-=AIA Document G701t" — 2001
Change Order
PROJECT (Name and address): CHANGE ORDER NUMBER: 001 OWNER:
Central Region W WTP Expansion, WIP DATE: July 06, 2006 ARCHITECT: E
No. 472- 169000-04503
355049TH ST, VERO BEACH, FL CONTRACTOR: E
329676303
TO CONTRACTOR (Name and address): ARCHITECT'S PROJECT NUMBER: IRC Bid No. 7029 FIELD: ❑
CONTRACT DATE: March 29, 2005 OTHER: ❑
CONTRACT FOR: Central Regon W WIP Expansion
WIP No. 472- 169000-04503
THE CONTRACT IS CHANGED AS FOLLOWS:
(Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives)
Additional work as directed (documentation attached)
The original Contract Sum was $ 4,477,000.00
The net change by previously authorized Change Orders $ 0.00
The Contract Sum prior to this Change Order was $ 4,477,000.00
The Contract Sum will be increased by this Change Order in the amount of $ 23,523.00
The new Contract Sum including this Change Order will be $ 4,500,523.00
The Contract Time will be increased by Thirty One ( 31 ) days.
The date of Substantial Completion as of the date of this Change Order therefore is July 31 , 2006
NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which
have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and
Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
Masteller & Moler, Inc. Indian River Industrial Contractors, Inc. Indian River County ' 1 "
Board of County eolialisssioners
ARCHITECT (Firm name) CONTRACTOR (Ft tt name) OWNER (Finrinar)ie . . . ..
<,..•.aa , Cf.
1655 27th Street, Suite 2 Post Office Bo 086 18402 5'"StreeYtNotth1$; •,
Vero Beach, Florida 32960 Jacksonville 32241 -3086 Veio 13�deb
ADDRESS ,, ,�— ADDRE DRESS
i��l�/J//?Z /
T i o c =c c
B�1 (Signature) —� BY (Signature) (SrgnaMrQ)".•• � ,�' ,t��`t ,•-
Frrl llt - AlzAder . OF, DE>r Mr. Steven H. Rea Arthur R .N@Utxel% ger ; Chairman
(Typed name) (Typed name) (Typed name) " 1 °" j
"7 I 1 -7 1 MOL August 22 2006
DATE DATE DATE
AIA Document G701TM — 2001 . Copyright m 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This Al e
Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA° Document, or any T
portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document
was produced by AIA software at 15:44:54 on 07/06/2006 under Order No.1000246449_1 which expires on 7/5/2007, and is not for resale.
User Notes: (1677068124)
}
CENTRAL REGIONAL WASTEWATER
TREATMENT PLANT EXPANSION
Item Amount
1 ( Relocate 4" and 8" Scum Lines $ 37010. 00
2 Clarifier / Filter Alignment $ 21983 . 00
3 130" Pipe / Duct bank Conflict $ 10 , 580 . 00
4 1Clarifier Influent Elevations $ 3 , 012 . 00
5 Pista Grit - Headworks Coating Repair 11 $ 950 . 00
6 lGrit Chute Revisions I $ 11850 . 00
7 New Chlorine Analyzer 1 $ 5 , 166 . 00
8 ( Hoffman PLC Enclosure 1 $ 21650 . 00
9 Site Grading & Drainage Modifications 1 $ 21 , 737 . 00
10 Electrical Issues $ 3564 . 00
11 1Electrical Value Engineering $ 11 , 878 . 40
12 1Deletion of the Scum Trough 1 $ 18 ; 900 . 00
13 lAdded Chlorine Eductor & Piping $ 750 . 00
14 1Deletion of Baffle Wall - Disinfection Basin $ 1 , 950 . 60
Total $ 23 , 523 . 00
Supporting documentation included in Exhibit "A"
EXHIBIT "A"
1 RELOCATE 4" AND 8" SCUM LINES Add $3,010 .00
LOCATION : 30" Secondary Clarifier Effluent to the Automatic Backwash Filter
The existing 4" Scum line and the existing 8" WAS line running between the new clarifier and the fitter
have a center line elevation of 12 . 80' . The new 30" effluent line has a centerline elevation of 13 .25' .
The existing lines were lowered below the 30" line utilizing mechanical joint 45 degree bends with
accessories . (4 each 4" MJ 45 and 4 each 8" MJ with megalugs and labor. )
2 CLARIFIER / FILTER ALIGNMENT Add $23983 .00
LOCATION : 30" Secondary Clarifier Effluent ( 30" x 16" Tee, Spool Piece, & 30" 90 Degree
Bend)
The east / west centerline dimension of the new Clarifier No. 3 and the new Backwash Filter are offset
approximately 20" . Referring to Drawing M7 , the makeup of the 30" Tee, the 30" spool piece, and the
30" 90 degree bend is approximately 64" . The Contract Drawings show the 30" pipe from the 90
degree bend at the Clarifier installed over to the center of the filter. Due to the 5'4" offset additional
fittings are required .
