HomeMy WebLinkAbout2009-227 IRC Work Order #11 ��
County Road 512 Ph . 4 — R/W monumentation
Page 1 of 1
r
•
Board of County Commissioners
Administration - Building A (South)
1801 27th Street
Vero Beach, Florida 32960
Telephone : (772) 567 - 8000 FAX : 772-778 -9391
Project ,
CR512 , Phase IV Roadway Improvements
Final Right- of-Way Mapping Project
IRC Project 9611 B
WORK ORDER NO . 11 ( Engineering /Surveying )
FOR
PROFESSIONAL SERVICES AGREEMENT
ANNUAL SURVEYING and MAPPING/GIS SERVICES
WITH
Masteller , Moler , Reed & Taylor , Inc .
In accordance with Contract No , 0725 2007 -2009
This Work Order No . 11 is in accordance with the existing AGREEMENT dated November 61"
2007 between Masteller , Moler , Reed & Taylor , Inc . ( SURVEYOR ) and Indian River County
( COUNTY) . This Work Order No . 11 amends the agreement as follows :
SECTION I — PROJECT LIMITS
This Work Order No . 11 is for the SURVEYOR to perform surveying services in connection with
the Right of Way Mapping of County Road 512 , Phase IV Roadway Improvements whose limits
range from Interstate 95 ( Sta . 35+ 00 ) to 1 , 000 feet west of County Road 510 ( Sta . 152 + 00
&
commencement point for existing Phase III R/W ) , all lying in Indian River County , Florida .
Length is approximately 13 , 500 feet ( 2 . 6 miles ) , limits include all properties associated with the
construction project .
SECTION II - SCOPE OF SERVICES
As agreed upon between Masteller , Moler , Reed & Taylor , Inc . and Indian River County , the
SURVEYOR shall provide Professional Land Surveying services to complete all tasks as
outlined in this Work Order No . 11 described as follows :
i . Project initiation , including review of existing files and field notes , preparation of work
orders and field crew folders .
2 . Project research including compilation of deeds , legal description and right of way
purchases and takings .
3 . Research and review property tax records for adjacent properties as necessary .
Depict provided documentation and current owner on Right of Way Map .
4 . Perform reconnaissance within the project limits . Recover existing monumentation
to establish existing R/W lines , property lines , etc . Perform tie - in of existing
monumentation including State Plane coordinates .
f:\public works\engineering division projects\0911b cr512 phase 4 row mapping ( mmr&t )\survey\work
orders\wo\0725_irc—wol1e_cr512_ph4_rw_mapping 9-8-09 . doc
IRC Work Order #11
County Road 512 Ph. 4 - R/W monumentation
Page 2 of 9
5. Set Permanent Reference Monuments along the Right of Way at all changes in
direction , including all Points of Curvature and Tangency . Provide State Plane
Coordinate values on all monumentation set . PRM ' s shall be an iron rod and disk
stamped as agreed and encased in a 4" by 4" concrete monument and shall be
placed at a maximum of 1000 feet apart .
6 . Set Permanent Reference Monuments along related project stormwater pond
properties as applicable . PRM 's shall be an iron rod and disk stamped as agreed
and encased in a 4" by 4" concrete monument and shall be placed at a maximum of
1 , 000 feet apart .
7. Monument all Permanent Control Points ( PCP's) along the baseline at all changes in
direction , including all Points of Curvature and Tangency . Provide State Plane
Coordinate values on all baseline control points . PCP 's shall be a Parker Kaylon nail
and tab or a 4" by 4" concrete monument stamped as agreed and shall be placed at
a maximum of 1 , 000 feet apart .
8 . Prepare Right of Way Map to depict all set or found monumentation and current title
work as applicable . Map shall adhere to Indian River County Right of Way Map
checklist. Provide copies for review and comment.
9 . Address comments and prepare mylars and other deliverables as required .
10 . Project (as a minimum ) shall adhere to attached Exhibit A " Proposal " and Right-of-
Way Map "Checklist" Exhibit B .
SECTION III — TIME FOR COMPLETION & DELIVERABLES/WORK PRODUCT
1 . Project shall be completed as follows .
a. Time of 90% PRELIMINARY review submittal shall be 90 calendar Days from
notice to proceed .
b . Time of FINAL project completion shall be within 30 calendar days of receipt of
the COUNTY review comments .
