HomeMy WebLinkAbout2008-111O+Da-0&
WORK ORDER NUMBER 12
This Work Order Number 12 is entered into as of this 8th day of April
2008 pursuant to that certain Continuing Contract Agreement for Professional Services entered
into as of April 6, 2004 ("Agreement"), and amended effective April 7, 2007 (as so amended, the
"Agreement"), by and between INDIAN RIVER COUNTY, a political subdivision of the State of
Florida ("COUNTY") and MASTELLER & MOLER, INC. ("CONSULTANT").
The COUNTY has selected the CONSULTANT to perform the professional services set
forth on Exhibit 1 (Scope of Work), attached to this Work Order and made part hereof by this
reference. The professional services will be performed by the CONSULTANT for the fee schedule
set forth in Exhibit 2 (Fee Schedule), attached to this Work Order and made a part hereof by this
reference. The CONSULTANT will perform the professional services within the timeframe more
particularly set forth in Exhibit 3 (Time Schedule), attached to this Work Order and made a part
hereof by this reference all in accordance with the terms and provisions set forth in the
Agreement. Pursuant to paragraph 1.4 of the Agreement, nothing contained in any Work Order
shall conflict with the terms of the Agreement and the terms of the Agreement shall be deemed to
be incorporated in each individual Work Order as if fully set forth herein.
IN WITNESS WHEREOF, the parties hereto have executed this Work Order as of the date
first written above.
CONSULTANT:
MAST LER & MOLER, INC.
By
ep en E. Moler, PE
Title: Vice President
Date:
BOARD OF COUNTY COM II'SSIONERt
OF INDIAN RIVER COUNTY.
q-ajn:dddra'L- Bowden, ft9lnnan
BCC Approved Date: Apri 1 S. c� 7
Attest: J. K. Baron, Clerk of Court
By: ( tzzv�
D puty Clerk
By:
.J -tea
E. Fell
and legal sufficiency:
Our File #0770
March 19, 2008
NON-EXCLUSSIVE PROFESSIONAL ENGINEERING AGREEMENT
CONTINUING CONSULTING SERVICES
EXHIBIT 1
Project Description
Masteller & Moler, Inc. is pleased to provide you with this proposal for providing civil engineering
services related to improvements to be made to Indian River County's Reuse Water System.
The Scope of Services described herein has been developed based upon numerous meetings
held with County Utilities Department staff. At said meetings, Masteller & Moler, Inc. was
advised as to the immediate goals that County Utilities desires to achieve relative to its reuse
water system. These goals and improvements are consistent with Indian River County's Reuse
Water Master Plan.
As a result, we have developed the following scope of work to be implemented to expand and
improve the overall reuse water system:
• Scope of Services
DESIGN SERVICES
Task A - Pumping and Storage Svstems
1) We shall develop design and construction plans for reuse water storage and pumping
facilities on the North County Wastewater Treatment Plant site. The proposed reuse water
ground storage tank shall have a volume of 3.0 MG as recommended by the Reuse Master
Plan. The new pumping facilities shall be designed within a pre -fabricated structure to
allow for improving delivery of reuse water to the Johns Island West and Red Stick golf
courses as well as to allow (in the future) for delivery of reuse water to the barrier island
Orchid Island, Windsor and Johns Island communities.
We shall provide a soils investigation and structural engineering design services to support
the design of the above described facilities. We shall also provide for electrical engineering
design services to support the design for supply of electrical power to the above described
facilities. We shall include a written performance specification stating the construction and
operational requirements for a scada system consistent with County standards.
The estimated construction cost for completion of the Task A improvements is
$ 21330,000.00.
Exhibit #1
3/20/2008
Page 2
Task B — Reuse Main Improvements — Under this Task we shall develop designs for
construction of new reuse main improvements.
As part of this Task, new reuse water mains and appurtenances will be designed to support
this project. Specifically, the following reuse main improvements will be designed:
1. 4200' lineal feet of existing 12" force main along CR510 from approximately the east
end of the bridge over the inter -coastal waterway to State Highway A -1-A shall be
replaced with 16" PVC and/or HDPE pipe. The east end will be designed to connect
to existing reuse mains on the west side of State Highway A -1-A. The west end will
be terminated with a valve and plug. The estimated construction cost for these
improvements is $ 5631500.00.
2. 2640' lineal feet of 16" reuse water main along Lateral "G" and Lateral "H" from 571h
Street to 53rd Street to connect to the existing reuse main extending west along 53rd
Street to the Waterway Village reuse water service connection. The design will
include a proposed directional drilled reuse main under the Indian River Farms Water
Control District's (IRFWCD's) North Relief Canal. The estimated construction cost for
these improvements is $ 366,400.00.
