HomeMy WebLinkAbout2005-031 Page 1 of 2
Board of County Commissioners 3
1810 25th Street O�"
Vero Beach, Florida 32960
Telephone: (772) 567-8000 FAX: 772-778-9391
Indian River County Project No . 0445
C . R. 512 Phase V, I-95 to 1301h Avenue (Willow St.)
WORK ORDER NO . 3 (Engineering)
FOR
PROFESSIONAL SURVEYING SERVICES AGREEMENT
FOR ANNUAL SURVEYING AND MAPPING SERVICES
WITH
Masteller, Moler & Reed, Inc.
In accordance with Contract No . 0390
This Work Order No . 3 is in accordance with the existing AGREEMENT dated September 23 , 2003 ,
and the extension thereof, between Masteller, Moler & Reed, Inc . (SURVEYOR) and Indian River
County (COUNTY) . This Work Order No . 3 amends the agreement as follows :
SECTION I — PROJECT LIMITS
County Road 512 , Phase V — the SURVEY LIMITS shall begin at the termination of County Road 512
Phase IV (East of I-95 ) and continue westerly on County Road 512 to 500 ' west of Willow Street ( 130th
Avenue)
SECTION II — SCOPE OF SERVICES
Masteller, Moler & Reed, Inc . (SURVEYOR) shall supply field and office Professional Land Survey
services to complete all task as outlined hereon in this work order No . 3 AND the attached (Exhibit
"A") Task description outline .
Brief:
The scope of services for this Work Order No . 3 , is the completion of all task as described in exhibit "A"
attached hereto, and preparation of a "Topographic" Survey for that portion of County Road 512 , Phase V
as mentioned in section I. The survey will be prepared in accordance with the Chapter 177 & Chapter
472 Florida Statutes and Chapter 61G17 (Florida Minimum Technical Standards) as set forth for these
types of surveys .
SECTION III - TIME FOR COMPLETION
An 80% submittal shall be delivered to the County for review and comments within 60 calendar days
from Notice To Proceed (NTP) . Final submittal will be delivered to the County within 30 calendar
days of receipt of the 80% submittal comments . Total 90 calendar days from NTP (Plus 80 % review
time by the COUNTY) .
SECTION IV — DELIVERABLES/WORK PRODUCT
a) Survey shall consist of a cover sheet, survey horizontal and vertical control sheet an subsequent
topographic sheets and details .
b) Deliverables for the 80% submittal will consist of paper copies of the survey for review and
comments .
c) Deliverables for the final ( 100%) submittal to the County will consist of a digital file and three
signed/sealed paper copies in 24" x 36 ' format . .
FAEngineering\Capital Projects\0390-Annual Survey Contracts 2003-2004\Masteller Moller and Reed\2004-2005\512 Ph 5 Topo-Design Jan
2005\ircwo 3- 512 phase 5 Topo-Design survey 1 -04 .doc
Page 2 of 2
(Section IV Cont. )
d) The SURVEYOR shall prepare its Work Product (Digital and paper versions) so that the
COUNTY or other consultants can readily use it for design and analysis of the area defined. It
shall contain all information necessary for a third-party surveyor to independently recreate and/or
utilize the survey work. It is acknowledged that all final products become property of Indian
River County and will be available for use by the public at large .
e) The SURVEYORS work product shall meet or exceed the minimum standards as defined by
sections II, III, IV and exhibit "A" attached hereto and made part of this agreement, or the
COUNTY will not approve the SURVEYORS request for payment.
SECTION V - COMPENSATION
The COUNTY agrees to pay , and the SURVEYOR agrees to accept, a fee for services rendered as
identified in Section II, III and IV of this Work Order No . 3 , for a Lump Sum of $49 , 930 . 00 .
All and/or any additional services not described hereon shall be pre -approved by the COUNTY .
Approved additional services shall be invoiced at the rates disclosed in the approved fee schedule
with the Surveyor for the contract year of October 1 , 2004 through September 30 , 2005 .
All invoicing and payments shall be accordance to original Professional Surveying Services
Agreement for Annual Surveying and Mapping Services, contract No . 0390 with the COUNTY and as
stated in sections III, IV and V hereon .
The AGREEMENT is hereby amended as specifically set forth herein . All remaining sections of the
AGREEMENT shall remain in full force and effect, and are incorporated herein .
IN WITNESS WHEREOF the parties hereto have executed these presents this 18th day
of Januar 005 .
MASTELLE$rM ER �D, INC . INDIAN RIVER COUNTY , FLORIDA
BOARD OF COUNTY COMMISSIONERS
BY : BY : � C.. S . ojL
THOMAS S . LOWTHER, Chairman
Title :
Approved by the BCC : January 18 2005
ATTEST :
Je
Cl � . �1 -
y _ .r
B :R
DEPUTYO GAO
JOPEPH rrR
TA M
14?Jovw-=�TF X
NVILILIAM G . LLINS , II
COUNTY ATTORNEY
FAEngineering\Capital Projects\0390-Annual Survey Contracts 2003 -2004\Masteller Moller and Reed\2004-2005\512 Ph 5 Topo-Design Jan
2005\ircwo 3 - 512 phase 5 Topo-Design survey 1 -04 .doc
jy • + Y2 " "7 x " s Rrs $ e +'"`"'�° ahY' 4` u i a'.. t ""1+ sr,,, ��6F k '� e
$ -t' t '` , 'tt
Y djT
5C6E
9
N
$. I'lls.
Route Survey and R/W Mapping - County Road 512 Phase V
I-95 West to Willow Street
Project Limits . 500 ' east of I-95 to 500 ' west of Willow St.