2 . Deliverables -The SURVEYOR shall provide the COUNTY :
a . PRELIMINARY REVIEW . 90% product for COUNTY review and comments . One
( 1 ) paper "hardcopy" and DWF formatted digital file . COUNTY shall strive to
provide review comments within 30 calendar days of preliminary submittal .
b. FINAL two (2) paper " hardcopy" signed and sealed sets and one ( 1 ) signed and
sealed MYLAR sets in adequate recording fashion ( I . E . Borders ) . Sheeted and
model space ( as applicable ) AutoCad drawing file and PDF and DWF formats on
CD .
c. Survey set/sheets shall include a cover sheet with location sketch , survey
certifications , and related title and project number ; a survey
notes/legend/abbreviation sheet , survey horizontal control sheet(s ) , right-of- way
plan view sheets and/or as indicated in the COUNTY supplied Right- of-Way map
"checklist" .
d . Work Product and digital versions are to prepared and submitted so that the
COUNTY or other consultants can readily use it for the design and analysis of
the area, as defined . It shall contain all information necessary for third-party
surveyor to independently recreate and/or utilize the survey work . It is
acknowledged all final products become property of COUNTY and will be
available for use by the public at large .
e . The SURVEYOR ' S work product shall meet or exceed the minimum standards
as defined by Sections II , III and IV or the COUNTY will not approve the
SURVEYOR' S request for payment.
MEMMONNOM
IRC Work Order #11
County Road 512 Ph . 4 — R/W monumentation
Page 3 of 9
SECTION IV — COMPENSATION
The COUNTY agrees to pay, and the SURVEYOR agrees to accept , for the above described
services rendered as identified in Sections I , II , and III of this Work Order No . 11 for a total lump
sum fee of $32 , 700 . 00 .
All and/or any additional services not described hereon shall be pre - approved by the
COUNTY. Approved additional services shall be invoiced at the rates disclosed in the
approved fee schedule with the SURVEYOR for the contract year (s ) of November 6th , 2007
through November 5'h , 2009 .
All invoicing shall include project identification , Work Order No . (WO 11 ) , Contract Number
0725 , itemize man - hours and materials expended to complete the scope of services . Payments
shall be in accordance with the original Professional Surveying and Mapping/GIS Services
Agreement, contract No : 0725 with the COUNTY and as stated in Section II , III and IV hereon .
Remainder of page left blank intentionally
IRC Work Order #11
County Road 512 Ph. 4 — R/W monumentation
Page 4 of 9
The AGREEMENT is hereby amended as specifically set forth herein . All remaining sections of
the AGREEMENT shall remain in full force and effect, and are incorporated herein .
IN WITNESS WHEREOF the parties hereto have executed these presents this 8th day
of Ste__ 2009 :
OWNER Masteller, Moler, Reed & Taylor, Inc .
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY, FLORIDA
(Sjodna ure) (Sig ature)
Wesley; S: Davis, Chairman
(Printed name and title)
Masteller, Moler, Reed & Taylor, Inc .
Approved by BCC September 8 , 2009
ATTEST. Witnessed by :
Jeffrey K. Barton, Clerk of Circuit Court
1:' ,C, k
eput Clerk (Signature)
Approved as to Form and Legal ufficiency :
tJ i Iz ! e I° / a S s-e,
William G . ollins 11 , COUNTY Attorney (Printed name)
i
eph gird , COUNTY Administrator
IRC Work Order #11
County Road 512 Ph . 4 — R/W monumentation
Page 5 of 9
Exhibit " A"
Proposal
Masteller, Moler, Reed $ Taylor, Inc.
