Laserfiche WebLink
SECTION 01820 <br /> Post Final Inspection <br /> 1 . 1 GENERAL <br /> A . Approximately one year after Substantial Completion , the OWNER will make <br /> arrangements with the ENGINEER and the CONTRACTOR for a post final <br /> inspection and will send a written notice to said parties to inform them of the <br /> date and time of the inspection . <br /> B . Corrections of defective work noted by OWNER and ENGINEER shall comply <br /> with the applicable sections of Article 13 , General Conditions . <br /> C . After the inspection , the OWNER will inform the CONTRACTOR of any <br /> corrections required to release the performance and payment bonds . <br /> 01820 Post Final Inspection <br /> 01820- 1 <br /> F:\Engineering\Capital Projects\0217-Powerline Road\Bid Documents\01820 - Post Final Inspection.doc <br />