II. LAND SURVEYING SERVICES
Under this Task, land surveying services will be completed to support the design services
as described above in Section I - Tasks A & B. Specifically, the following land surveying
services will be provided:
A limited topographic survey of portions of the North WWTP site shall be performed
to support the design of the reuse storage and pumping improvements planned at
said site,
A route survey shall be performed along each of the proposed new reuse main
improvements limited and the CR 510 (East End of Bridge to A -1-A) replacement
main and the State Highway A-1 -A reuse main extension as described above,
A route survey shall be performed along Lateral "G" and Lateral "H" from 57'h Street
to 53'h Street including cross-sections of the existing North Relief Canal system.
III. SITE PLAN PERMITTING SERVICES NORTH PLANT SITE
In order that the reuse improvements to be designed under Task I may be constructed, we
shall make application for the following permits/approvals:
Task A (1) - North County Storage & Pumping Facilities
Indian River County Major Site Plan Approval
Indian River County Type "A" Stormwater Permit
Exhibit #1
3/19/2008
Page 3
IV. CONSTRUCTION SERVICES
Masteller & Moler, Inc. will provide assistance during bidding and periodic observation of
construction of the reuse improvements described above in Tasks I -A and I -B on an as -
needed basis to observe that construction is in reasonable compliance with the Contract
Plans and Permits. We will also attend meetings, review shop drawings and monthly pay
estimates from the Contractor. Following successful completion of the Contract work as
evidenced by as-builts and testing by the selected Contractor, we shall prepare Engineer's
Certificates confirming that the project improvements have been constructed in substantial
conformance with design plans and specifications.
CONSULTING
EXHIBIT 2
Method and Amount of Compensation
Our File #0770
March 19, 2008
Masteller & Moler, Inc. proposes to provide the Scope of Services described in "Attachment V based on
the following lump sum fees:
I. DESIGN SERVICES:
Provide for Engineering Design; Preparation of Specifications & Bid Documents
Utilizing Standard IRC Bid Documents. Forms, Documents & Drawings will be in
electronic Format Acad & MS Word
Fees: Task A (1) — North Plant Reuse Storage & Pumping Facilities
Engineering Design $ 128,850.00
Task B (1) — Reuse Main Improvements — CR 510 16" Reuse Main
Engineering Design $ 37,021.00
Task B (2) — Reuse Main Improvements — Lateral "G & H" 16" Reuse Main
Engineering Design $ 263014.00
II. SUB -CONSULTANT SPECIALIZED SERVICES
Land Surveying
$
203800.00
Soils Investigations
$
71200.00
Structural Engineering Design
$
5,500.00
Electrical Engineering Design
$
31200.00
Ill. SITE PLAN PERMITTING SERVICES (North Plant Site) $ 20,000.00
Exhibit 2
3/1912008
Page 2
IV. CONSTRUCTION SERVICES:
Assistance during Bidding, Bid Evaluation, Contract Award & Construction
Administration; Periodic Administration and Periodic Construction/Field Observation
Task A (1) — North Plant Reuse Storage & Pumping Facilities
Construction Services $ 40,309.00
Structural Construction Services $ 31200.00
Electrical Construction Services $ 17600.00
Task B (1) — Reuse Main Improvements — CR 51016" Reuse Main
Construction Services $ 16,172.00
Task B (2) — Reuse Main Improvements — Lateral "G& H" 16" Reuse Main
Construction Services $ 11,981.00
Note: There
is no construction related to
Design Task A.
In addition, these
fees may be
renegotiated
for any portion of the proposed
construction that
is not initiated within
two (2) years
following execution of this work authorization.
Printing and Reproduction
The County shall make direct payment to our office for the cost of printing project plan sheets required
for utility coordination and for copies of reports, drawings, specifications, bidding and construction
contract documents, and other pertinent items required by federal, state and local agencies from whom
approval of the project must be obtained, prospective bidders, material suppliers, and other interested
parties, but may charge only for the actual cost of proving such copies based on the following tabulation:
8'h" x 11" $ 0.25/sheet
11" x 17" $ 0.50/sheet
3%" diskette $ 5.00/each
CD $10.00/each
Application Fees
Blue line prints $ 0.333/SF
Reproducible sepias $ 0.75/SF
Reproducible mylars $ 4.40/SF
The County shall make direct payment to our office for the actual cost of all construction permit
application fees paid to jurisdictional agencies.
CONTINUING
• Time of Performance
EXHIBIT #3
SERVICES
Our File #0770
March 19, 2008
The estimated time frame for completion of services from the approval of this Work Order* is as follows:
MILESTONE
Engineering Design &
Preparation of Construction Plans
Submittal of Permit Applications
And Receipt of Permits
Project Construction Services
*COMPLETION DATE
August 29, 2008
November 29, 2008
June 30, 2009
*Dates are based on assumption that County Commission will approve this Work Authorization by
Tuesday, April 8, 2008.