HomeMy WebLinkAbout2007-263E i
D O N A D I O
& Associates, Architects, P.A .
TO: LOU FIORE TURNER CONSTRUCTION
STEVE BLUM INDIAN RIVER COUNTY
LYNN WILLIAMS INDIAN RIVER COUNTY
TOM FRAME INDIAN RIVER COUNTY
JIM LEVERONI DONADIO AND ASSOCIATES
FROM: ANTHONY J. DONADIO, AIA, NCARB
DONADIO & ASSOCIATES, ARCHITECTS, P.A.
DATE: FRIDAY - JUNE 29, 2007
ISSUE DATE: SATURDAY - JULY 07, 2007
PROJECT NO. 2102.18
REGARDING: INDIAN RIVER COUNTY ADMINISTRATIVE COMPLEX
BUILDING 2 - IST FLOOR - WEST AND CENTER PORTION
INTERIOR PUNCH LIST
TIME: 2:00 P.M.
WEATHER: CLOUDY / RAINY
Building 2 - 1st Floor Interior Punch List
Corridor 103
L Door 103A — Door 103A needs to be cleaned of dirt, debris and drywall mud.
2. Door is scratched at the inside face at the exit devices.
3 . Hollow metal frames need to be repainted inside and out.
4. Above Door 103A drywall needs to be repainted above the top right edge and also drywall where it abuts the
hollow metal frame 103A needs to be sanded, caulked and repainted.
5 . West wall outside corner to the left of Tax Collectors door drywall is damaged needs to be patched and
repaired. That is also true of the outside and inside corner of this projection wall.
6. Door 103A needs to be cleaned of dirt and debris outside and inside faces are scratched.
7 . Hollow metal door frame needs silencers and need to be repainted.
8. Right outside corner to the door leading into the Tax Collectors office and to the left of Door 103A outside
corner is chipped needs to be patched and repaired. That is also same with the right outside corner of Door
301 A, marks in the drywall need to be patched and repaired.
9. Outside corner of vinyl base needs to be adhered.
609 17" Street Vero Beach, Florida 32960 Phone 772 794 2929 Fax 772 562 8600
Email dm@donadio-ach.com License No . AA0002238
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 2
Corridor 103 (continued)
10. Drywall wall between Door 301A and 303B above the vinyl base needs to be repainted and also to the left of
the outside corner by Door 303B drywall needs to be repainted along with scratches and dents on the outside
corner.
11 . Drywall to the left of hollow metal door frame 303B above the vinyl base needs to be repainted. That is also
true at the top right and left comers on the right side of the hollow metal frame completely around Door 303B ,
the drywall needs to be repainted.
12. Vinyl base to the right of Door 303B is not setting flush to the wall, needs to be removed, sanded and re-
installed.
13. Paint needs to be removed from the hinges of Door 303B .
14. Right outside corner of Door 303B above the vinyl base door is damaged. This needs to be repaired.
15 . Length of wall from Door 303B to Door 311A the wall needs to be cleaned of dirt, debris, drywall dust and
touched up and repainted where necessary where the finish has been damaged.
16. Drywall around Door 311A needs to be completely repainted, door has just been recently installed, hollow
metal frame 311A has not been painted.
17 . Floor tile has been chipped up to install the hollow metal door frame to the left of the Door 311A and to the
right of hollow metal door frame 311 A .
18. Door 311A has no view lights installed.
19. Drywall needs to be repainted completely around the right and left sides and tops of Doors 31 IA.
20. Fire extinguisher cabinet still has painter tape around it.
21 . Exterior Door 103B - Ceramic tile needs to be grouted at the threshold and at the removable mullion .
22 . Exterior hollow metal Door 103B needs to be repainted inside and the jambs right and left sides .
23 . Access panel to the right of hollow metal door 103B needs to be painted, finish is chipped . It is white finish
at this time.
24. Head of hollow metal frame where the removable mullion has been attached, needs to be sanded and
repainted.
25 . Painters tape needs to be removed from fire alarm pull station, fire alarm horn strobe and electrical outlets in
this area.
26. Ceiling tile is missing in 6 locations in this area in front of Door 103B .
27. Boxed out column to the right of Door 103B no ceiling grid installed around that boxed out area.
28. Drop ceiling in front of Doors 211A and 401A & B ceiling tile not in place .
29. Drywall ceiling in front of Door 311A needs to be touched-up with paint along the complete perimeter
adjacent to the wall. Also, drywall opening at the sprinkler heads in front of Door 311A and in front of door
401A & B opening cut too large needs to be patched and repaired .
30. Light fixture, can lights need to set flush and level to the drywall .
31 . West end of drywall ceiling bottom edge is chipped, needs to be repainted.
32. Ceiling tile in the area from Alcove for 311A down to the end of Corridor 103 numerous ceiling tiles are out
of place.
33 . Ceiling grid adjacent to west face of the dropped ceiling in front of Doors 311A needs to be cleaned of
drywall mud, etc . Also, ceiling tile to the left needs to be refinished, this is chipped.
34. Drywall to the left of Door 401B needs to be repainted, spots in the drywall finish.
35 . Hollow metal door frame 401B needs to be repainted on the sides and at the head where the drywall abuts the
head needs to be sanded, caulked and repainted.
36. Hollow metal frame 401 A needs to be repainted completely .
37 . Transition strips needed between the carpet and ceramic tile at Door 401A and 401 B .
38. Door 401A inside left edge finish is scratched.
39. Drywall to the right of hollow metal frame 401A needs to be repainted where the metal frame abuts the
drywall .
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1 st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 3
Corridor 103 (continued)
40. Outside corner to door 401A needs to be repainted where it has been chipped, top and bottom.
41 . Drywall at the outside corner of the wall in front of Door 401 A at the ceiling level needs to be repainted
completely along the length of that wall between Door 401A and 108A. Insufficient coats of paint.
42. Exterior Door 103B hollow metal doorjamb the fasteners need to be patched, sanded and repainted. Heads
are exposed at this time.
43 . Drywall between Door 401A and 108A needs to be cleaned of dirt and debris and touched-up with paint along
the complete length at numerous areas above the vinyl base where there are gouges in the drywall and glue on
the wall, etc .
44. Door 108A hollow metal door frame needs to be repainted.
45. Metal door frame needs to be cleaned of drywall dust, dirt and debris.
46. Top right corner and top left comer of the hollow metal frame is bent.
47. Drywall to the top left comer of Door 108A appears to have been an irregularity in the drywall finish, needs
to be sanded and repainted.
48. Drywall in hollow metal door frame 107A needs to be repainted completely.
49. Top right of door frame 107A drywall is irregular needs to be sanded and repainted.
50. Bottom right of Door 107A is irregular needs to be sanded and repainted.
51 . Three ceiling tiles out of place in front of Door 301 A.
52 . Ceiling grid top left corner leading out to Door 103A grid is damaged and has drywall mud on it, needs to be
cleaned and repainted, repaired.
53. Ceiling tiles in front of Door 303B four ceiling tiles out of place.
54. Ceiling tiles between Door 311 , 303B and 311A six ceiling tiles out of place.
55 . Ceiling tile about the middle of the way between Door 303B and 31 IA damaged at the center. Also, to the
right of this same area edge of the ceiling tile damaged.
Data Room 107
1 . Outside edge of door is chipped, needs to be cleaned of paint and debris.
2. Outside face is chipped at the center of the door and inside face needs to be cleaned of drywall debris and
yellow paint on the hinge side and the bottom of the door.
3 . Top right comer of hollow metal frame 107 needs to be cleaned of drywall mud.
4. Boxed out column area vinyl base needs to be cleaned of glue.
Electrical Room 108
1 . Outside face of Door 108 needs to be cleaned of paint on the bottom edge of the door.
2. Inside face of Door 108 needs to be cleaned of drywall dust and paint.
3 . Drywall to the right and above Door 108 needs to be sanded and repainted, finish is very irregular above and
below the Siemens panel to the right of Door 108.
4. Ceiling tile needs to be cut neat and clean around conduit penetration, this should trimmed out at all possible
with sand grid.
5 . Electrical outlet cover plates need to be cleaned of paint.
6. Plywood backboard needs to be touched-up with paint where the fire proof paint has been damaged.
Tax Collector Area
1 . Door 201 - Doors need to be cleaned of dirt and debris and scratches on the interior face .
2. Hollow metal door frames need to be repainted.
3 . Removable mullion not installed.
4. Satellite to the right of Door 201 frame needs to be sanded and repainted .
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 — 1 st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 4
Tax Collector Area (continued)
5 . Coral cast column to the right of the side light at Door 201 , coral cast base where it abuts the drywall is very
irregular, unacceptable. That is also typical at the head, capital, of the coral cast column on the right and left
sides.