Task # Description Man -hours Rate Total
1 Project preparation and research, including locating plats , tax
maps, and r/w maps . Review documents to establish a well
defined plan to conduct survey. Prepare work orders and field
crew folders .
Professional Surveyor - Principal 1 $ 120 . 00 $ 120 .00
Survey Project Manager 1 $ 85 .00 $ 85 . 00
Project Surveyor 2 $ 75 . 00 $ 150 . 00
Clerical 4 $35 . 00 $ 140 . 00
Task Sub-total $495 . 00
2 Perform reconnaissance within project limits . Recover existing
monumentation to establish existing R/W lines, property lines,
section lines , DOT baselines, benchmarks and GPS control .
Professional Surveyor - Principal 2 $ 120 . 00 $240 . 00
Project Surveyor 4 $75 .00 $300 . 00
2-Man Field Crew 32 $90 .00 $2 , 880 . 00
Task Sub-total $3 ,420 .00
3 Perform tie-in of existing monumentation including State Plane
coordinates .
Professional Surveyor - Principal 2 $ 120 . 00 $240 . 00
Project Surveyor 2 $75 .00 $ 150 . 00
2-Man GPS Crew 8 $ 115 . 00 $920 . 00
Task Sub-total $ 1 ,310 . 00
4 Establish Survey baseline within project limits, including tie to
existing survey baseline for County Road Phase IV project .
Establish control points at a maximum of 500 foot intervals .
Professional Surveyor - Principal 3 $ 120 .00 $ 360 . 00
Project Surveyor 5 $75 . 00 $ 375 . 00
3 -Man Field Crew 40 $ 115 . 00 $45600 . 00
Task Sub-total $ 55335 . 00
Masteller, Moler Reed , Inc . 1 of 3 2205 14th Ave . , Vero Beach , FL
,". c ' Ts,.
a
f R
ami. ., s � ... . , . .. . r, fau a '+?�1e.... Akti.�s.�._ t _ . .8»..^:J.Y"Rr. .,, ; . , . .
s3 > '.,
Route Survey and R/W Mapping - County Road 512 Phase V
I-95 West to Willow Street
Task # Description Man -hours Rate Total
5 Perform Vertical Bench Loop to establish elevations based on the
North American Vertical Datum of 1988 . Calculate, verify and
adjust Bench Loop as necessary . Establish Benchmarks at a
maximum of 1200 foot intervals .
Professional Surveyor - Principal 2 $ 120 . 00 $240 . 00
Professional Surveyor - P . S .M . 4 $95 . 00 $380 . 00
3 -Man Field Crew 32 $ 115 . 00 $ 33680 . 00
Task Sub-total $4, 300 . 00
6 Reference established Baseline at a maximum of 1000 foot
intervals with a minimum of 3 reference monuments . Establish
NAVD 1988 elevations on same .
Survey Project Manager 6 $ 85 . 00 $ 510 . 00
Project Surveyor 5 $75 . 00 $375 . 00
3 -Man Field Crew 40 $ 115 . 00 $4,600 . 00
Task Sub-total $ 5 ,485 . 00
7 Prepare Horizontal and Vertical Control sheets with Baseline
establishment, reference points and project benchmarks .
Professional Surveyor - Principal 3 $ 120 . 00 $ 360 .00
Project Surveyor 4 $ 75 . 00 $ 300 .00
Survey CAD Operator 32 $65 . 00 $29080 . 00
Task Sub-total $2 , 740 . 00
8 Perform topographic survey of Project limits and 200' beyond
proposed R/W including pertinent vegetation/trees, water bodies
and drainage features . Survey will also include 250' on side
streets , front building corners, visible utitlies, driveways etc .
Professional Surveyor - Principal 3 $ 120 . 00 $360 . 00
Project Surveyor 8 $ 75 . 00 $600 . 00
2-Man Field Crew 80 $ 90 . 00 $7 ,200 . 00
Task Sub-total $ 8 , 160 . 00
Masteller, Moler Reed , Inc. 2 of 3 2205 14th Ave . , Vero Beach , FL
17
rk9 4x' F
, . � . « .... _ s.e ...P . ,.�. ,_ . �.ra'.,. _,.. ,+..w.. .. _ ,_..^n.n ':'. ..�" ac' �' "a!l`C :diad ✓. R, ,.... 4 r . s
N. _ °
Route Survey and R/W Mapping - County Road 512 Phase V
I-95 West to Willow Street
Task # Description Man -hours Rate Total
9 Perform x-sections at a minimum of 100 foot intervals and
high/low areas throughout project. Profile centerline of side
streets 500 ' beyond proposed R/W.
Professional Surveyor - Principal 4 $ 120 . 00 $480 . 00
Project Surveyor 15 $ 75 .00 $ 1 , 125 . 00
2-Man Field Crew 120 $90 . 00 $ 109800 . 00
Task Sub-total $ 12 ,405 . 00
10 Prepare Base Plan Sheets of above described topography, features,
baseline, R/W, x-sections, and adjacent parcel information
throughout the project limts and 500 ' beyond.
Professional Surveyor - Principal 4 $ 120 .00 $480 . 00
Project Surveyor 8 $75 .00 $ 600 . 00
Survey CAD Operator 80 $ 65 . 00 $59200 . 00
Task Sub-total $ 6,280 . 00
Time of Completion and Deliverables shall be in accordence
with Work Order No : 3 with the COUNTY.
Total Cost $499930 .00
Masteller, Moler Reed , Inc. 3 of 3 2205 14th Ave . , Vero Beach , FL