HomeMy WebLinkAbout2007-137 Indian River Co. Approved Date ® Administration Legal IA Document G701TM — 2001 DBudget— epartment Risk Mana ment Change Order PROJECT (Name and address): CHANGE ORDER NUMBER: 077 OWNER: New County Administration Building DATE: April 17, 2007 ARCHITECT: Lying Between the Main Relief Canal to Ej the North, the Lateral D Canal on the CONTRACTOR: Sounth and East and 20th Avenue to the West FIELD: ❑ TO CONTRACTOR (Name and address): ARCHITECT'S PROJECT NUMBER: 2102 OTHER: ❑ Turner Construction Company CONTRACT DATE: (Amendment # 2) August 23, 2005 800 N. Magnolia Avenue CONTRACT FOR: Guaranteed Maximum Price - Orlando, Florida 32803 Construction Manager at Risk THE CONTRACT IS CHANGED AS FOLLOWS: (Include, where applicable, any undisputed amount attributable to previously executed Construction Change Directives) Reference Description Amount SECTION I COR 091 Modifications to Building 2 for New Conference Room and CCD-021/PCO 103-Conference Room 2. 1 -501, Production 1 .2-704 & Computer Room L2-302 & Computer Room 1 .2-302 585, 134 COR 093 Modify Scope of Existing Manhole Extensions per CCD-01 1 $ 19,438 COR 095 Modify Revise Elevator Machine Rooms to Meet Revised Codes CCD-021 and CCD-026 $42.511 COR 096 Architecture] Revisions and Miscellaneous Carpet Revisions. $44,071 COR 097 Modify Drainage at Bridge Approach at East End of 27th St. $ 14, 102 COR 102 Revise Design in Commission Chambers. $26,640 COR 103 Miscellaneous Site Revisions and Expedite Fixture Delivery $ 12,522 Total $244,418 Approval of this SECTION I of this Change Order will not change the GMP but will decrease the Owner's Contingency by $244,418. SECTION 2 ADDITIONAL COSTS : Modifications to Electrical, Data and Communications Systems to accommodate Owner Requirements for new configurations resulting from installation of furnishings, more refined IT power sources, and support infrastructure for Audio Visual systems. $841 .588 Other known additional cost items which are not-to-exceed expenses but which are well scoped include the following: Add sidewalk and steps. $ 32 ,000 Revise Atrium Drywall and Koral Kast $ 10,000 Add Coaxial Cable System for Cable TV $ 85,000 Misc. Interior Revisions $ 25,000 Misc. Exterior Revisions $ 25,000 Subtotal $ 177,000 Approval of this SECTION 2 of this Change Order will increase the GMP by $956,661 and will decrease the Owner' s Contingency by $61 ,927. Grand Total $ 1 ,263,006 The original Guaranteed Maximum Price was $ 33.086,442.00 The net change by previously authorized Change Orders $ (6. 190,487.00) The Guaranteed Maximum Price prior to this Change Order was $ 26,895955 .00 The Guaranteed Maximum Price will be increased by this Change Order in the amount of $ 956,661 .00 The new Guaranteed Maximum Price including this Change Order will be $ 27,852,616.00 The Contract Time will be increased/decreased by zero ( 0 ) days. The date of Substantial Completion as of the date of this Change Order therefore is June 30, 2007. AIA Document G701 TM - 2001 . Copyright © 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING: This AIA" Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this Ale Document, or any � portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:20 :01 on 04/11 /2007 under Order No. 1000250302_I which expires on 7/25/2007, and is not for resale. User Notes: (4165883699) NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been swill by Construction Change Directive until the cost and time have been agreed upon by both the Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive. NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER. Donadio & Associates, Architects, P.A. Turner Construction Company Indian River Coun[y. Board of County Commissioners ARCHITECT (Firm name) CONTRACTOR (Firm name) OWNER (Finn?rignje� : -°rq,,, 609 17t eet, Vero Beach, Florida 800 N. Magnolia Avenue, Orlando, FL 184025th Street, Vero Bead jtonda 329 32803 32960 ADDR AD BS BY gr Lure) BY (Signatu BY (Sag •Zoe), b Anthony Donadio Louis Fiore Gary C. eeter.• Chairmm@7r (Typed non (7 jTed name) (Typed name)' s i': DATE DAT%Z DATE ' D � AIA Document G701 *e — 2001 . Copyright © 1979, 1987, 2000 and 2001 by The American Institute of Architects. All rights reserved. WARNING : This AIA, Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA, Document, or any 2 portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 14:20:01 on 04/11 ,2007 under Order No. 1000250302_1 which expires on 7i2512007, and is not for resale. User Notes: (4165883699)