6. Electrical outlet to the right of the coral cast column and also Door 201 cover plate missing. Also, in this
same area of the Johnson control box needs to be set plumb and level to the wall and cleaned of paint.
7. Need to make sure that the coral cast columns are caulked where they abut the ceramic tile floors and the
drywall.
8. All window sills on the south wall need to be cleaned of paint at the underside and the edges.
9. Hollow metal strorefront windows on the south wall need to be cleaned of paint and caulking in numerous
areas. Also, drywall jambs need to be painted in locations where there are insufficient coats of paint and also
the outside edges of the drywall jambs where they have been chipped in side window locations.
10. South wall to the left of Door 201B outlet box is exposed.
11 . Fire Extinguisher to the right of Door 201B needs to be caulked to the wall and the protective covering
removed.
12. Electrical outlet to the right of Door 201B needs to be cleaned of paint.
13 . Ceramic tile floor needs to be cleaned of paint, dirt and debris throughout the whole floor area. Numerous
areas have white and gray paint throughout out on different riles .
14. Coral cast column to the left of Door 201 needs to be cleaned of drywall dust, dirt and debris .
15 . Quad outlet to the left of the coral cast column needs cover plate installed.
16. Duplex electrical outlet to the right of the data outlet 45/46 needs paint removed from the electrical device.
17 . Door 203A — Hollow metal frame on the outside needs to be touched-up with paint.
I & To the right of Door 202A right hand side corner paint needs to be cut in properly. At this location there is
two paint colors and they overlap in the inside comer.
19 . Door frame 202A left side needs to be cleaned of paint.
20. East and wall between Door 202A and to the left towards the Reception Area needs to be touched-up with
paint that is on the east and south side fingerprints, dirt, etc.
21 . Drywall header over the Tax Collector Reception counter running the complete length of this space, outside
edge where the vertical face meets the ceiling horizontal, paint cut in is very irregular and not acceptable.
Also, chips on the edges need to be patched and repainted.
22. Drywall ceiling at the westernmost coral cast column, between Reception Area 201 and Open Office Area
202 directly in front of the drive thru window, pencil marks on the ceiling need to be cleaned. Also, to the
east of this same coral cast column in the drive thm area drywall opening cut too large around the can light,
needs to be patched and repaired.
23 . Drop ceiling over the Reception counter to the west of door 201 numerous can lights drywall opening cut too
large, needs to be patched and repaired starting on the east end of 2nd and 41Il can lights .
24. Drop ceiling over the Tax Collector Reception area A/C grilles fingerprints on the drywall need to be cleaned
and repainted .
Reception Area 201
1 . Acoustical ceiling tiles that cover about 10% are missing, not in place.
2. Ceiling grid above Door 202A finish is damaged on the grid.
3 . Ceiling grid to the right of Door 202A next to the coral cast column uneven , needs to be corrected, not setting
flush.
4. Light fixture along the south exterior wall the easternmost light fixture prismatic lens is dented. Also going to
the west the 3rd light fixture off the Atrium wall prismatic lens is dented.
5 . Ceiling grid along the face of the drop header needs to be cleaned of accent color paint.
D O N A D I O
& Associates, Architects, P.A .
Indian River County Administration Complex
Bldg. 2 — 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 5
Reception Area 201 (continued)
6. Ceiling grid to the left of the westernmost coral cast column on the north side joint in the grid is unacceptable;
finish on the grid is damaged.
7 . Ceiling tile to the west of the 3rd light fixture coming off of Door 201 and the 2 full ceiling tile off the
drywall header chip in the rile .
8. Door 202A needs to be cleaned of dirt and debris .
9. Transition strip is needed between ceramic tile floor and the carpet at Door 202A.
10. Outside corner of Work Room 203 in the Open Office area 206 just in front of Door 202A paint finish around
this corner needs to be touched-up with paint. Wall has fingerprints, dirt, etc. That is the complete wall from
Door 202A to the outside corner and from outside corner to borrowed light 203.
11 . Green accent wall along Office 205 and the partial wall at the end of Corridor 208 and Open Office Area 205
needs to be repainted, fingerprints, scratch, dirt and debris on the wall.
12. Hollow metal door 205A needs to be repainted on the left and right jambs approximately 12 inches up off the
floor. Also, left jamb hinge side is bent at the floor of the door frame.
13 . Green accent wall the outside wall of Office 205 on either the left and right side of borrowed light 205 needs
to be repainted in numerous areas .
14. Borrowed light 204 and BL2 that is the right of Door 204A top left corner needs to be cleaned of green accent
color.
15 . Hollow metal door frame 204A needs to be touched-up with paint the he base.
16. Cabinetry along the east exterior wall at the drive thru area needs to be caulked where it abuts the drywall, the
base cabinets and the back splash.
17. Back splash to the right of drive thru window joint in the back splash is unacceptable, irregular.
18. Drive thru window sill is unfinished.
19. Back splash to the left of the drive thru window has caulking and drywall mud on it, needs to be cleaned off.
Also, edges of the drywall opening to the drive thru window needs to be patched and repaired.
20. Back splash along the south exterior wall needs to be caulked where it abuts the drywall and that is the same
with base cabinet.
21 . Southernmost knee space underneath the drive thru window drywall cut out around junction box is very
irregular, needs to be neat and clean. Also, center knee space there is an opening between the knee space and
the sill of the drive thru window.
22. Electrical outlet to the right of the F4 window and exterior wall at the drive thru area, needs to be cleaned of
paint.
23 . Back side of drop soffit at Open Office Work Area 206 & 202, ceiling grid needs to be cleaned of black paint.
Also, joints at the radius of the grid in this area are excessive, this needs to be corrected and be cleaned of
drywall mud.
24. Header between the outside corner of Work Room 203 and Office 205 where the grid abuts this header, not
acceptable, west side of the grid is a double ceiling grid butted together, irregular, voids in it, drywall mud,
etc ., southeast fingerprints, paint, unacceptable, ceiling tile setting uneven the complete length of this header.
25 . Ceiling tile in front of the borrowed light window 203 just to the right of exist sign chip in the tile.
Office 201
1 . Door 204A — Wall mounted door stop needs to be installed for Door 204A.
2. Finish on the metal of view light frame needs to be repainted inside and out. Paint is peeling off.
3 . Door needs to be cleaned of dirt and debris.
4. Drywall around electrical outlet to the left from Door 204A needs to be sanded and repainted. This is also
true of the light switch, drywall is irregular.
5 . Pocket Door 205B bottom right and bottom left drywall needs to be sanded and repainted, very irregular.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 6
Office 201 (continued)
6. To the left of hollow metal door frame 205B at the latching device height drywall is irregular, needs to be
sanded and repainted.
7 . Hollow metal frame at the head stops for the pocket door needs to be caulked and repainted . Also, the head
track for the pocket door is unacceptable, screws do not engage for the stops into anything and the exposed
wood can be seen.
8. Drywall to the left of Door 205B and to the right of Data outlet 31/32 just above the vinyl base to the left and
the right of the data outlet needs to be sanded and repainted.
9. Drywall around quad outlet to the left of the data outlet needs to be sanded and repainted. Drywall irregular.
10. Desk set in place in this room, unable to physical see condition of the wall at borrowed light 204 BLl .
11 . Drywall above light 204 BLl needs to be sanded and repainted at the hollow metal window frame .
12. Ceiling grid in front of Door 204A is chipped, that is the 2°d one off the exterior wall and the ls` the above the
left side of the door.
13 . Ceiling grid the 1st ceiling grid off the south wall and 4`' full tile off the west wall, finish on the tile is
damaged.
14. Ceiling tile ls` full tile off the east wall, 2"d full ceiling tile off the north wall tile is chipped.
Work Room 203
1 . This room is full of chairs from wall to wall. This room can not be completely punched out due to the chairs .
Unable to access the borrowed light 203 BL from inside of Work Room 203 , needs to he punched out at a
later date.
2. Door 203 - Hollow metal frame needs to be touched-up with paint inside and out.
3 . Inside top right corner of the door frame is bent.
4. Door 203A is a Dutch door, inside face of Dutch door shelf needs to be finished, unfinished at this time .
5 . Inside face of Door 203A, chips in the finish, top right at the dead bolt and lockset, etc.
6. Vinyl base to the left of Door 203 needs to be re-adhered.
7 . Left of Door 203A drywall needs to be repainted from the vinyl base up, insufficient coats of paint.
8 . Light switch covers and light finish device needs to be cleaned of paint.
9. Ceiling grid above 203A full of drywall mud and paint, this needs to be cleaned.
Office 205
1 . Desk has been set in place in this room.
2. View light in pocket door 205B has not been installed.
3 . Door 205A - Metal view light frame needs to be repainted, paint is chipping especially no paint on the screw
head.