1655 27th Street, Suite 2
Vero Beach , FL 32960
Phone : 772-564-8050
M
Fax: 772-794-0647 e-mail : mmrpsm@bellsouth . net
M �
AGREEMENT FOR PROFESSIONAL SERVICES
PROJECT: County Road 512 Phase IV RW Map PHONE: Work - ( 772) 567-8000
CLIENT NAME: Michael O'Brien PHONE: Fax - (772) 778-9391
SITE ADDRESS: County Road 512 MAILING ADDRESS: 1801 27th Street
Sebastian , FL 32958 Vero Beach , FL 32960
Hereby requests and authorizes the following services:
Perform surveying services in connection with the Right of Way Mapping of County Road 512 Phase 4 . County Road 512
Roadway Improvements whose limits range from Interstate 95 (Sta . 35+00 ) to 1000 feet west of County Road 510 (Sta .
152+00 8 commencement point for existing Phase 3 R/W) , and also 101st Avenue extension from County 512
to
intersection with 102nd Terrace, all lying in Indian River County, Florida. ( 13, 500 LF ). Limits include
all properties
associated with the construction project. Project (as a minimum ) shall adhere to Indian River Right-of-Way Map "Checklist"
and shall include the following Scope of Services:
1 . Project initiation, including review of existing files and field notes, preparation of work orders and field crew
folders .
2. Project research including compilation of deeds, legal description and right of way purchases and takings.
3. Research and review property tax records for adjacent properties as necessary. Depict provided
documentation and current owner on Right of Way Map.
4. Perform reconnaissance within the project limits. Recover existing monumentation to establish existing R/W
lines, property lines , etc. Perform tie-in of existing monumentation including State Plane coordinates.
5. Set Permanent Reference Monuments along the Right of Way at all changes in direction , including all Points
of Curvature and Tangency. Provide State Plane Coordinate values on all monumentation set. PRM's shall be
an iron rod and disk stamped as agreed and encased in a 4" by 4" concrete monument and shall be placed at
a maximum of 1000 feet apart.
6. Set Permanent Reference Monuments along related project stormwater pond properties as applicable . PRM 's
shall be an iron rod and disk stamped as agreed and encased in a 4" by 4" concrete monument and shall be
placed at a maximum of 1000 feet apart.
7. Monument all Permanent Control Points (PCP's) along the baseline at all changes in direction , including all
Points of Curvature and Tangency. Provide State Plane Coordinate values on all baseline control points .
PCP's shall be a Parker Kaylon nail and tab or a 4" by 4" concrete monument stamped as agreed and shall be
placed at a maximum of 1000 feet apart.
8 . Prepare Right of Way Map to depict all set or found monumentation and current title work as applicable. Map
shall adhere to Indian River County Right of Way Map checklist. Provide copies for review and comment.
9 . Address comments and prepare mylars and other deliverables as required.
We propose to perform the above described scope of services for a lump sum fee of $ 32, 700.00.
Upon your verbal authorization for this survey, we order research materials and set up your job file. In the event of a
cancell and in order to cover our costs, you will be billed for all work/expenses incurred up to the date of cancellation ,
inclu ' g co is to close out your file. Additional charges may also apply for research and office work and expenses
ne ssaryt resolve problem wit your legal description, conflicts with neighboring legal descriptions, and/or
di repanc' s du adver u , naccurate or missing information.
L 8/1912009
a ylor, President Date
Masteller, Moler, Reed 8 Ta o , Inc.
PT P/Contracts/2859. doc
IRC Work Order #11
County Road 512 Ph . 4 — R/W monumentation
Page 6 of 9
EXHIBIT "A " - MAN-HOUR ESTIMATE
County Road 512 Phase IV R/W Monumentation Map
Interstate 95 to West of County Road 510
Task Description Hours Rate Total
Project initiation , including review of existing files and field notes,
1 , 2 , 3 preparation of work orders and field crew folders. Project research
including compilation of deeds, legal description and right of way
purchases and takings.
Project Manager - P . S .M . 8 $ 115 .00 $920 . 00
Field Operations Supervisor 3 $95 .00 $285 .00
Clerical 12 $45 .00 $540 . 00
Task Sub-total $ 1 , 745 . 00
Perform reconnaissance within new project limits. Recover existing
4 monumentation to establish existing R/W lines, property lines, etc.
Perform tie-in of existing monumentation including State Plane
coordinates.
Project Manager - P. S . M. 6 $ 115 . 00 $690 . 00
Field Operations Supervisor 6 $95 .00 $570 .00
2-Man Field Crew 48 $ 115 .00 $5 , 520 . 00
Task Sub-total $6 , 780 . 00
Set Permanent Reference Monuments along the Right of Way at all
changes in direction , including all Points of Curvature and Tangency.