The 30" influent pipe (the 90 degree bend and embedded slab pipe at the filter) will be turned on a 45
degree angle out from the filter. ( 1 each 30" MJ 45 degree bend with megalugs and labor.)
3 30" PIPE / DUCTBANK CONFLICT Add $ 10, 580 .00
LOCATION : 30" Secondary Clarifier Effluent to the Automatic Backwash Filter
Existing electrical ductbank is located in the same location as the new 30" effluent from the new Filter.
The pipe will be relocated to avoid the conflict with the ductbank. (2 each 30" MJ 45 degree bends and
pipe relocation labor. )
4 CLARIFIER INFLUENT ELEVATIONS Add $39012.00
LOCATION : 20" Secondary Clarifier Influent
Pipe elevation problems : The new 20" clarifier influent pipe elevations are shown on the drawings at
differnet elevations . Due to the different elevations and the location of the existing pipe that the new
pipe ties into, the space needed to make the connection needs to be increased . Excavate more of the
existing pipe and cut the pipe to install the new piping . ( 1 each solid sleeve and labor. )
5 PISTA GRIT - HEADWORKS COATING REPAIR Add $950.00
The Special Coating installed in the Pista Grit Chamber ( installed on the original project) had
delaminated from the concrete. The old coating was removed , the damaged area was sandblasted and
new coating applied .
EXHIBIT "A"
6 GRIT CHUTE REVISIONS Add $ 1 ,850 .00
The grit chutes shown on the Contract Drawings were extended down closer to the dumpster and
rubber chutes were added at the ends of both as directed by the County .
7 NEW CHLORINE ANALYZER Add $59166 .00
As directed by the County, when the new Disinfection Basin was added no provision was made in the
documents to monitor the Chlorine Residual so as directed , the analyzer was added .
Hach CL 17 Total Chlorine Analyzer $3, 561 . 39
Little Giant Model C-07147-40 $ 141 .24
centrifugal submersible
low flow pump
115 VAC
18 feet cord included
Flexible hose, PVC pipe, pipe supports, fasteners & installation labor $1 , 463. 37
8 HOFFMAN PLC ENCLOSURE Add $29650 .00
On the instrumentation drawings, the New Main PLC # 2 Back Panel was not shown to be in it own
enclosure. This Panel required an enclosure in the electrical room .
9 SITE GRADING & DRAINAGE MODIFICATIONS Add $215737.00
Raise four (4) each electrical manholes $37428. 00
Concrete work, drilling & epoxying rebar dowels, formwork, concrete redi mix,
replacing aluminum covers, labor, and insurance & bond cost
Drainage pipe and grading $182309. 00
Aluminum grating, stainless steel anchors, 24" DR-18 pipe, concrete pads, rebar,
140 ft of 6" PVC pipe w/couplings, 180 ft of 8" PVC pipe w/couplings, 8" wye, 6" tee,
6" 45 degree bends, glue, PVC cleaner, excavation & backfill for pipe, equipment
cost plus fuel , sidewalk & stair rehab at the Disinfection Basin, regrading of
contours, labor, and insurance & bond cost
10 ELECTRICAL ISSUES Add $3, 564.00
Filters - Sheet E-16 shows a single point connection for the travelling bridge. There $ 1 ,416. 00
is additional electrical work required to include:
Pumps, beacons, receptacles, limit switches, term. At control panel
Head Works - Sheet E-12 shows an "existing" conduit from BSCP-2 to C-4. This $2 , 148. 00
conduit did not exist.
Route wiring to C-4/PLC 1/0 through an existing conduit from BSCP-2 to an existing
pullbox at northeast corner of Head Works then through a new 1 " conduit installed
underground south to C-4.
T EXHIBIT "A"
11 ELECTRICAL VALUE ENGINEERING Ded -$30, 778.40
Electrical Value Engineering and Deletion of Scum Trough
Revising the conduit and cable to the new influent pump -$9, 378. 40
Change feeder to new EFF-2 ( 100HP motor) from 6" aluminum conduit w/250MCM
Deletion of the cable try system -$2, 500. 00
Deletion of the scum trough att he disinfection basin -$ 187900. 00
12 ADDED CHLORINE EDUCTOR & PIPING Add $750 .00
As directed this chlorine eductor was added to add chlorine into the system at the Clarifiers .
13 DELETION OF BAFFLE WALL - DISINFECTION BASIN Ded -$ 1 ,950 .60
Since the new disinfection basin does not have Effluent pumps, the anti-vortex walls were not needed
and deleted .