4. Outside face of door bottom edge needs to be cleaned of paint and finish has been chipped.
5 . Borrowed light 205 BL2 hollow metal frame needs to be touched-up with paint to the left jamb and top head
and also drywall where it abuts the head of the frame needs to be sanded and repainted.
6. Hollow metal door frame 205A bottom right of the door is dented.
7. Vinyl base to the left of 205A needs to be cleaned and also inside comer needs to be repainted.
8. To the left of Door 205A drywall around electrical outlet needs to be repainted.
9. Left side of hollow metal door frame from the vinyl base up to the strike needs to be repainted and
re-caulked.
10. Borrowed light 205 BL1 that is the narrow view light in the east wall of Office 205 , frame needs to be
repainted completely.
11 . Two ceiling tiles misplaced at this time.
12 . Ceiling tile between boxed out column and A/C diffusers tile is chipped.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 7
Work Room 207
1 . Hollow metal door frame 207 bottom left is dented.
2. Left side of Door 207 between the bottom hinge and the middle hinge edges are chipped.
3 . Inside face of Door 207 needs to be cleaned of dirt and debris.
4. Right of door 207 vinyl base needs to be cleaned of paint and drywall mud.
5. General areas throughout this room of the vinyl base needs to be cleaned of drywall mud, dirt, debris and
paint.
6. Drywall around electrical outlet between the metal borrowed light 205 and borrowed light 204 needs to be
patched and repaired .
7. Inside face of hollow metal door frame 204 BLl needs to be repainted on the bottom left edge.
8. West wall data outlet D04 drywall opening cut too large needs to be patched and repaired.
9. East wall electrical outlet cover plates not installed.
10. Electrical outlet to the right of north exterior wall and window drywall needs to be sanded and repainted.
11 . Six ceiling tiles not in place at this time/
12 . Northeast inside corner ceiling tile has paint on it.
13 . Outside corner coming off of Door 207A is chipped and needs to be repainted in numerous areas.
14. Drywall on the outside of Door 207 top left corner needs to be repainted and the drywall where it abuts the
header of the metal frame, door frame needs to be sanded and repainted.
15. Drywall around fire alarm horn strobe to the left of Door 207 opening cut tool large needs to be patched and
repaired. Also, in this same area carpet glue on the walls.
16. Right of Door 207A outside corner vinyl base is not adhering.
17. Open alcove to the right of Work Room 207 furniture is installed completely in this area. Walls need to be
touched-up with paint in numerous locations.
18. Back wall drywall needs to be patched and repaired around electrical outlet and electrical outlet cover needs
to be set flush to the drywall. This is the Office Alcove between Work Room 207 and Office 210.
19. Above this area alcove two ceiling tiles missing not in place.
20. Left outside corner to the left of Door 210A fingerprints on the drywall needs to be repainted .
Office 210
1 . Door 210A - Bottom left of hollow metal door frame 210A is damaged.
2. To of hollow metal door frame where drywall abuts it needs to b sanded, caulked and repainted.
3 . Hollow metal door frame needs to be repainted from the floor up approximately 18 to 24 inches .
4. Inside face of Door 210 below the view light finish has been damaged, irregular.
5 . West wall above the vinyl base carpet glue on the wall .
6. Exterior window on the west wall right side drywall jamb needs to be repainted.
7 . North wall electrical outlet to the far right drywall around the outlet is irregular needs to be sanded and
repainted.
8. Boxed out column drywall surface above the vinyl base needs to be repainted. Also, the outside corners
where the vinyl base is not adhered to this outside column area.
9. Electrical outlet to the left f Door 210 the outlet device needs to be cleaned of paint and the outlet needs to be
set plumb and level.
10. Two ceiling tiles not in place.
11 . Ceiling grid around the boxed out column is not setting flush to the drywall . Also, ceiling grid between the
boxed out column and the north wall has paint on it, that is the grid along the wall.
12. Drywall to the right of Door 210 and to the Vestibule on Corridor 208 side needs to be patched and repaired
above the vinyl base, drywall is damaged and also glue on the wall.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 8
Vestibule 211
1 . Transition strip needed between the ceramic tile and the carpet.
2. Right and left outside corners where the ceramic tile and vinyl base meet the transition is not acceptable.
3 . Floor tile is not grouted at the exterior door.
4. Top left comer and the drywall above the door to the left of exterior Door 211 A needs to be repainted.
5 . Outside edges drywall jambs leading to Door 211 need to be repainted.
6. Hollow metal door and frame inside face needs to be completely repainted.
7 . North wall around borrowed light 213 drywall needs to be touched-up with paint, fingerprints, dirt, chips in
the paint.
S. Borrowed light hollow metal frame 213 needs to be repainted at the head and the jamb and sill, in numerous
areas outside edges are chipped and bottom right corner is dented. Also, edges /sides of the hollow metal
frame where it abuts the drywall need to be sanded and repainted.
Office 213
1 . Bottom left of hollow metal Door 213 , hollow metal frame is damaged.
2. Hollow metal frame the strike side needs to be repainted, fingerprints all over the door.
3 . Drywall where it abuts the head of Door 213 needs to be sanded and caulked and repainted. That is the head
and the top right jamb.
4. Bottom right inside corner within to the right of Door 213 drywall needs to be sanded and repainted.
5 . Drywall around hollow metal door frame at the head needs to be sanded, painted and re-caulked .
6. Top left corner of hollow metal borrowed light is damaged.
7. Drywall to the bottom hollow metal borrowed light, drywall needs to be patched and repaired.
8. Right inside comer above the vinyl base at the exterior wall needs to be sanded and repainted just above the
base.
9. Drywall around the light switch needs to be sanded and repainted, very irregular.
10. Top left corner of hollow metal door frame 213 needs to be repainted.
11 . Drywall to the left of hollow metal door frame from the floor up to the strike needs to be sanded, caulked and
repainted.
12. Two ceiling not in place .
13 . Ceiling grid above Door 213 needs to be cleaned of dirt.
14. Ceiling tile in the far northeast comer next to the return air grille is chipped.
15 . Outside wall of Office 215 to the right of Door 213 bottom right above the vinyl base pencil marks , paint on
the wall needs to be repainted.
16. Electrical outlets between Door 213 and 214 drywall need to be sanded and repainted.
17. Drywall to the bottom left of Door 214 needs to be patched and repaired.
Office 214
1 . Hollow metal door frame 214 bottom left is damaged. Also, at the middle hinge.
2. Drywall to the left of door frame 214 needs to be sanded and repainted. That is also true of the head where
the drywall abuts the hollow metal door frame head and the bottom right above the vinyl base.
3 . To the right of Door 214 inside the office area drywall and hollow metal frame needs to be sanded where it
abuts the drywall approximately 12- 18 inches off the floor. Also, inside corner of vinyl base is not adhered
and drywall in this area is very rough and irregular, needs to be sanded.
4. To the left of Door 214 paint needs to be removed from the electrical outlet cover and Johnson control box.
5 . Boxed out column outside edges need to be sanded and repainted there rough and irregular. Also, ceiling gird
at this same boxed out column is not setting level to the ceiling and has drywall mud on it.
6. Three ceiling tiles not in place at this time.
7 . Ceiling gird to the left and 2°d grid to the left of the return air grille is damaged.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 9
Office 214 (continued)
8 . Ceiling tile the 2nd ceiling tile off the west wall and 2nd full ceiling tile off the south wall , tile is chipped .
9. Drywall above Door 214 needs to be repainted between the door head and ceiling.
10. To the left of fire alarm horn strobe just above the fire extinguisher cabinet and to the left of Door 002 needs
to be sanded and repainted. Fingerprints and irregularities in the drywall .
11 . Door 002 is waiting to be replaced with solid core door without a view light.
12. At this time vinyl base is not secured at Door 002 at exit stairs .
13 . Hollow metal frame needs to be repainted and carpet needs to extend out towards the inside of the hollow
metal door frame stop. Carpet is cut too short.
Office 215
1 . Vinyl base to the left of Door 215 on the outside not secured properly to the drywall and also above the vinyl
base area irregularities in the drywall need to be patched and repaired .
2 . Hollow metal door frame top left corner needs to be sanded and repainted . Also, drywall where it abuts the
door needs to be sanded, caulked and repainted.
3. Wall mounted wall stop the door stop needs to be installed.
4. Drywall at the top of the hollow metal door frame 215 needs to be sanded, caulked and repainted.
5. This room has furniture in it.
6. Metal frame for Door 215 outside face top right and left corners are dented .
7. Drywall jambs for interior window need to be repainted on left and right sides and storefront frame has
excessive staining on it, needs to be cleaned.
8. Bottom left of Door 216B where it abuts the drywall and the bottom right needs to be sanded, caulked and
repainted. Very irregular.
9. Vinyl base to the left of Door 216 is not adhered properly.
10. Stops in the head of the pocket door frame 216 needs to be caulked and repainted. Also, inside of the head
frame wart is exposed, unacceptable.