5 Provide State Plane Coordinate values on all monumentation set .
PRM's shall be an iron rod and disk stamped as agreed and encased
in a 4" by 4" concrete monument and shall be placed at a maximum
of 1000 feet apart .
Project Manager - P . S . M. 8 $ 115 . 00 $920 . 00
Field Operations Supervisor 8 $95 .00 $760 . 00
3-Man Field Crew 56 $ 130 .00 $7,280 . 00
Monuments 65 $ 11 .00 $715 . 00
Task Sub-total $9 , 675 . 00
Set Permanent Reference Monuments along related project
6 properties as applicable. PRM's shall be an iron rod and disk
stamped as agreed and encased in a 4" by 4" concrete monument
and shall be placed at a maximum of 1000 feet apart.
Project Manager - P . S . M . 3 $ 115 .00 $345 . 00
Field Operations Supervisor 4 $95 .00 $380 .00
3-Man Field Crew 16 $ 130 .00 $2 , 080 . 00
Monuments 15 $ 11 .00 $ 165 . 00
Task Sub-total $25970 . 00
IRC Work Order #11
County Road 512 Ph . 4 — R/W monumentation
Page 7 of 9
EXHIBIT "A " - MAN-HOUR ESTIMATE
County Road 512 Phase IV R/W Monumentation Map
Interstate 95 to West of County Road 510
Task Description Hours Rate Total
Monument Permanent Control Points ( PCP 's) along the baseline at
7 all changes in direction , including all Points of Curvature and
Tangency. Provide State Plane Coordinate values on all baseline
control points. PCP's shall be a Parker Kaylon nail and tab stamped
as agreed and shall be placed at a maximum of 1000 feet apart .
Project Manager - P. S . M. 4 $ 115 .00 $460 . 00
Field Operations Supervisor 5 $95 . 00 $475 . 00
3-Man Field Crew 24 $ 130 .00 $33120 . 00
Task Sub-total $4 , 055 . 00
Prepare Right of Way Map to depict all set or found monumentation
and current and original right of way lines as applicable. Map shall
8 , 9 adhere to attached Right of Way Map checklist (Exhibit "B"). Provide
copies for review and comment. Address comments and prepare
mylars as required .
Senior Survey Technician - CADD 60 $85 . 00 $55100 .00
Project Manager - P . S . M. 12 $ 115 . 00 $ 1 ,380 . 00
Mylars 20 $25 . 00 $500 . 00
Printing - (square feet) 750 $0 .30 $225 . 00
Clerical 6 $45 .00 $270 .00
Task Sub-total $7 ,475 . 00
$32 , 700 .00
IRC Work Order #11
County Road 512 Ph . 4 — R/W monumentation
Page 8 of 9
EXHIBIT " B "
CR512 Phase 4
INDIAN RIVER COUNTY
RIGHT OF WAY MAP CHECKLIST
All Right-of-way projects shall adhere to Chapter 177 & 4725 F. S. and Chapter 61G17,
F . A. C. as minimum and be certified as such .
R/W Maps shall be prepared/submitted in the form of a certified R/W Map will all
applicable certifications and criteria met.
A Copy of this check list is to be provided to the county with all submittals . The check list items
shall be individually noted as complete, pending etc with a note explaining why the item is not
competed.
1 . Cover sheet/Key sheet . (To be supplied by IRC in DWG . )
2 . Survey notes and report sheet .
3 . Key sheet ( s )
4 . Survey Control sheet .
5 . Subsequent R/W map sheets .
6 . Supply a Box or area for county acceptance and/or certification .
7 . Title Box of each sheet must contain :
a . County
b . State Road and/or County Road Number
c . Designed , drawn and checked by ( use names or initials ) & date
d . Scale
e . Field Book References
f . Sheet Numbers to be in numerical order ( 1 , 21 33 4 , etc . ) NOT ( 1 , 1 Al 1 B , 2 , etc
. )
8 . Any notes necessary to set out the type and/or purpose of the map shall be shown .
