CHANGE ORDER NO . 010 — RECONCILIATION CHANGE ORDER
DATE OF ISSUANCE : January 6 , 2009 EFFECTIVE DATE : January 13 , 2009
OWNER : Indian River County
CONTRACTOR : Lucas Marine Construction , LLC
Contract : Main Relief canal Pollution control System
Project : No . 0113 COUNTY' s BID No . 2007066
ENGINEER : Indian River County CONSULTING ENGINEER : N/A
ormwater Division
The following reconciliations are made to the Final Contract Price :
1 . Description : Return five wall - mount davit crane base plates to manufacturer
( restocking fee ) .
Reason : The wall - mount davit crane base plates were not used due to conflicts with
other equipment .
Change in Contract Price : Increase = $ 1 , 508 . 00
Change in Contract Time : None
Attachments : Letter from Bruce G . Smith , Lucas Marine Construction , LLC to Keith
McCully , IRC , dated January 6 , 2009
2 , Description : Substitute Macarthur Palms for Sentry Palms .
Reason : The Sentry Palms were not readily available .
Change in Contract Price : Total Decrease = ($ 1 , 000 . 00 )
Change in Contract Time : None
Attachments : Email from Bruce G . Smith , Lucas Marine Construction , LLC to Keith
McCully , IRC , dated August 14 , 2008
3 , Description : Substitute Chinese Fan Palms for Ribbon Palms .
Reason : The Ribbon Palms were not readily available .
Change in Contract Price : Total Decrease = ($650 . 00 )
Change in Contract Time : None
Attachments : Email from Bruce G . Smith , Lucas Marine Construction , LLC to Keith
McCully , IRC , dated August 14 , 2008
4 . Description : Increase Bid Item 2 . 05 by 26 square yards .
Reason : The quantity of asphalt was increased due to City' s relocation of the access
driveway .
Change in Contract Price : Increase = 26 SY * $ 18 . 00/SY = $468 . 00
Attachments : None
5 . Description : Increase Bid Item 2 . 06 by 24 square yards .
Reason : The quantity of stabilized subgrade was increased due to City ' s relocation
of the access driveway .
Change Order No . 010 - Final
Change Order - Page 1 of 5
FAPublic WorksWeithM\Stormwater Projects\Main Relief Canal\Change Orders\Change Order No. 010 - Final Change
Order\Change Order No 010 - Final Change Order. doc Last revised 9/27/01
Change in Contract Price : Increase = 24 SY * $ 14 . 00/SY = $ 336 . 00
Attachments : None
6 , Description : Increase Bid Item 2 . 07 by 84 square yards .
Reason : The quantity of base course was increased due to City' s relocation of the
access driveway .
Change in Contract Price : Increase = 84 SY * $22 . 00/SY = $ 1 , 848 . 00
Attachments : None
7 , Description : Decrease lump sum Bid Item 2 . 09A ,
Reason : This amount is decreased because the Sediment Recovery Area slab-on -
grade was deleted from the Contract .
Change in Contract Price : Decrease = 156 . 77 SF * $ 7 . 50/SF = ( $ 1 , 175 . 78 )
Attachments : None
8 . Description : Decrease lump sum Bid Item 2 . 09B .
Reason : This amount is decreased because the Sediment Recovery Area reinforced
concrete walls were deleted from the Contract .
Change in Contract Price : Decrease = 8 CY * $ 850 . 00/CY = ( $6 , 800 . 00 )
Attachments : None
9 , Description : Delete two bollards that were to be installed at the Sediment Recovery
Area .
Reason : The Sediment Recovery Area was deleted from the Contract .
Change in Contract Price : Decrease = ($ 600 . 00 )
Attachments : Letter from Bruce G . Smith , Lucas Marine Construction , LLC to Keith
McCully , IRC , dated January 6 , 2009
10 . Description : Decrease Bid Item 2 . 10 by 634 square feet .
Reason : Concrete sidewalks were eliminated due to deletion of the Sedimentation
Recovery System from the Contract and the City' s relocation of the access
driveway .
Change in Contract Price : Decrease = 634 SF * $ 7 . 50/SF = ( $4 , 755 . 00 )
Attachments : None
11 . Description : Increase Bid Item 2 . 11 by 0 . 82 square feet .
Reason : The sedimentation pump equipment pad ( 36 . 38 SF ) was not constructed
because the sedimentation pumps were deleted from the Contract . The emergency
generator pad size was increased by 37 . 20 SF .