Office 216
1 . Drywall above hollow metal door frame head outside of Door 216 needs to be sanded, caulked and repainted.
2. Door 216 bottom right the bottom hinge finish is chipped and also edges of door needs to be touched-up, re-
stained, at the hinge side and the strike side.
3 . Top right interior hollow metal door frame is dented.
4. Top left of fire wall where it abuts the hollow metal frame needs to be sanded, caulked and repainted.
5. Drywall around light switch to the right of Door 216 needs to be sanded and repainted, irregular.
6. Electrical outlet on the east wall electrical cover needs to be set plumb and level .
7. Two ceiling tiles out of place .
8. Ceiling tiles to the north and the west of the return air grille are damaged .
9. Left drywall jamb of exterior window needs to be repainted.
10. Exterior window has excessive dirt, etc. Needs to be cleaned.
11 . Drywall to the right of Door 217 to the outside comer of Training Room 217 above the vinyl base drywall
needs to be patched and repaired.
12. Drywall on the Corridor side from the southwest corner of Training Room to the southeast corner at Door
217 , door needs to be cleaned of drywall, dust, dirt and debris the completer length of the wall.
13 . Drywall below fire extinguisher cabinet and above vinyl base needs to be repainted.
14. Drywall to the right of Door 217 needs to be repainted between the Door 217 and the outside corner.
15 . To the left of door frame 217 approximately 12 inches off the floor drywall rough and irregular needs to be
sanded and repainted.
16. Door 217 - outside, right side paint on the finish.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - Ist Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 10
Office 216 (continued)
17 . Drywall to the right of Door 217 below the electrical outlet needs to be sanded and repainted, irregular.
18 . Drywall above Door 217 needs to be sanded, caulked and repainted.
19. Carpet joints in the green accent carpet tile, irregular, they need to be set flush and true.
20. Vinyl base on the back wall is not adhered in numerous locations, pulling off the back accent wall .
21 . Center of south wall about center of the wall above the vinyl vase drywall is irregular needs to be sanded and
repainted.
22. West wall towards left end corner carpet glue on the wall, needs to be cleaned and also that same area dent in
the drywall above the vinyl base needs to be patched and repaired.
23. Painters tape needs to be taken off the north wall.
24. Electrical outlet on the east wall, drywall around the outlet is irregular, needs to be sanded and repainted.
25 . Need wall mounted door stop installed.
26. Northwest corner ceiling tile in front of the light fixture is chipped.
27 . Ceiling tile above the fire alarm horn strobe needs ceiling grid in this area and one grid on either side of it
finish has been damaged where there is mastic on it needs to be cleaned.
28 . Ceiling grid, joint to the top right of door 217 is unacceptable, it is irregular.
29. Wall channel for the ceiling grid on both of the long walls, the north and south walls, very rough and
irregular.
Office 219
1 . Drywall to the bottom left and right of hollow metal door frame 219B needs to be sanded and repainted.
2. Hollow metal door frame where fingerprints are on throughout the door.
3 . Wall mounted door stop needs to be installed for Door 219B .
4. Bottom face of Door 219B needs to be cleaned of dirt and debris.
5 . Bottom left of Door 219B drywall needs to be sanded and repainted.
6. Carpet cut too short that is the left inside corner of Door 219B , concrete slab exposed, unacceptable.
7 . Drywall above hollow metal door frame 219B needs to be sanded, caulked and repainted .
S . Drywall to the right of Door 219B electrical outlet and light switch needs to be sanded, caulked and repainted.
9 . Right hand side comer at the boxed out column drywall needs to be sanded and repainted. Also, at this
outside corner of this same area vinyl base is not adhering.
10. East wall to the right of the boxed out column above the vinyl base scratches in the drywall needs to be
patched and repaired.
11 . Door 219A- Drywall to the bottom left screw heads exposed need to be patched and repaired.
12. Drywall above Door 219A at the hollow metal door frame needs to be sanded and repainted.
13 . Borrowed light 219B BLl underside at the fill and bottom right and left jambs drywall needs to be sanded and
painted and underside of metal frame needs to be sanded and repainted.
14. Two ceiling tiles not in place in this Room 219 .
15 . Ceiling gird around boxed out column is irregular, needs to be corrected. Double grid that sets around the
column has exposed joints.
16. East outside wall of Office 219 has furniture in front of it. Unable to inspect properly.
17 . Outside corner to the left Door 219A above the vinyl base and about 30 inches off the floor drywall is dented
and damaged. Needs to be patched and repaired.
18 . Hollow metal frame to the left between the top and middle hinge is dented.
19 . Drywall to the bottom right at the hollow metal frames is rough and irregular needs to be sanded and
repainted.
20. To the right of hollow metal door frame 219A marks on the drywall above the vinyl base needs to be patched
and repaired.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 11
Office 219 (continued)
21 . Right outside comer of Office 219 the northeast comerjust to the left and above the vinyl base approximately
5ft. dents in the drywall need to be patched and repaired.
22. Work area cabinetry south of Office Area 218 and 219?? ? ?????
23. East end at the filler strips, filler strips edges are chipped and damaged where it has been caulked to the
drywall.
24. Vinyl base to the bottom left of this eastern end is not adhered to the drywall.
25 . Above the back splash at the outside corner of this eastern wall between the upper cabinets and the base
cabinets fingerprints on the paint finish.
26. Above the wall cabinets at the east end, left inside corner and approximately off of that needs to be patched,
repainted and repainted.
27. Cabinetry needs to be cleaned of drywall dust, dirt and debris .
28. West end below the wall cabinets where there is no base cabinets installed the inside corner about the middle,
drywall is damaged needs to be patched and repaired. Also, coming off this same area the outside corner of
the wing wall needs to be patched, repaired and repainted.
29 . Ceiling tile to the left of th4eoutside corner of Office Area 219, tile is chipped.
30. Ceiling gird on the west end of the upper cabinets up above the cabinets do not set flush and level to the wall.
31 . Ceiling tile in Open Office Area 218 approximately 6 tiles not in place.
32. Ceiling tile at the exit device between boxed out column and Door 215 at the exit sign, tile is damaged. That
is also true in this same area, 2 or 3 tiles near the return air grille and the 2x2 light fixture in front of Door 215
and 216.
33 . Ceiling tile the 5`h ceiling tile off the north Training Room wall and the 4th tile off the boxed out column to the
left of Door 215 tile is chipped.
Storage Room 220
1 . Transition strip needed between VCT and ceramic tile.
2 . Hollow metal door frame 220 needs to be caulked where it abuts the masonry on the inside both the jambs
and the heads .
3 . Door 220 needs to be cleaned of dirt, drywall dust, etc.
4. Hollow metal door frame needs to be completely repainted.
5 . No vinyl base installed.
6. Floor needs to be cleaned of dirt and debris .
7. All penetrations in the masonry wall needs to be sealed properly and closed off.
S. Light fixture lenses are loose, some are damaged this needs to be replaced.
9. Grout joints in numerous areas are cracked, these need to be filled in especially on the north block wall and
the south block wall.
10. This room needs an additional coat of paint.
11 . Electrical outlets on the east wall opening cut out very large and irregular, this needs to be patched and
repaired properly. That is also true of the light switch to the left of Door 220.
12. Drywall around fire alarm horn strobe to the right of Door 220 opening cut too large, needs to be patched and
repaired.
Receiving Room 221
1 . Drywall to the left and right of Door 221 needs to be touched-up with paint.
2 . Transition strip needed between ceramic tile and sealed concrete.
3 . Hollow metal door frame bottom left metal wire needs to be removed and door needs to be caulked.
4 . Exterior Door 221 B needs to be repainted on the inside and also hollow metal frame needs to be caulked
where it abuts the masonry on the inside.
D O N A D I O
& Associates , Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - I st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 12
Receiving Room 221 (continued)
5. Right inside corner to the right of Door 221B is cracked, this needs to be caulked.
6. Cut out in masonry for light switch, data switches and electrical outlet are unacceptable, very rough and
irregular, this needs to be redone.
7. Hallway leading to exterior Door 222A needs to be touched-up with paint above the ceramic tile in numerous
areas where dirt and debris.
8 . Ceramic file is not finished grouting at exterior Door 222A, door needs to be repainted on the inside and
hollow metal frame needs to be repainted.
9. Large stack of acoustical insulation stored in this area right now.
10. Transition strip needs to be installed between the ceramic file and the carpet at the area directly in front of
Corridor 222 where it changes from carpet to ceramic tile in front of Door 220, 221 & 222.
Open Work Area 223
1 . Hollow metal Door 223 right side of door frame above them idle hinge is damaged.
2. Top of hollow metal door frame needs to be repainted.
3 . Bottom left of hollow metal door frame drywall needs to be sanded.
