r <br /> SECTION 00800 - SUPPLEMENTARY CONDITIONS TO THE <br /> GENERAL CONDITIONS <br /> SC-1 .00 Introduction <br /> These Supplementary Conditions amend or supplement the Standard General Conditions of the <br /> Construction Contract (No. 1910-8 , 1996 Edition) and other provisions of the Contract <br /> +� Documents as indicated below. All provisions , which are not so amended or supplemented , <br /> remain in full force and effect. <br /> r The terms used in these Supplementary Conditions will have the meanings indicated in the <br /> General Conditions . <br /> SC-1 .01 Defined Terms <br /> r <br /> SC-1 . 01 .A. 20 . Delete paragraph GC 1 . 01 .A. 20 in its entirety. <br /> r <br /> SC-2 . 05 Before Starting Construction <br /> SC-2. 05 . C. Delete paragraph GC 2. 05. 0 in its entirety and insert the following paragraph in its <br /> place: <br /> C . Evidence of Insurance: CONTRACTOR shall not commence work under this <br /> Contract until he has obtained all insurance required under Article 5 and such <br /> insurance has been delivered to the OWNER and approved by the OWNER, nor <br /> • shall the CONTRACTOR allow any Subcontractor to commence work on his <br /> subcontract until all similar insurance required of the Subcontractor has been so <br /> obtained and approved . All such insurance shall remain in effect until final <br /> r payment and at all times thereafter when CONTRACTOR may be correcting , <br /> removing or replacing defective Work in accordance with Article 13 . <br /> SC-2.06 Preconstruction Conference <br /> SC-2 . 06 Delete paragraph GC-2. 06.A in its entirety and insert the following paragraph in its <br /> place: <br /> r A. Immediately after awarding the contract, but before the CONTRACTOR begins <br /> work, the Engineer will call a preconstruction conference at a place the <br /> ENGINEER designates to establish an understanding among the parties as to <br /> 40 the work and to discuss schedules referred to in paragraph 2 . 05 . 13, procedures <br /> for handling Shop Drawings and other submittals, and maintaining required <br /> records. Utility companies and others as appropriate will be requested to attend <br /> r to discuss and coordinate work. <br /> SC-3.06 Coordination of Plans, Specifications, and Special Provisions <br /> r <br /> SC-3. 06 Add the following new paragraphs immediately after paragraph GC-3. 05: <br /> SC-3. 06 Coordination of Plans, Specifications, and Special Provisions <br /> A. In case of discrepancy, the governing order of the documents shall be as follows: <br /> 1 . Written Interpretations <br /> 2 . Addenda <br /> r 3 . Specifications <br /> 4 . Supplementary Conditions to the General Conditions <br /> 5 . General Conditions <br /> 6. Approved Shop Drawings <br /> 7. Drawings <br /> 8 . Referenced Standards . <br /> 00800-1 <br /> 00800 - Supplementary conditions REV 04-07.doc <br /> 00800 1 FdEngineefing\Capital Proje %9611-CR 512 Wdening19611 CR 512 PHASE IV\Contrac[ Dowmenls 00 - SWplem ry CoMkions REV 06-07.Coe <br />