9 . Provide in survey notes - all relevant resources to prepare the Right- of-Way map .
10 . Show pertinent dimensions and bearings in the following fashion as the case may be :
a . Plat — ( P)
b . Computed — ( C)
c . Field — ( F)
d . Deed ( D)
11 . Table of Ownerships shall show :
a. Parcel Number
b . Recording Data
12 . Show stations and offsets to all Right of Way Breaks , bends , PC' s , PT's , block corners (per plat) .
13 . Show stations , deflection (or bearing) of all intersecting section , 1/4 section lines to baseline ( either
field or calculated as applicable) .
14 . Show monumented baselines and all references thereto .
15 . Verify that computed distances and bearings are supported by field measurements .
16 . Verify and/or monument significant elements of Baseline alignment shown . ( i . e . curves , bearings
and P . I . Stations)
17 . Ensure that significant elements of all curves are shown and are correct. Also show curve data on
all sheets where they appear.
18 . Provide stations on the controlling baseline at the beginning , ending of R/W Project , 500 ' intervals ,
all bends , PC 's , PT's , PI 's .
19 . Stationing in field minimum 500 ' beyond beginning and ending of project.
20 . Baseline (equate to intersecting State or County Jobs by Station and job number when available)
as available .
IRC Work Order #11
County Road 512 Ph . 4 — R/W monumentation
Page 9 of 9
21 . Projects shall be in NAD83/90 State plane coordinate system and bearings reference shall be
shown and must be clearly stated . Values shall be place on key baseline monumentation .
22 . County/State lines
23 . Section
24 . Township
25 . Range
26 . Government Lots , Grants , etc .
27 . Delineate positions or alignments of all Sections and 1/4 Sections ( lines & corners) used in the
course of the survey OR intersecting with project baseline AND Rights- of Way lines . Station and
deflections shall be provided at all positions .
28 . Certified Corner reports of all Section and Y4 corners used in the course of survey shall be
completed and/or updated and recorded with DEP .
29 . City Limits by Name & Symbol ; Name of City, if job entirely within city limits but does not cross- city
limits .
30 . Land and Subdivision Ties (angles and/or, bearings & distances)
31 . Subdivision name and limits
32 . Plat Book and page
33 . Lots and Blocks
34 . Lot and Street dimensions ( plat or document of record ) .
35 . Show all original plat and R/W lines of record , if different from present time , with dashed lines and
notation of the previous R/W documentation or references .
36 . Show/plot all Murphy Reservations and/or release lines ( including document of record ) via graphic
or dimension which ever is obtainable .
37 . Show names of subdivision streets , plat book and page recording — also , show Lot and Block
number and Dimensions , Exceptions , Easements , and Vacated portions .
38 . When property lines break the Right of Way on curve , show tangent bearings or chord bearings .
39 . Show any replat of a subdivision — show old subdivision when necessary to clear up former
acquisition or old title references — use system of dashed lines , dotted figures , etc. , with ties shown
and name and plat book reference indicated
40 . Stations and Angle Ties to ALL Existing Major and Minor Side Streets ( Public Road R/W) as
surveyed and/or calculated .
41 . Show field located P . R . M . /major property corner or parcel ties by station/offset to baseline/control
line .
42 . Current Street , County or State Road names and historical names are to be provided .
43 . Any buildings within 25 feet of proposed R/W line shall be dimensioned to R/W line . If proposed
R/W line is unknown , obtain buildings within +/- 25' of existing R/W . Locations of buildings and
large structures can be obtained from field and/or photographic / planimetric methods , note shall be
placed on plan as to origin .
44 . Show and identify all easements within , along or abutting the Right-of-Way or affected property on
detail Maps by width , use and ownership (where applicable) .
45 . Monumentation shall be a standard 4" x 4" ( PRM) concrete monument with Indian River County
Disc. All Disc are to be stamped Right- of-Way (or abbreviation ) and with the surveyors LB or
License Number
46 . Permanent Control Points ( PCP) shall be a standard PK nail (or substitute) with an Indian River
County Disc. All Disc are to be stamped Base- Line or reference line (or abbreviation) as applicable
and with the surveyors LB or License Number
47 . Any other items as to meet the goals and objectives established by the County.