4. Inside face of Door 223 finish is damaged and that is also true of the bottom above and below the view light.
5. Drywall to the left of the hollow metal door frame above the vinyl base needs to be repainted. Also, hollow
metal frame is dented just below the bottom hinge.
6. Drywall to the bottom left of Door 224 drywall needs to be sanded and repainted.
7 . Right of Door 224 hollow metal frame is not cut flush to the door frame.
S . Vinyl base top edge between outside corner and the Door 224B drywall mud needs to be removed.
9. Hollow metal Door 224B needs to be repainted on the outside edges and at the head.
10. Stops for the pocket door needs to be painted and caulked.
11 . Inside head opening wood exposed, unacceptable.
12 . Acoustical grid along the wall at Door 224B , drywall mud the complete length needs to be cleaned and
removed.
13. Inside corner to the left of the exterior window needs to be cleaned of drywall mud at the vinyl base.
14. Drywall below the window sill of exterior window to the bottom right towards the bottom left drywall is
damaged, needs to be patched and repaired.
15. Anchor for the furniture systems has pulled the drywall where it has been secured underneath the window sill.
16. Right side jamb at the exterior wind needs to be repainted.
17 . Borrowed light 225 BL2 window frame needs to be sanded and repainted, rough and irregular at the bottom
left at the jambs , etc.
18 . Four or five ceiling tiles not in place.
19. Borrowed light 225 BLl left side bottom left needs to be sanded and repainted and bottom left outside edge.
20. Drywall to the right approximately 8 inches off the bottom right comer needs to be sanded and repainted.
Computer Room 225
1 . Wood Door 225 side of door at the hinges is not finished.
2. Outside and inside face of Door 225 needs to be cleaned of dirt and debris .
3. Drywall above Door 225 needs to be repainted.
4. Right of Door 225 , FM 200 line coming up at the door needs to be relocated. It is in an improper location .
5 . To the right of borrowed light 225 BL2 outside corner of boxed in column this area needs to be patched,
repaired, sanded and repainted. All chips, fingerprints, dirt, unpainted areas on the wall need to be sanded and
repainted.
6. Top right of the hom strobe drywall needs to be repainted.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 13
Computer Room 225 (continued)
7 . All plywood back boards need to be touched-up with paint where they have been cut and chipped, this is a
black fire protective treated paint.
8. Borrowed light 225 BL I , bottom right drywall needs to be sanded and repainted, rough and irregular.
9. Bottom right and left of the hollow metal frames needs to be sanded and repainted.
10. To the right of borrowed light 225 BU and to the left of Outlet V22 drywall needs to be sanded, caulked and
repainted between the hollow metal frame and drywall.
11 . Drywall wall between Door 223A and 227A needs to be touched-up with paint where there is carpet glue and
dirt and debris . Also, above the vinyl base in numerous area gouges in the drywall needs to be patched,
sanded and repainted.
Production Room 226
I . Drywall to the left of Door 226 needs to be sanded and repainted.
2. Door 226 needs to be cleaned of paint, drywall and dirt, etc .
3 . Bottom left of door 226 vinyl base is not adhered.
4. Left side of hollow metal frame 226 needs to be caulked and repainted where it abuts the drywall .
5 . Boxed out column to the right of Door 226 vinyl base is not adhered at the corners .
6. Ceiling grid to the front of fire alarm horn strobe three grids off the wall, plastic on it, needs to be cleaned.
7 . Five ceiling tiles not in place.
8 . Ceiling tiles at sprinkler heads have fingerprints, dirt and debris.
9 . Vinyl base needs to be installed at the cabinetry kick.
10. Floors need to be cleaned of scuff marks, dirt and debris.
11 . Back splash needs to be cleaned of paint at the side and in the back.
Mailroom 227
1 . Bottom left and right of Door 227, hollow metal frame needs to be sanded and repainted, drywall is irregular.
2. Door needs to be cleaned of dirt, debris, drywall mud, etc .
3 . Door head needs to be repainted at the outside edges.
4. Walls need to be touched-up with paint in numerous areas where there is fingerprints, dirt, etc .
5 . Three ceiling tiles not in place
6. Top left of Door 227 at the top hinge drywall needs to be touched-up with paint.
7. Drywall above the vinyl base between doors 227A and 228A is very rough and irregular. Needs to be sanded
and repainted.
Work Room 228
1 . Door 228 needs to be cleaned of dirt, debris, fingerprints, etc.
2. Inside to the right of hollow metal door frame 228 drywall needs to be sanded, caulked and repainted.
3 . Bottom edge of hollow metal window lights hollow metal frame needs to be sanded and repainted.
4. Bottom left of door frame 228 drywall caulking needs to be painted.
5 . Floor needs to be cleaned of paint, scuff marks, etc .
6. Seven ceiling tiles not in place.
7 . The 2nd ceiling tile off the south wall and the 5b ceiling tile off the west wall tile is damaged. That is also true
of the 4's ceiling tile off the south wall and 7" ceiling tile off the west wall.
8. Corridor leading to Door 209A leading out to Corridor 103 walls need to be cleaned of drywall dust, dirt and
debris, completely on both sides.
9. Hollow metal door frames need to be cleaned of carpet glue.
10. East wall opposite the restrooms areas, there are dents and fingerprints in the drywall. Need to be touched-up
with paint the complete length of wall.
D O N A D I O
& Associates, Architects, P.A .
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 14
Work Room 228 (continued)
11 . Bottom left of door 209 , inside corner needs to be repainted.
12. Drywall below drinking fountains needs to be touched-up with paint.
13 . Drinking fountains need to be cleaned of dirt, debris and drywall mud.
14. Bottom left of door 209 vinyl base does not set flush to the drywall , needs to be removed and drywall sanded
in and made smooth.
15 . Bottom right of hollow metal Door 209 needs to be sanded and repainted, finish is irregular and also chips in
the hollow metal frame.
16. Hollow metal frame 230, outside edges where it abuts the drywall , needs to be sanded and repainted . Also,
inside edges need to be sanded and repainted where it has been chipped.
Men's Restroom 229
1 . Light switch cover needed to the right of Door 229.
2. Hollow metal door frame top right needs to be sanded and repainted.
3. Door 229 needs to be cleaned of dirt and debris .
4. Paper towel holder needs to be caulked where it abuts the drywall finish.
5 . Ceramic tile needs to be cleaned of dirt and debris .
6. Ceramic tile where the drain lines penetrate need to be replaced, opening is cut large and irregular and not
neat, not acceptable.
7 . Floor, wall tiles, etc, need to be cleaned of dirt and debris, not cleaned at this time.
8. All toilet accessories need to be caulked to the drywall finish.
9. Ceramic tile below Handi-cap lavatory opening cut too large where the drain lines penetrate the ceramic tile
wall.
10. Walls and floors are full of drywall dust, etc. Needs to be cleaned.
11 . Grout in the ceramic tile around the toilet paper holder and the Handi-cap stall is irregular, unacceptable need
to be redone and corrected.
12. South wall left inside comer where ceramic tiles meets the drywall, finish is irregular and rough, painters tape
was left on the finish and the finish is not cut in tight to the ceramic tile.
13 . All toilet partitions need to he cleaned of drywall dust, dirt and debris .
14. Ceramic tile needs to be cleaned of all markers .
15 . Wall finish where it abuts the ceramic tile finish, tape has been left in throughout.
16. Finish on the paint has been left in place and tape cut in to the tile leaving the paint finish on the tape. All tape
needs to be removed and finished patch is unacceptable.
17 . Drop ceiling needs to be touched-up with paint in numerous areas by the can lights.
18 . Center of dropped drywall ceiling paint finish again is irregular, painters tape left in place and finished over.
19. Ceiling grid has a mark on the finish, the ceiling gird just to the left of the vanity at the toilet partition screen
support.
Women's Restroom 230
1 . Floors need to be cleaned, toilet partitions need to be cleaned, counter top and Restroom needs to be
completely cleaned of drywall dust, dirt and debris.
2. Same issue as we had on Restroom 229 painters tape in place and finish applied over the painters tape at all
inside corners at walls and ceilings and hollow metal door frames .
3 . Hollow metal door frame, inside face, needs to be repainted where the paint finish is damaged.
4. Light switch cover left off to the left of Door 230.
5 . Toilet accessories need to be caulked where they abut the finish.
6. Ceramic tile needs to be cleaned of dirt and debris .
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 — 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 15
Women's Restroom 230 (continued)
7 . Drywall ceiling where it has been damaged throughout needs to be patched and repaired and repainted.
8 . East wall running form the left corner of the Women' s Restroom down to the end of the Corridor to Area 206
numerous areas of wall need to be cleaned of dirt and debris, touched-up with paint above the vinyl base, etc.
the complete length of the wall .
