<br /> r equipment and machinery, tools , appliances , fuel,
<br /> 6 . 01 Supervision and Superintendence power, light, heat, telephone, water, sanitary facilities ,
<br /> temporary facilities, and all other facilities and
<br /> A. CONTRACTOR shall supervise , inspect, and incidentals necessary for the performance, testing ,
<br /> i direct the Work competently and efficiently, devoting start-up, and completion of the Work.
<br /> such attention thereto and applying such skills and
<br /> expertise as may be necessary to perform the Work in B . All materials and equipment incorporated into
<br /> W accordance with the Contract Documents . CON- the Work shall be as specified or, if not specified , shall
<br /> TRACTOR shall be solely responsible for the means , be of goad quality and new, except as otherwise
<br /> methods, techniques , sequences , and procedures of provided in the Contract Documents. All warranties
<br /> construction , but CONTRACTOR shall not be and guarantees specifically called for by the
<br /> i responsible for the negligence of OWNER or Specifications shall expressly run to the benefit of
<br /> ENGINEER in the design or specification of a specific OWNER. If required by ENGINEER, CONTRACTOR
<br /> means, method , technique, sequence, or procedure shall furnish satisfactory evidence (including reports of
<br /> i of construction which is shown or indicated in and required tests) as to the source , kind , and quality of
<br /> expressly required by the Contract Documents . CON- materials and equipment. All materials and
<br /> TRACTOR shall be responsible to see that the equipment shall be stored , applied , installed ,
<br /> completed Work complies accurately with the connected , erected , protected , used , cleaned , and
<br /> i Contract Documents. conditioned in accordance with instructions of the
<br /> applicable Supplier, except as otherwise may be
<br /> B . At all times during the progress of the Work, provided in the Contract Documents.
<br /> • CONTRACTOR shall assign a competent resident
<br /> superintendent thereto who shall not be replaced 6 .04 Progress Schedule
<br /> without written notice to OWNER and ENGINEER
<br /> except under extraordinary circumstances . The A. CONTRACTOR shall adhere to the progress
<br /> i superintendent will be CONTRACTOR's schedule established in accordance with paragraph
<br /> representative at the Site and shall have authority to 2 . 07 as it may be adjusted from time to time as
<br /> act on behalf of CONTRACTOR. All communications provided below.
<br /> i given to or received from the superintendent shall be
<br /> binding on CONTRACTOR. 1 . CONTRACTOR shall submit to
<br /> ENGINEER for acceptance (to the extent indi-
<br /> 6.02 Labor, Working Hours cated in paragraph 2 .07) proposed
<br /> Ir adjustments in the progress schedule that will
<br /> A. CONTRACTOR shall provide competent, not result in changing the Contract Times (or
<br /> suitably qualified personnel to survey, lay out, and Milestones). Such adjustments will conform
<br /> r construct the Work as required by the Contract Docu- generally to the progress schedule then in
<br /> ments. CONTRACTOR shall at all times maintain effect and additionally will comply with any
<br /> good discipline and order at the Site. provisions of the General Requirements
<br /> applicable thereto .
<br /> B. Except as otherwise required for the safety or
<br /> protection of persons or the Work or property at the 2. Proposed adjustments in the
<br /> Site or adjacent thereto, and except as otherwise progress schedule that will change the
<br /> i stated in the Contract Documents, all Work at the Site Contract Times (or Milestones) shall be
<br /> shall be performed during regular working hours, and submitted in accordance with the requirements
<br /> CONTRACTOR will not permit overtime work or the of Article 12. Such adjustments may only be
<br /> performance of Work on Saturday, Sunday, or any made by a Change Order or Written Amend-
<br /> legal holiday without OWNER's written consent ment in accordance with Article 12 .
<br /> (which will not be unreasonably withheld) given after
<br /> prior written notice to ENGINEER. 6 .05 Substitutes and "Or-Equals"
<br /> i
<br /> A. Whenever an item of material or equipment is
<br /> 6 .03 Services, Materials, and Equipment specified or described in the Contract Documents by
<br /> using the name of a proprietary item or the name of a
<br /> 110 A. Unless otherwise specified in the General particular Supplier, the specification or description is
<br /> Requirements, CONTRACTOR shall provide and intended to establish the type, function, appearance,
<br /> assume full responsibility for all services, materials, and quality required . Unless the specification or
<br /> i equipment, labor, transportation, construction description contains or is followed by words reading
<br /> 00700 - General Conditions REV 04-07
<br /> 00700 - 19
<br /> F:\EngineeringUWiNtams\MasterContMdWaster Contract Domments100700 - General Conditions REV 04 7.doc
<br /> i
<br />
|