfied as to all federal , state , and local Laws and <br /> Regulations that may affect cost, progress, and performance of the Work. <br /> D. CONTRACTOR has carefully studied all : ( 1 ) reports of explorations and tests of <br /> subsurface conditions at or contiguous to the Site and all drawings of physical conditions <br /> in or relating to existing surface or subsurface structures at or contiguous to the Site <br /> (except Underground Facilities) which have been identified in the Supplementary <br /> Conditions as provided in paragraph 4.02 of the General Conditions and (2) reports and <br /> drawings of a Hazardous Environmental Condition , if any, at the Site which have been <br /> identified in the Supplementary Conditions as provided in paragraph 4.06 of the General <br /> r Conditions. <br /> E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having <br /> done so) all additional or supplementary examinations, investigations , explorations, tests, <br /> studies, and data concerning conditions (surface , subsurface, and Underground Facilities) <br /> at or contiguous to the Site which may affect cost, progress, or performance of the Work <br /> or which relate to any aspect of the means, methods, techniques, sequences, and <br /> procedures of construction to be employed by CONTRACTOR, including applying the <br /> specific means, methods, techniques, sequences, and procedures of construction , if any, <br /> expressly required by the Contract Documents to be employed by CONTRACTOR, and <br /> safety precautions and programs incident thereto <br /> F. CONTRACTOR does not consider that any further examinations, investigations, <br /> explorations, tests, studies, or data are necessary for the performance of the Work at the <br /> 00520 - Agreement (Public Works) REV 04-07 <br /> 00520 - 5 �[,L,'t✓/ <br /> C:M)OCenrane and seainosNnclauohonuxel seairogmTenVonary kss m F4"No J(5=Wo - Fgreem (PWlk Works) REV 04-07-dw <br />