9. Corridor running from Open Office Area 209 down to the end of Corridor 222 ceiling tiles not in place .
10. Ceiling tile opposite Storage Room Door 231 is chipped.
Storaee Room 231
1 . Storage Room 231 is locked unable to inspect.
2 . Drywall between Door 231 and 226 needs to be touched-up with paint and cleaned of drywall, dirt and debris.
3 . Center of this wall above the vinyl base marks and chips in the drywall need to be patched and repaired.
Exterior Stairwell 002 (Stair #2)
1 . Hollow metal door frame 002A is going to be replaced with a flush door.
2. Door frame needs to be touched-up with paint.
3. Exterior exit Door 002B needs to be touched-up with paint at the door and the jambs.
4. Top right of exterior Door 002B plaster is cracked, needs to be caulked and repainted.
5 . Hand rails need to be touched-up with paint where it has been chipped and repainted and actually there other
chips in the paint. This needs to be sanded smooth and repainted. Unacceptable.
6. Risers at the stairs need to be repainted.
7 . Around the wall above mid-landing by the fire alarm hom strobe needs to be repainted where it has been
patched and repaired.
8. Concrete floor at the 2nd floor landing where it abuts the kick plate is very irregular, needs to be cleaned and
made level and smooth. Also, the tread at the I ' riser, where the steel stairs meet the concrete landing, there
is a crack in the concrete.
9. Windows need to be cleaned of dirt and debris and plaster. Needs to be touched-up where it has been patched
at the mid-landing at the 2nd floor landing, etc.
10. Top tread of the stairs is not level, exposed to the front, this needs to be corrected.
11 . Intermediate landing to the right, crack in the wall needs to be patched and repaired. That is also going up at
inside corner at the north end at the intermediate landing. East wall right hand side corner, the corner is
cracked, and left and right of that area of the wall is cracked going from landing up towards the 2"d floor
ceiling .
Reception Area 301
1 . Door 301 A — Inside face of door needs to be cleaned of dirt, debris and scratches below the exit devices .
2. Ceiling tile above the left side of Door 301A is missing, not in place.
3. Top right comer hollow metal door frame needs to be sanded and repainted.
4. Bottom left of hollow metal door frame above the vinyl base, drywall needs to be cleaned and imperfections
in the drywall sanded and repainted.
5 . Drywall to the right of hollow metal door frame 301 A needs to be sanded and repainted where paint is peeled
off and have been painted over.
6. Vinyl base below the fire alarm horn strobe needs to be cleaned of fingerprints.
7. Electrical outlet on the west wall just opposite Door 304A, drywall needs to be sanded and repainted on the
outlet, very irregular. Also, to the bottom left of this imperfection in the drywall needs to be sanded and
repainted.
8. At this time the Systems Furniture is in place and laying up against the wall, some areas are hard to inspect.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 — 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 16
Reception Area 301 (continued)
9. South wall adjacent to Library 204 needs to be repainted, area has been scratched, scuff marks, etc.
10. Drywall to the left of Door 303A left inside comer needs to be sanded and repainted.
11 . Drywall adjacent to hollow metal door frame 303A needs to be repainted.
12. Door 303A needs to be cleaned of dirt and debris, scratch on inside face below the view light and on the
outside face on the Reception Area side and inside face on the Conference Room side.
13 . Eight ceiling tiles not in place at this time.
14. Ceiling tile to the right of Door 303A grid has been pulled off the wall grid, this needs to be set flush.
15 . Ceiling grid on the north wall at Library 304 double grid uneven, this needs to be set flush and also along this
same area to the right or to the east, the ceiling grid is damaged, that is approximately 4ft. off the right hand
side corner.
16. Boxed out column ceiling grid around the boxed out column needs to be cleaned of caulking and drywall
mud. Also, just in front of this column edge of ceiling tile is stained.
Conference Room 303
1 . Door 303B outside face, edges need to be cleaned, bottom right, paint on the doors.
2. Hinges need to be cleaned of drywall dust, dirt and debris.
3 . Inside face of inactive door bottom left scratches on the face.
4. This area is still being worked on, staging area for equipment, tool boxes, tables, etc. has not been cleaned.
Needs to be punched out at a later date.
5 . Carpet to the right of Door 401A, transition strip is needed between the carpet and the ceramic tile.
6. Door 401 A inside face bottom left door finish is scratched. Door frame needs to be repainted.
7 . Door 401B needs to be cleaned of dirt and debris. Door frame needs to be repainted.
Library 304
I . Drywall to the right of hollow metal door frame 304 outside corner needs to be patched and repaired where it
has been chipped and drywall adjacent to the hollow metal frame needs to be sanded and repainted.
2. Drywall to the left of hollow metal door frame needs to be repainted.
3. Hollow metal door frame needs to be repainted.
4. Door needs to be cleaned of dirt and debris , outside and inside.
5 . Drywall to the left of hollow metal door frame 304 drywall finish has been chipped needs to be patched and
repaired.
6. Drywall above hollow metal door frame 304 needs to be sanded, caulked and repainted.
7. Drywall to the right of hollow metal door frame 304 needs to be sanded and repainted, finish is very irregular.
8. North wall drywall around electrical needs to be sanded and repainted.
9. East wall electrical outlet plate needs to be cleaned of paint and caulking.
10. South wall drywall around electrical outlet needs to be sanded and repainted, large area of paint finish is not
finished and outlet cover plate needs to b cleaned of paint.
11 . Six ceiling tiles not in place at this time.
12. Plastic covering still on the light fixtures.
13 . Fire extinguisher cabinet to the left of Door 304 needs to be set secure to the wall and caulked where it abuts
the drywall.
14. Drywall from Door 304 to the left outside corner of Library 304 wall needs to be repainted, patched and
repaired above the vinyl base in numerous locations.
DONADIO
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 099 2007
Page 17
Corridor 305
1 . Left outside corner of Library 304 needs to be repainted where it has been touched-up with paint. In this same
area marks on the wall need to be repainted .
2. Drywall around electrical outlet between the right outside corner of Library 304 and the right corner of Work
Area 309, drywall finish needs to be sanded and repainted. Also, top left to that electrical outlet, mark on the
drywall needs to be patched and repaired.
3 . Right outside corner of Office Area 309 drywall above vinyl base needs to be repainted .
4. Drywall to the right of Door 310 needs to be sanded and repainted on the bottom right and the bottom left.
5. Drywall to the left of Door 310A needs to be sanded and repainted from floor to left top of hollow metal door
frame.
6. Drywall to the right of hollow metal door frame 310, above the vinyl base, nicks in the drywall and dirt marks
need to be patched and repaired. This is continuously along this wall above the vinyl base down to Doors
312C at the Receiving Area.
7 . Doors 312C hollow metal frame needs to be repainted.
8 . Drywall above the hollow metal frame needs to be patched and repaired, caulked and repainted where it abuts
the head of the hollow metal frame.
9. Left and right jambs of hollow metal frame 312C, needs to be caulked and repainted where it abuts the
drywall .
10. Boxed out column in front of hollow metal frame 312C, drywall needs to be patched and repaired above the
vinyl base.
11 . Drywall to the right of Door 308A above the vinyl base marks on the drywall need to be patched and repaired.
12. Drywall to the left of Door 308A from the floor to the top left frame needs to be sanded and repainted. That is
also true of the head where the drywall meets the door head, needs to be sanded, caulked and repainted .
13 . Boxed out column between Doors 304A and 308A bottom left and right corners need to be patched and
repaired.
14. Right of hollow metal Door 307A drywall needs to be patched and repaired above the vinyl base.
15 . Drywall above vinyl base between Door 304A and 306A needs to be patched and repaired, irregularities in
the drywall, etc .
16. Drywall to the right of Door 306A and the vinyl base up to about the strike level, just above the strike needs
to be sanded, caulked and repainted. That is also true of the left jamb needs to be sanded and repainted.
17. West wall in front of Door 306A drywall needs to be touched-up with paint from Door 306A down past 304A
above the vinyl base.
18. Three ceiling tiles not in place in Corridor 305 .
19. Ceiling tile in the outside comer of File Room 210, chip in the tile . Also, outside corner ceiling grid has paint
on it, drywall mud needs to be cleaned.
20. Ceiling tile in front of Door 312C just in front of the fire sprinkler head is not setting flush in the grid.
Office 306
1 . Door 306 needs to be cleaned of dirt and debris .
2. Wall mounted stop needs to be installed for Door 306.
3 . Inside hollow metal frame needs to be touched-up with paint at the strike.
4. Top right, top left corner of hollow metal frame drywall in that area needs to be sanded, caulked and
repainted.
5. Electrical outlet to the far left of Door 306A drywall needs to be sanded and repainted .
6. Furniture in front of this office has not been installed in this office.
7. Fourth ceiling rile is not in place this time.
8.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 18
Office 306 (continued)
9. Inside comer, to the left of the exterior window, drywall at the ceiling grid needs to be sanded, patched and
repainted.
