WORK ORDER NUMBER 3 -EM
SUPPORT ENGINEERING SERVICES FOR EGRET MARSH REGIONAL
STORMWA TER PARK FINAL REDESIGN AND CONSTRUCTION
This Work Order Number 3 -EM is entered into as of this 12th day of
February , 2008, pursuant to that certain Continuing Contract Agreement for
Professional Services entered into as of March 15, 2005 ("Agreement'), by and between
Indian River County, a political subdivision of the State of Florida ("COUNTY") and
Malcolm Pirnie, Inc. ("CONSULTANT').
The COUNTY has selected the CONSULTANT to perform the professional services
set forth on Attachment 1, attached to this Work Order and made part hereof by this
reference. The professional services will be performed by the CONSULTANT for the fee
schedule set forth in Attachment 2, attached to this Work Order and made a part hereof by
this reference. The CONSULTANT will perform the professional services within the
timeframe more particularly set forth in Attachment 3, attached to this Work Order and
made a part hereof by this reference, all in accordance with the terms and provisions set
forth in the Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in
any Work Order shall conflict with the terms of the Agreement and the terms of the
Agreement shall be deemed to be incorporated in each individual Work Order as if fully set
forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of
the date first written above.
CONSULT NT BOARD OF COUNTY -COMMISSIONERS
MALCO PIRNIE, INC. OF INDIAN FINER COMTY
SN
By: ! B L B a 4)0,91) > c/
S dfa`�,'�, *den,b4rman
' ^
Title Ti QCA%,._..... ,, r
Attest: J.K. Barton, Clerk of Court
BY
Deputy Clerk
In A. Baird, Countv Administrator
as to form and legal sufficiency:
4 � _
E. Fell, Assistant County Attorney
1
CADocuments and Settings\hurlburt\Local Settings\Temporary Internet Fi1es\OLK16A\Ma1co1m Pirnie Work Order 43 -EM - FINAL.doc
ATTACHMENT 9 to WORK ORDER NO, 3 -EM
ADDITIONAL ENGINEERING SERVICES FOR EGRET MARSH REGIONAL
STORMWATER PARK FINAL REDESIGN AND CONSTRUCTION
PROJECT SCOPE
The COUNTY is preparing an alternate design for the Egret Marsh Regional Stormwater
Park (Egret Marsh). The CONSULTANT shall assist the COUNTY in the alternate design
and subsequent construction by providing certain professional engineering services.
Specific tasks follow:
2. DESIGN SERVICES
Task No. 1 — COMPUTER DRAFTING SERVICES — provide computer aided drafting
(CAD) services for approximately seven civil and mechanical construction drawings.
Task No. 2 — STORMWATER MODELING — provide stormwater modeling services for the
post -construction site as required by Indian River County, including a final stormwater
modeling report.
Task No. 3 — ENGINEERING SERVICES — provide professional engineering services as
necessary to assist the COUNTY in its redesign efforts. These services will include, but
may not be limited to electrical engineering services.
Task No. 4 — SHOP DRAWING REVIEW AND RESPONSE TO CONTRACTOR'S
REQUEST FOR INFORMATION SUBMITTALS — provide structural and electrical
engineering services as necessary for shop drawing reviews and respond to contractor
requests for information during the construction period.
Task No. 5 — SITE VISITS DURING CONSTRUCTION AND ASSOCIATED MEMOS —
conduct up to 12 site visits to the project construction site to observe and review project
construction activities. Prepare and submit to the COUNTY, a memo summarizing
observations made during each site visit.
Task No. 6 — STARTUP SITE VISIT AND MEMO - conduct a site visit to the project
construction site at the time of scheduled startup to observe and review project activities.
Prepare and submit to the COUNTY, a memo summarizing observations made during the
startup site visit.
**END OF ATTACHMENT 1**
2
CADocuments and SettingsUmarino\Local SettingsUemporary Internet FileslContent.Outlook\BGUD33FE\Malcolm Pimie Work Order
#3 -EM - FINAL.doc
ATTACHMENT 2 to WORK ORDER NO. 3 -EM
ADDITIONAL ENGINEERING SERVICES FOR EGRET MARSH REGIONAL
STORMWA TER PARK FINAL REDESIGN AND CONSTRUCTION
1. COMPENSATION
The COUNTY agrees to pay and the CONSULTANT agrees to accept, a not -to -exceed fee
of $85,410.00 for services rendered according to Attachment 1 of this WORK ORDER.
2, PARTIAL PAYMENTS
The COUNTY shall make monthly partial payments to the CONSULTANT for all
authorized work pertaining directly to this project performed during the previous calendar
month. The CONSULTANT shall submit invoices monthly for services performed and
expenses incurred pursuant to this Agreement during the prior month.
The CONSULTANT shall submit duly certified invoices in duplicate to the Director of
the Public Works Department. For lump sum line items, the amount submitted shall be the
prorated amount due for all work performed to date under this phase, determined by
applying the percentage of the work completed as certified by the CONSULTANT, to the
total due for this phase of the work. For time and material line items, the amount
submitted shall be based on the actual hours worked and expenses incurred for the billing
period.
The amount of the partial payment due the CONSULTANT for the work performed
to date under these phases shall be an amount calculated in accordance with the previous
paragraph, less ten percent (10%) of the invoice amount thus determined, which shall be
withheld by the COUNTY as retainage, and less previous payments. Per F.S. 218.74(2)5
the COUNTY will pay approved invoices on or before the forty-fifth day after the COUNTY
receives the CONSULTANT's invoice.
Per F.S. 218.74(2), the ten percent (10%) retainage withheld shall be paid in full to
the CONSULTANT by the COUNTY, on or before the forty-fifth day after the date of final
acceptance of the Work by the Public Works Director.
**END OF ATTACHMENT 2**
3
CADocuments and SettingsUmarino\Local Settings\Temporary Internet Files\Content.Outlook\BGUD33FE\Malcolm Pimie Work Order
#3 -EM - FINAL.doc
ATTACHMENT 3 to WORK ORDER NO. 3 -EM
ADDITIONAL ENGINEERING SERVICES FOR EGRET MARSH REGIONAL
STORMWA TER PARK FINAL REDESIGN AND CONSTRUCTION
TIME FOR COMPLETION
The CONSULTANT's time -of -completion for engineering design services covered
by this Work Order depends on County staff's ability to get information to the
CONSULTANT. The engineering design portion of the work is anticipated to be complete
within 30 calendar days from the date the necessary information is transmitted to the
CONSULTANT by County staff. The CONSULTANT's time -of -completion for the
remainder of the work herein depends on the construction schedule determined by the
construction contract. Said construction schedule is anticipated to range from 300 to 360
calendar days.
**END OF ATTACHMENT 3**