HomeMy WebLinkAbout2007-137D Turner March 12 , 2007 Mr. Steve Blum Project Manager Indian River County Administration Complex 2625 19th Avenue Vero Beach , FL 32960 RE: IRC New Admin Building 2625 19th Avenue Vero Beach , Florida 32960 Project #: 11531 Change Order Request Number COR-096 Scope Change Dear Mr. Blum, We have finalized gathering all the required quotations for PCO-061 for the following extra work: Architectural Revisions per CCD's 12, 16, & 24; and Misc Carpet Revisions We have reviewed the Subcontractor Proposals (copies attached hereto) and have verified that all extra work items are in compliance with our Contract Agreement. The following is a detailed itemization of all extra costs: PCO No Item No Description Amount Contractor 061 001 Revise Hollow Metal , Wood Doors and Hardware $4,000. Turner Estimate per CCD's 12 , 16 , & 24. Includes Panic Hardware for Main Electrical Switchgear Room Doors. 061 005 Revise Partition Work per Architectural Drawings $6,356. ACOENG Revised 7/12/06 CCD 12 . 061 006 Revise Partition Work per Architectural Drawings $ 11 ,479 . ACOENG Revised 8/25/06 CCD-16 re-issued as Revised 2/12/07 CCD-24. 061 008 Change Carpet in Rooms 1 .2-503, 504 5505, 506 , $15,027. ACOENG 507, 508, 509, 510 , 511 , 105, & 108 to Bentley Elysian Tip , Color Vestal 887944 . 061 009 Revise paint in Rooms in Commissioner's Area $1 ,500 . Turner Estimate and Exec Offices Building 1 , Floor West. 061 010 General Conditions @ 10% $32836. TURCON 061 012 Fee @ 4.25% of Total $1 ,873. TURCON 061 014 Release Contingency-CCD's 12, 16, & 24. ($44 ,071 . ) INDRIV Total Change to the GMP : $0.00 This change results in a schedule impact of 45 days to the Project. The Extension of Time is included in COR 094 along with concurrent time extensions from other CCD's referenced in COR 094 Please return one ( 1 ) signed copy of this letter indicating your authorization to process this Change Order Request which does not change our Contract Amount. Following final approval of the actual Change Order by the Board of County Commissioners, the Owner's Contingency will be decreased by Forty Four Thousand Seventy One Dollars ($44,071 . ). This approval will also authorize us to issue Subcontract Change Orders as required . If you have any questions regarding this Change Order Request, please call me at your earliest convenience. IM��Mi r� ou i e`L�Dao•(u, herty Sr. Project Engineer Source of Funding: Recommended By: Date : q ' // • D 7 S Bf roject Manager Approved By: 772!�" LA) ' ry jlate: Y / Tom Frame-Director of G eral Services cc: COR-096, PCO-061 , Cost, Purchasing , Accounting , Donadio, Tom Frame AA� COUSTI www.ACOUSTI .com NGINEERING SINCE 1946 COMPANY OF FLORIDA CG-CO20791 - INTERIOR CONSTRUCTION SYSTEMS - CEILINGS WALLS FLOORS 426 Gus Hipp Blvd. PH: (321 ) 636-4042 Turner Construction Company Rockledge, FL 32955 FAX: (321 ) 636-4087 262519'" Avenue Vero Beach, FI 32960 Fax # (772)564-8143 E r ATTN : Mike Dougherty RE: Indian River Admin Subject: PCO-061 Added Walls & Demo Old Mike, We are pleased to provide the following breakdown for the added cost to add 60' of new drywall partitions of metal studs in Building 1 and add 24' o€ new drywall partitions and Demo 13' of metal studs and drywall on one side. Building 1 Add 60' Walls per attached #17 $5662 Building 1 Demo 42' Walls & Credit D.W. per attached #18 <$ 1513> Building 2 Add 24' Walls per attached #19 $2265 Building 2 Demo 13' Walls & Credit D.W. per attached #20 <$58> Total Add $6356 Sincerely, ACOUSTI EN EERING COMPANY OF FLORIDA Douglas R. Capps, 11 Branch Manager RECENED OCT 12 2006 TURNER CLEARWATER COCOA FT. MYERS GAINESVILLE JACKSONVILLE MIAMI ORLANDO PENSACOLA TALLAHASSEE TAMPA WEST PALM BEACH HOUSTON, TX NASHVILLE, TN CHARLOTTE, NC RALEIGH, NC Condition Detail IRC ADMIN Drywall Changes Bid No . 