10. Ceiling grid at the sprinkler head closest to Door 306A is dirty, fingerprints need to be cleaned.
11 . Ceiling grid at the sprinkler head in front of exterior windows on the east side, grid has fingerprints on it.
Production Room 307
1 . Door 307 no lockset or strike plate installed. Door needs to be cleaned inside and outside face.
2. Door 307A needs to be cleaned inside and outside face.
3 . Wall mounted door stop needs to be installed for Door 307A.
4. Hollow metal door frame needs to be repainted, especially the bottom left on the inside needs to be sanded
and repainted along with the drywall at this same area.
5 . Furniture installed in this room.
6. One ceiling tile out of place in this room.
7. Ceiling grid the 1 s` ceiling grid off the east wall, 3rd tile off the south wall, finish is chipped. Also, ceiling grid
at the corner of the A/C grille is bent, needs to be repaired.
Office 308
1 . Door 308 outside face, outside edge is chipped and outside edge on the right side below lockset door finish
outside bottom and top edge, lockset side door is chipped.
2 . Wall mounted door stop needs to be installed for Door 308A.
3 . Top right corner inside the office area drywall needs to be patched and repaired at the top right corner of the
hollow metal door frame.
4. Drywall around electrical outlet to the right of Door 308A needs to b sanded and repainted.
5 . Electrical outlet covers need to be cleaned of paint.
6. Bottom right drywall jamb needs to be repainted.
7 . Ceiling grid in front of Door 308 has debris in it, needs to be cleaned.
8 . One ceiling tile not in place at this time.
9 . Ceiling tile the 2nd the off the exterior wall 3`d ceiling tile off the west wall, ceiling tile damaged.
Oven Work Area 309
1 . Furniture installed in this area.
2. Ceiling tile not setting flush near the grid and also at the back area in front of the sprinkler head, ceiling tile
damaged.
3 . Two ceiling tiles not in place in this location.
File Room 310
1 . Door needs to be cleaned of dirt and debris, drywall dust. Hinges, etc . need to be cleaned.
2 . Carpeting needs to taken into the inside face of the door stop of the hollow metal frame.
3 . Drywall top left of Door 310 needs to be repainted.
4. Painters tape still been left on the vinyl base throughout these areas .
5 . Electrical outlet device to the right of Door 310 needs to be cleaned of paint.
6. Four ceiling tiles not in place at this time.
7. Ceiling tile at the center of the room to the left in front of the A/C grille is damaged.
Work Area 312 & Receiving 313 not ready to be punched out, this area is being used as a Storage Room and has
not been cleaned .
D O N A D I O
& Associates, Architects , P.A.
Indian River County Administration Complex
Bldg. 2 — 1st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 19
Mail Room 311
1 . This Room is not ready to be punched out. Cabinetry not completed, floor, walls and Cabinetry full of dirt and
debris. Double door and frame just installed,
Reception Area 401
1 . Assistant ' s furniture is in place in this area.
2. Left of Door 401A quad outlet underneath Assistants furniture needs cover plate installed. Also, true at both
electrical quad outlets on that wall to the left of Door 401A which would be the north wall .
3 . South wall duplex outlet needs cover plate installed to the right of fire extinguisher cabinet.
4. Drywall to the bottom left of hollow metal door frame 404 needs to be sanded and repainted.
5 . Carpet tile joint in front of Door 404 needs to be set tight and flush to the floor.
6. Drywall to the right of Door 403A above the vinyl base irregularity in drywall needs to be sanded and
repainted.
7. Hollow metal frame right side where it abuts the drywall at Door 403 needs to be sanded, caulked and
repainted.
8 . Hollow metal door frame 402 bottom right needs to be sanded and repainted. Also, top right needs to be
sanded and repainted between the green accent color and the top left needs to be cleaned of drywall mud and
repainted.
9. Open office area to the west of Reception Area 401 , six ceiling tiles not in place at this time.
10. Ceiling tile at the sprinkler head closest to Door 401A, chip in the tile. Also, ceiling grid at this location
finish is damaged and ceiling tile at smoke detector edge of the tile is chipped.
11 . Drywall ceiling at the Reception Area 401 — South face of the dropped ceiling edges need to be repainted and
also ceiling between Door 401A and 402A marks on the drywall need to be touched-up with paint.
12. Drywall face outside edge in front Room 402, center of the drywall header needs to be touched-up where it is
chipped.
13 . North face drywall corner bead is damaged needs to be patched and repaired about the middle of the dropped
header.
14. Acoustical ceiling in the center of the dropped drywall ceiling, ceiling tiles need to be set flush in the grid ,
exposed edges are showing.
Conference Room 402
1 . Door 402 needs to be cleaned of dirt, debris and drywall dust, etc . inside and out.
2. Hollow metal door frame needs to be repainted.
3 . Inside right of door frame 402 light switch cover needs to be installed.
4. Left side of hollow metal door frame needs to be cleaned of drywall and repainted. Also, where it abuts the
drywall needs to be sanded, caulked and repainted.
5. Electrical outlet to the right of door frame 402 needs cover plate installed.
6. South wall, accent wall needs to be touched-up with paint where there is drywall dust and fingerprints
throughout.
7. Green accent carpet tile needs to have joints set flush and level
8 . Drywall on the south wall, around electrical outlet need to be sanded and repainted .
9. West wall, vinyl base needs to be cleaned of paint on the complete wall .
10. Ceiling tile above the fire alarm horn strobe edges is chipped.
11 . Ceiling grid along the east wall, grid is uneven, sagging in numerous areas, needs to be level and plumb.
12. Nine ceiling tiles not in place at this time.
13 . Ceiling tie to the south of the return air grille, 2"d tile off the wall, debris in the grid needs to be cleaned so
the tile can set flush.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 - 1 st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 20
Production Room 403
1 . Door 403 needs to be cleaned of drywall mud and dust, outside edge hinge side of door finish is scratched.
That is also true of the bottom below the view light. Inside face needs to be cleaned of paint, drywall dust, etc.
2 . Hollow metal door frame needs to be repainted.
3. Top of hollow metal door frame needs to be sanded, caulked and repainted where it abuts the drywall.
4. Electrical outlet to the right of Door 403 needs cover plate installed. That is true of all electrical outlets in this
room needs cover plate installed.
5 . South wall boxed out conduit area to the left of this area, inside corner needs to be sanded and repainted.
6. Drywall at boxed out area conduit, ceiling grid not installed in this area. Drywall abuts the underside of the
ceiling.
7. Two ceiling tiles not in place at this time.
8. Ceiling grid, five ceiling grids off the north wall and two ceiling tiles off the east wall, grid has black mastic
and finish is damaged.
Office 404
1 . Door 404 bottom left door, finish is chipped and also outside edges.
2. Hollow metal door frame to be repainted.
3 . Vinyl base in Office 404 needs to be cleaned of drywall mud, dirt, debris and paint.
4. Electrical outlet to the right of Door 404 needs cover plate installed.
5 . Vinyl base to the right the complete length of the wall paint on the top vinyl base throughout the room
6. Furniture installed in this room.
7. All electrical outlets in this room need cover plates installed.
8. One ceiling the not setting flush in the grid .
9. Ceiling grid to the top left of Door 404 debris on the edge of the grid.
Open Office Area 405
1 . Drywall around boxed out column at Open Office Area 405 needs to be sanded and repainted .
2. Open Office Area furniture is installed at this time throughout.
3 . Fire alarm horn strobe the drywall opening cut too large, needs to patched and repaired . That is on the wall
opposite Conference Room 402 to the west wall of the Open Office Area 405 .
4. Vinyl base needs to be cleaned of paint at the top edge throughout. Also, dirt and debris .
5 . Ceramic tile where ceramic tile and carpet meet leaning towards Office Areas 407, 408 & 410 need transition
strip between carpet and ceramic tile.
6. Bottom left of Door 406 drywall needs to be sanded and repainted.
7 . Seven ceiling tiles not in place at this time at Open Office Area 405 .
8. Ceiling grid in front of boxed out column finish is damaged.
9. The two ceiling tiles to the left or to the east of the boxed out column , chip in the tile.
10. Ceiling grid in front of Door 406 in front of the sprinkler heads, fingerprints on the grid.
Office Area 406
1 . Door 406 bottom right scratch on the door finish on the outside face.
2. Inside face needs to be cleaned of paint, etc.
3 . Bottom left of Door 406 drywall above the vinyl base needs to be sanded and repainted.
4. Furniture in this room.
5 . Vinyl base needs to be cleaned throughout.
6. Jog in the east wall, side of jog needs to be sanded and repainted, finish is irregular.
7 . One ceiling tile not in place at this time.
