14 . 06 Final inspection <br /> B . Review of Application and Acceptance <br /> A. Upon written notice from CONTRACTOR that <br /> the entire Work or an agreed portion thereof is 1 . If, on the basis of ENGINEER's <br /> complete , ENGINEER will promptly make a final observation of the Work during construction <br /> inspection with OWNER and CONTRACTOR and will and final inspection , and ENGINEER's review <br /> notify CONTRACTOR in writing of all particulars in of the final Application for Payment and <br /> which this inspection reveals that the Work is accompanying documentation as required by <br /> incomplete or defective. CONTRACTOR shall the Contract Documents , ENGINEER is <br /> immediately take such measures as are necessary to satisfied that the Work has been completed <br /> complete such Work or remedy such deficiencies . and CONTRACTOR' s other obligations under <br /> the Contract Documents have been fulfilled , <br /> 14 . 07 Final Payment ENGINEER will , within ten days after receipt of <br /> the final Application for Payment, indicate in <br /> A. Application for Payment writing ENGINEER's recommendation of <br /> payment and present the Application for <br /> 1 . After CONTRACTOR has , in the Payment to OWNER for payment. At the same <br /> opinion of ENGINEER , satisfactorily completed time ENGINEER will also give written notice to <br /> all corrections identified during the final OWNER and CONTRACTOR that the Work is <br /> inspection and has delivered , in accordance acceptable subject to the provisions of <br /> with the Contract Documents , all maintenance paragraph 14 . 09 . Otherwise , ENGINEER will <br /> and operating instructions , schedules , guaran- return the Application for Payment to <br /> tees, Bonds , certificates or other evidence of CONTRACTOR , indicating in writing the <br /> insurance certificates of inspection , marked-up reasons for refusing to recommend final <br /> record documents (as provided in paragraph payment, in which case CONTRACTOR shall <br /> 6 . 12) , and other documents , CONTRACTOR make the necessary corrections and resubmit <br /> may make application for final payment follow- the Application for Payment. <br /> ing the procedure for progress payments. <br /> C . Payment Becomes Due <br /> 2 . The final Application for Payment <br /> shall be accompanied (except as previously <br /> delivered) by: (i) all documentation called for in <br /> the Contract Documents , including but not <br /> limited to the evidence of insurance required by ren.e. rn �ner�d. ed by ENGINEER will beMicne due <br /> subparagraph 5 . 04 . 6 . 7 ; (ii) consent of the and , whes due, <br /> will be paid by OWNER to <br /> surety, if any, to final payment; and (iii) G <br /> complete and legally effective releases or <br /> waivers (satisfactory to OWNER) of all Lien 14 . 08 Final Completion Delayed <br /> rights arising out of or Liens filed in connection <br /> with the Work. A. If, through no fault of CONTRACTOR , final <br /> completion of the Work is significantly delayed , and if <br /> 3 . In lieu of the releases or waivers of ENGINEER so confirms , OWNER shall , upon receipt <br /> Liens specified in paragraph 14 . 07 .A. 2 and as of CONTRACTOR's final Application for Payment and <br /> approved by OWNER , CONTRACTOR may recommendation of ENGINEER, and without terminate <br /> furnish receipts or releases in full and an ing the Agreement, make payment of the balance due <br /> affidavit of CONTRACTOR that: (i) the releases for that portion of the Work fully completed and <br /> and receipts include all labor, services , accepted . If the remaining balance to be held by <br /> material , and equipment for which a Lien could OWNER for Work not fully completed or corrected is <br /> be filed ; and (ii) all payrolls, material and less than the retainage stipulated in the Agreement, <br /> equipment bills, and other indebtedness and if Bonds have been furnished as required in <br /> connected with the Work for which OWNER or paragraph 5 . 01 , the written consent of the surety to <br /> OWNER's property might in any way be the payment of the balance due for that portion of the <br /> responsible have been paid or otherwise satis- Work fully completed and accepted shall be submitted <br /> fied . If any Subcontractor or Supplier fails to by CONTRACTOR to ENGINEER with the Application <br /> furnish such a release or receipt in full , CON- for such payment. Such payment shall be made <br /> TRACTOR may furnish a Bond or other under the terms and conditions governing final <br /> collateral satisfactory to OWNER to indemnify payment, except that it shall not constitute a waiver of <br /> OWNER against any Lien . Claims. <br /> 00700 - General Conditions <br /> 00700 - 42 <br /> FAEngineeringTapital Projects10217-Powerline Rcad\Bid Documents100700 - General Conditions.doc <br />