Change in Contract Price : Increase = [37 . 20 SF - 36 . 38 SF] * $20 . 00/SF = $ 16 . 40
Attachments : None
12 . Description : Decrease Bid Item 2 . 12 -A by 142 square feet .
Reason : This quantity of steel sheet piling was not used .
Change in Contract Price : Decrease = 142 SF * $ 38 . 00/SF = ($ 5 , 396 . 00 )
Attachments : None
Change Order No . 010 - Final
Change Order - Page 2 of 5
FAPublic Works\KeithM\Stormwater Projects\Main Relief Canal\Change Orders\Change Order No . 010 - Final Change
Order\Change Order No 010 - Final Change Order. doc Last revised 9/27/01
Monk
13 . Description : Decrease Bid Item 2 . 12- 13 by 218 . 75 square feet .
Reason : This quantity of steel sheet piling was not used .
Change in Contract Price : Decrease = 218 . 75 SF * $ 38 . 00/SF = ($ 8 , 312 . 50 )
Attachments : None
14 . Description : Decrease Bid Item 2 . 13 by 23 lineal feet .
Reason : This quantity of chain link fence material was not used .
Change in Contract Price : Decrease = 23 LF * $ 34 . 00/LF = ($ 782 . 00 )
Attachments : None
15 . Description : Delete Bid Item 2 . 16 by 107 square yards .
Reason : This quantity of Bahia sod was not used .
Change in Contract Price : Decrease = 107 SY * $ 3 . 00/SY = ($ 321 . 00 )
Attachments : None
16 . Description : Decrease Bid Item 2 . 18 for non -potable water pipe and associated
equipment that was not installed . ( Includes 77 lineal feet of 2 - 1 /2 " PVC pipe , one
spring rewind reel , 1 "x100 ' water hose , one fog nozzle , fittings , NPW sign and post ,
etc . )
Reason : These materials were not installed because the Sediment Recovery Area
was deleted from the Contract .
Change in Contract Price : Decrease = ($ 1 , 500 . 00 )
Attachments : Letter from Bruce G . Smith , Lucas Marine Construction , LLC to Keith
McCully , IRC , dated January 6 , 2009
17 . Description : Delete Bid Item 2 . 33 .
Reason : The sedimentation pump and motors were deleted from the Contract .
Change in Contract Price : Decrease = ( $2 , 500 . 00 )
Attachments : None
18 . Description : Increase Bid Item 3 . 01 by 10 . 44 cubic yards .
Reason : This quantity reinforced concrete was increased during construction . The
additional concrete was required for a protective cap over a steel sheet piling
headwall at the box culvert discharge and for additional concrete pedestals to
support the conveyor systems .
Change in Contract Price : Increase = 10 . 44 CY * $ 850 . 00/CY = $ 8 , 874 . 00
Attachments : None
19 . Description : Delete Bid Item 3 . 02 ,
Reason : This quantity of extra excavation was not required .
Change in Contract Price : Decrease = ($ 1 , 200 . 00 )
Attachments : None
20 . Description : Delete Bid Item 3 . 03 .
Reason : This quantity of extra imported fill material was not required .
Change in Contract Price : Decrease = ($2 , 000 . 00 )
Attachments : None
Change Order No . 010 - Final
Change Order - Page 3 of 5
FAPublic Works\KeithM\Stormwater Projects\Main Relief Canal\Change Orders\Change Order No . 010 - Final Change
Order\Change Order No 010 - Final Change Order.doc Last revised 9/27/01
21 . Description : Delete Bid Item 3 . 04 ,
Reason : This sheet piling was not used .
Change in Contract Price : Decrease = ($24 , 000 . 00 )
Attachments : None
22 . Description : Add three units to Bid Item 4 . 01 .
Reason : Revised site plan due to City's relocation of the access driveway .
Change in Contract Price : Increase = 18 * $ 12 . 95 = $233 . 10
Attachments : None
23 . Description : Decrease the unit price of Bid Item 4 . 03 by $ 500 . 00
Reason : Decrease the clear trunk height .
Change in Contract Price : Decrease = 10 * $ 500 = ( $ 5 , 000 . 00 )
Attachments : None
24 . Description : Add one unit to Bid Item 4 . 03 ,
Reason : Revised site plan due to City' s relocation of access driveway .
Change in Contract Price : Increase = $ 5 , 800 . 00
Attachments : None
25 . Description : Decrease Bid Item 4 . 07 by 807 square feet .