14 Condition NoQ17 Section Mat. Lab. Unit Total Nam061 Added Walls Bldg 1 9250 23.11 71 .26 94.37 5,662 Type: Interior Walls Area: Building 1 Quantity 1 : 6GLF Quantity 2: 0 Quantity 3: 0 Height: IT 0" Count: 0 Notes: No. Section Item Lab. Code Height OC Layers Qty UOM Size Mat Price Per Lab. Cost MatTotal LabTotal 1 9250 TT35820 TOPTRACK20 1 .00 60 LF 10' 450.00 1,000 LF 2.000 27 120 2 9250 TTF 12 " 1 .00 66 EA 0.11 1 EA 7 3 9250 BT35820 BTRACK20 1 .00 60 LF 10' 300.00 1 ,000 LF 2.000 18 120 4 9250 FF3/4 6 " 1 .00 132 EA 0.15 1 EA 20 5 9250 S35820 STUDS20 13' (r 16 " 1 .00 585 LF 13' 455.00 1 ,000 LF 0.350 266 205 6 9250 716PAN 161, 4.00 204 EA 150.00 Box 2 7 9250 B120 ICM/ 1 .00 66 LF Z Y 0.45 1 LF 0.250 30 15 8 9250 58FC20 HANG20 13' 9' 2.00 1 ,669 SF 4 x 12' 400.00 1 ,000 SF 0.500 668 780 9 9250 TF-4 FINISH-4 13' 0" 2.00 1 ,560 SF mixture 0.03 1 SF 0.500 44 780 10 9250 114DWSS 13' 0" 12 " 2.50 11950 EA 127.00 Box 31 D 11 9250 R11 SAB SABS 13' 0" 0.50 390 SF 2' x 8' 161 .60 1 ,000 SF 0.250 63 98 Combined Markup Totals Material Labor Total Net Totals 1,175.35 2511725 39292.60 Stock 0.00 7646 76.46 Clean152.91 0.00 152.91 Supervision _ 238.07 238.07 Per Diem _ 000 0.00 Escalation 0.00% 0.00 0.00% 0.00 0.00 Tax/Burden 7.00% 82.27 50.05% 11293.64 1 ,375.91 SubTotals 19257.62 3,878.33 5,135.95 Overhead 5.00% 62.88 5.00% 193.92 256.80 Profit 5.00% 66.03 5.00% 203.61 269.64 Section Totals 1,386.53 49275.86 51662.39 10/11/2006 3: 16:41 pm Page 1 Condition Detail IRC ADMIN Drywall Changes Bid No . 14 Condition No.. 18 Section Mat. Lab. Unit Total Name: PCO-061 Deleted Walls Bldg 1 & Demo ! - 9250 -14. 19 -21 .82 -36.01 -1 ,513 Type: Interior Walls Area: Building 1 Quantity 1: 42LF Quantity 2: 0 Quantity 3: 0 Height: 13' 0" Count: 0 Notes: ------------ ---------- --- -- ------- -- --- - - -- ---- ------- - ------- -- - -- - - -------- ----------- -- -- - - - - - - - ---------- - --____________ -- _.... . . . . . . . . .._--_ . . .__ . . . __ . .__ . Demo Studs only , credit given for Drywall not hung & finished --------- - --- - - - -- - -- - ------- - - - - - - - ---- No. Section Item Lab. Code Height OC Layers Qty UQM Size Mat. Price Per Lab, Cost MatTotal LabTotal 1 9250 DEMO HANG20 13' 0" 1 .00 584 SF 4 x 12 100.00 1 ,000 SF 1 .000 58 546 WALUSF 2 9250 SBFC20 HANG20 -1 ,168 SF 4' x 12' 400.00 1 ,000 SF 0.330 -467 -386 3 9250 TF-4 FINISH-4 -1 ,092 SF mbdure 0.03 1 SF 0,500 -31 -546 4 9250114DWSS -1 ,365 -EA 127.00 Box -22 D 5 9250 R11SAB SABS -273 SF 2' x8' 161 .60 1 ,000 SF 0.250 -44 -68 Combined Markup Totals Material Labor Total Net Totals 506.28 463.79 569.07 Stock _ 0.00 -16.39 -16.39 Clean 0.00 -32.T7 -32.77 Supervision _ _51 .03 -51 .03 Per Diem _ 0.00 0.00 Escalation 0.00°16 0.00 0.00% 0.00 0,00 Tax/Burden 7.00% -35.37 50.05% -277.26 -312.63 SubTotals 540.65 431.24 -11371.89 Overhead 5.00% -27.03 5.00% 41 .56 -68.59 Profit 5.00% -28.36 5.00% 43.64 -72.02 Section Totals 596.07 516A4 -19512.51 10/11 /2006 3:31 :27 pm Page 1 Condition Detail IRC ADMIN Drywall Changes Bid No. 14 Condition No.: 19 Section Mat. Lab. Unit Total Name: PCO-061 Added Walls Bldg 2 9250 23.11 71 .26 94.37 2,265 Type: Interior Walls Area: Building 2 Quantity 1: 24LF Quantity 2: 0 Quantity 3: 0 Height: 13' 0" Count: 0 Notes: No. Section Item Lab. Code Height OC Layers Qty UOM Size Mat. Price Per Lab. Cost MatTotal LabTotal 1 9250 TT35820 TOPTRACK20 1 .00 24 LF 10' 450.00 1 ,000 LF 2.000 11 48 2 9250 TTF 12 " 1 .00 26 EA 0. 