8. Ceiling tile above Door 406 corner is cracked.
D O N A D I O
& Associates, Architects, P.A .
Indian River County Administration Complex
Bldg. 2 - 1 st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 21
Office Area 406 (continued)
9. Ceiling grid in the back right corner finish is damaged.
10. Ceiling grid around the sprinkler head in that area needs to be cleaned of dirt.
11 . Exterior Door 405A, hollow metal frame needs to be repainted and door needs to be repainted.
12. Ceramic tile base right and left of Door 405A is not installed. Also, floor tile has not been grouted.
13 . Head of metal door frame 405A needs to be repainted where the drywall head and the hollow metal meet.
Office Area 407
1 . Door needs to be cleaned of debris, hollow metal frame needs to be repainted.
2. Door stop needs to be installed for Door 407.
3. Furniture in this room.
4. Back wall opposite Door 407 needs to be repainted where it has been patched and repaired. Large area.
5 . Seven ceiling tiles not in place at this time.
6. Five ceiling tiles off of door 407 and one off the south wall , tile is damaged.
7. Ceiling tile to the left of the exterior window right in front of the 2x2 light fixture tile is scratched.
Office Area 408
1 . Bottom left of Door 408 needs to be cleaned of carpet glue.
2 . Office Area 408 and 407 needs to have transition strips between the ceramic tile and carpet tile.
3. Drywall to the bottom right of Door 408 above the vinyl base needs to be sanded and repainted.
4. Top right hollow metal door frame needs to be repainted .
5 . Furniture in place in this office.
6. Three ceiling tiles not in place.
7. The 3rd ceiling grid off the west wall 2°d ceiling the off the south wall, grid finish is damaged.
Closet 409
1 . Door locked. Can not access to punch out.
Oven Office Area 410
1 . Open Office Area in front of Office 410 needs to have transition strip where carpet and ceramic tile meet.
2. Fire extinguisher needs to be caulked where it abuts the drywall .
3 . Open Office Area in front of 410 - four ceiling tiles not in place at this time.
4. Two ceiling tiles missing in area in front of door 405A and one not in place above Door 408.
Office Area 410
1 . Hollow metal frame 410 needs to be cleaned of carpet glue .
2. Inside face hollow metal door frame needs to be cleaned of carpet glue and repainted completely.
3 . Drywall to the bottom right of door frame 410 needs to be sanded and repainted. That is also along the right
side of Door 407 where it abuts the drywall and the left side needs to be sanded, caulked, and repainted.
4. Boxed out column to the left of Door 410 above the vinyl base needs to be repainted.
5 . Furniture is in this room.
6. Carpet and vinyl base needs to be cleaned of drywall dust.
7 . Ceiling file is not in place at this time.
8 . Ceiling grid along the west wall about the center, debris on the grid needs to be cleaned.
D O N A D I O
& Associates, Architects, P.A .
Indian River County Administration Complex
Bldg. 2 - 1 st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 22
File Room 411
1 . Door 411 needs to be cleaned of dirt and debris.
2. Wall mounted door stop needs to be installed on Door 411 .
3 . Hollow metal frame needs to be cleaned of drywall dust at top left and the side needs to be touched up with
paint and top right side needs to be repainted where marker is coming thru the paint finish.
4. Two electrical outlets do not have cover plates installed in this room.
5 . Outside door File Room 411 needs to be repainted.
6. Vinyl transition strip needs to be installed between carpet and VCT flooring .
7 . Scuff marks on the VCT in front of Door 411 .
8. Three ceiling tiles not in place at this time.
9. Back left comer at return air grille ceiling tile is chipped. Also, two ceiling tiles along the back wall are not
setting flush into the grid. Cut too short.
Conference Room 501
1 . Door 501A - Outside face of Door 501A needs to be cleaned of dirt, debris, DuraPlex, etc . Same with inside
face.
2. Bottom right of hollow metal frame 501A below the side light drywall needs to be sanded and repainted
above the vinyl base.
3 . West wall approximately 8ft. in form the west wall 2 r/2 ft. above the floor, chip in the drywall need to be
patched and repaired. Also, on this same wall vinyl base needs to be cleaned of paint.
4. Duplex electrical outlet on the north end of the west wall, outlet device needs to be cleaned of paint and
drywall around cover. Electrical outlet cover needs to be touched-up with paint.
5 . Door 502B - Inside face needs to be cleaned and inside edge below center hinge, door finish is chipped on the
edge.
6. Outside face needs to be cleaned of paint on the bottom right comer and throughout.
7 . Drywall to the left of hollow metal door frame above vinyl base needs to be sanded and repainted.
8 . Left side of hollow metal frame needs to be touched-up with paint.
9. Vinyl base needs to be cleaned of paint on the top edge throughout.
10. Door 502C is not in place. Hollow metal frame needs to be repainted completely.
11 . South wall, far left east end electrical outlet about 30-36 inches above the floor 42 inches drywall needs to be
sanded ad repainted, opening cut too large.
12. Ceiling tile towards the back wall which would be the north wall at the quad outlet and junction box, tile is
damaged.
13 . Ceiling tile around the projection screen housing needs to be set flush and level.
Office Area 504
1 . Door 504 no view light installed.
2. Hollow metal frame 504 needs to be repainted completely.
3 . Office 504 painters tape on vinyl base and outlet cover plates.
4. Door 504 is covered with paint, drywall mud, debris, etc .
5 . West wall left end of wall above the vinyl base holes in the drywall need to be patched and repaired and
carpet glue needs to be cleaned off the drywall .
6. Electrical outlet off the Door 504 drywall around this electrical outlet needs to be sanded and repainted .
Finish is irregular.
7 . Floor stop needs to be added for Door 504.
8 . Right of Door 504 about the middle of the wall, irregularity in the drywall finish needs to be sanded and
repainted.
D O N A D I O
& Associates, Architects, P.A.
Indian River County Administration Complex
Bldg. 2 — 1 st Floor Punch List - Friday - 06/29/07
July 09, 2007
Page 23
Storage Area 505
1 . Door 505 needs to be cleaned of drywall mud, dirt and debris, etc.
2. Bottom left edge outside face needs to be cleaned of paint.
3 . Inside face needs to be cleaned of drywall mud .
4. Hollow metal door frame 505 needs to be completely repainted.
5 . Drywall to the left of door 505 above the vinyl base needs to be repainted. Also, above Door 505 , drywall
needs to be repainted.
6. West wall, opposite Office 504, needs to be repainted at the outside comer, chip in the drywall finish above
the vinyl base .
7. Chairs stored in this area at this time.
8 . East wall of Storage Area ,behind the boxed out column, drywall is not completely painted . Also, to the left,
which would be the northeast corner, drywall needs to be repainted in this area.
9. Ceiling tile at the sprinkler head in front of the return air grille chip in the tile finish.
10. Ceiling tile I " full ceiling tile off the north wall and seven ceiling tiles off of Door 505 tile has scratch in it.
11 . Vinyl base in the Alcove leading to Office 504 and Storage 505 needs to be cleaned of paint.
12. Drywall to the right of Door 505 needs to be sanded and repainted above the vinyl base.
GENERAL NOTES:
1 . All closures need to be adjusted so they meet the 51b. closing force as required by the ADA Accessibility
Code .
2. All fire extinguisher cabinets need to be caulked where they abut the drywall and also, need to be cleaned of
protective covering.
3 . All windows, window frames, interior and view lights and the doors need to be cleaned of dirt, debris, paint
painters tape, glass tape, etc.
4. All cabinetry doors and drawers need to be adjusted to set level and plumb and operate properly.
5. All hollow metal door frames need silencers installed.
6. All hollow metal frames for the door view lights need to be sanded and repainted, paint is peeling.
7 . All hollow metal door frames approximately 18-24 inches up off the floor need to be repainted where it has
been damaged.
8. All vinyl base needs to be cleaned of drywall dust, drywall mud. Scuff marks, dirt and debris .
9. All vinyl base at inside corners are not cut and set flush to the inside corner, this is typical throughout.
10. In less otherwise noted all Office area and Open Office area have furniture completely installed which
impacts the visibility for the Punch List of areas.
11 . All drywall where it abuts the hollow metal door frames at the door head and the hollow metal borrowed
light, frames at the window heads needs to be sanded, caulked and repainted., drywall is irregular.
12. All doors have not been cleaned of drywall dust, drywall mud, paint, scratches, unable to properly punch out
the doors due to the fact that they have not been cleaned.
13 . All vinyl tile where it abuts the hollow metal door frames needs to be caulked.
14. All area where carpet is cut into the door frames needs to be re-looked at. Carpet cut too short, not adhering
properly, appears in numerous locations.
15 . All electrical outlets, outlet cover plates need to be cleaned of dirt, debris and paint.
End of Punch List Building 2 West and Center Portion.