Reason : Revised site plan due to City' s relocation of the access driveway .
Change in Contract Price : Decrease = 807 SF * $ 3 . 25/SF = ($2 , 622 . 75 )
Attachments : None
26 . Description : The construction trailer with engineer' s office , telephone , new copy
machine , etc , was not supplied as required by Section 01590 of the contract
documents . Basis of cost : rental = $ 175 per month ; telephone and high speed
internet service = $ 150 per month ; new copy machine = $ 50 per month ; electrical
service = $ 100 per month ; bottled water cooler = $ 25 per month ; septic services =
$25 per month ; setup and takedown = $ 1 , 600 ; original contract time = 10 months .
Total = [ 10 * $ 525] + $ 1 , 600 = $ 6 , 850 . 00
Change in Contract Price : Decrease = ($ 6 , 850 . 00 )
Attachments : None
27 . Description : Three inch by five inch hard copies of construction photographs were
not provided as specified in Section 01380 .
Change in Contract Price : Decrease = 412 photos * $ 0 . 50/photo = ( $ 206 . 00 )
Attachments : None
Change Order No . 010 - Final
Change Order - Page 4 of 5
FAPublic Works\KeithM\Stormwater Projects\Main Relief Canal\Change Orders\Change Order No . 010 - Final Change
Order\Change Order No 010 - Final Change Order.doc Last revised 9/27/01
CHANGE IN CONTRACT PRICE :
Description Amount
Original Contract Price $ 3 , 3689799 . 60
Net Increase from previous Change Orders
No . 000 to 009 : $ 360 , 835 . 89
Contract Price prior to this Change Order: $ 3 , 729 , 635 . 49
Net Decrease of this Change Order: $ 56 , 587 . 53
Contract Price with all approved Change $ 3 , 6739047 . 96
Orders :
CHANGE IN CONTRACT TIMES
Description Time
Original Contract Time : (days or dates )
Substantial Completion : 270 days - 5/23/2008
Final Completion : 300 days = 6/22/2008
Net change from previous Change Orders
No . 000 to 009 :
Substantial Completion : 116 days
Final Completion : 116 days
Contract Time prior to this Change Order: (days or dates )
Substantial Completion : 393 days — 9/24/2008
Final Completion : 423 days — 10/23/2008
Net increase this Change Order: (days or dates )
Substantial Completion : -0 - days
Final Completion : -0 - days
Contract Time with all approved Change (days or dates )
Orders : w,
Substantial Completion : 393 days � V/24/2008
Final Completion : 1 423 days -- 1 .0/231008
ACCEP RECOMMENDED : ZAPPR ; ,
. ,
B By : '�
.40 A16
ONTRACTOR ( Signature) E GIN E (Signature) Wesley S . Da airman ,
Keith McCully, P . E . Indian Indian River County Commission
River County Stormwater
Engineer
( Name and Title )
Date : 1 Date : Date : January 20 2009
Change Order No . 010 - Final
Change Order - Page 5 of 5
FAIDublic Works\KeithM\Stormwater Projects\Main Relief Canal\Change Orders\Change Order No . 010 - Final Change
Order\Change Order No 010 - Final Change Order. doc Last revised 9/27/01
Marine Lucas Marine Construction , LLC
conisTaucTioni
January 6 , 2009
Attn : Mr . Keith McCully P . E .
Indian River Storm Water Division
437543 rd Ave .
Vero Beach , Fl . 32967
Reference : Indian River County Main Relief Pollution Control Project
" Change Orders"
Dear Mr. McCully :
Per our recent conversations pertaining to Reconciliation change order # 10 , Lucas Marine
Construction Submits the following for your review .
Item # 1 . The restocking fee for the wall mounted davits total cost =$ 1508 . 00
Item # 9 Lucas Marine offers a credit of $ 300 . 00 each x 2 =<$ 600 . 00>
Bollards were excluded from contract .
Item # 17 Lucas Marines offers a credit of = < $ 1500 . 00 >
Hose reel & appurtenances was deleted from contract
In closing, if I can be of further assistance to you, please do not hesitate to call me .
Your truly,
Bruce G . Smith
Project Manager
3130 SE Slater Street, Stuart, FL 34997 • (772) 286=5094 . ( 772) 286-1139 ( Fax)
1100 Shetter Ave . Ste , 101 , Jacksonville Beach , FL 32250 a (904) 2464017 • (904) 246-6018 ( Fax)