11 1 EA 3 3 9250 8735820 BTRACK20 1 .00 24 LF 10' 300.00 1,000 LF 2.000 7 48 4 9250 FF3/4 6 " 1 .00 53 EA 0.15 1 EA 8 5 9250 535820 STUDS20 131011 16 " 1 .00 234 LF 13' 455.00 12000 LF 0.350 106 82 6 9250 716PAN - 16 " 4.00 82 EA 150.00 Box 1 7 9250 8120 ICIW 1 .00 26 LF 20' 0.45 1 LF 0250 12 6 8 9250 58FC20 HANG20 13' 0" 2.00 668 SF 4 x 12' 400.00 1 ,000 SF 0.500 267 312 9 9250 TF4 FINISH-4 13' 0" 2.00 624 SF mixture 0.03 1 SF 0.500 17 312 10 9250114DWSS 13' 0" 12 " 2.50 780 EA 127.00 Box 12 D 11 9250 R11 SAB SABS 13' 0" 0.50 156 SF 7 x8' 161 .60 1 ,000 SF 0.250 25 39 Combined Markup Totals Material Labor Total Net Totals 470.14 845.90 1,317.04 Stock30.58 0.00 30.58 Clan 0.00 61 .17 61 .17 Supervision - 95.23 95.23 Per Diem _ 0.00 0.00 Escalation 0.00% 0.00 0.00% 0.00 0.00 Tax/Burden 7.00% 32.91 50.05% 517.46 550.37 SubTotals 503.05 11561.33 2,054.38 Overhead 5.00% 25. 15 5.0% 77.57 102.72 Profit 5.00% 26.41 5.00% 81 .44 107.85 Section Totals 554.61 11710.34 2,264.95 10/11/2006 3: 17:40 pm Pagel Condition Detail IRC ADMIN Drywag Changes Bid No . 14 Condition No. 20 Section Mat. Lab. Unit Total Name: CO-061 Deleted Walls Bldg 2 & Demo : 9250 -5.99 1 .50 -4.50 -58 Type: Interior Walls Area: Building 1 Quantity 1 : 13LF Quantity 2: 0 Quantity 3: 0 Height: 13' 0" Count: 0 Notes: - ---- - ------ - -- ------ - ----- ----------- - - - ------- - - - - - - ----- - - --- - - - - - -- -- -- Demo Studs & Drywall on one side only, credit given for Drywall not hung & finished ------ -- --- ------- --- - - -------- - -- ------ - - -- - - ---- - -- ' No. Section item Lab. Code Height OC Layers Qty UOM Size Mat. Price Per Lab. Cost MatTotal LabTotal 1 9250 DEMO HANG20 13' 0" 1 .00 181 SF 4 x 12' 100.00 1 ,000 SF 1 .000 18 169 WALUSF 2 9250 DEMO HANG20 181 SF 4 x 12' 100.00 1 ,000 SF 0.500 18 91 WALL(SF 3 9250 58FC20 HANG20 -181 SF T x 12' 400.00 1 ,000 SF 0.330 -72 -60 4 9250 TF-4 FINISH-4 338 SF mixture 0.03 1 SF 0.500 -9 -169 5 9250 114DWSS -423 EA 12700 Box -7 D 6 9250 R11 SAB SASS -85 SF 2' x S' 161 .60 1 ,000 SF 0.250 -14 -21 Combined Markup Totals Material Labor Total Net Totals -66.06 9.65 56.41 Stock 0.00 035 0.35 Clean 0.00 0.70 0.70 Supervision _ 1 .08 1 .08 Per Diem - 0.00 0.00 Escalation 0.00% 0.00 0.00% 0.00 0,00 Tax/Burden 7.00% -4.62 50.05% 5.89 127 SubTotals -70.67 17.67 53.01 Overhead 5.00% -3.53 5.00% 0.88 -2.65 Profit 5.00% 3.71 5.00% 0.93 -2.78 Section Totals -77.92 19A8 58.44 10/11/2006 3:33 :40 pm Page 1 i Tu 118 SCENE 045 Buiidho the Future IRC New Admin Building B 14 0 6 Transmittal project # 11531 2625 11 Avenue ACOUSTI - ROCYL[993Wheet, Detailed, Grouped by Each Transmittal Number] Vero Beach , FL 32960 Telephone: 772.564.8141 Fax: 772 .564.8143 August 07, 2006 Date: r0 . Transmittal No: • : Doug Capps Karen Berg Acousti Engineering Company of Florida Turner Construction Company 426 Gus Hipp Blvd. 2625 19th Avenue Rockledge, FL 32955 Vero Beach , FL 32960 Tel: 321 -636-4042 Tel: 772-564-8141 Fax: 321 -636-4087 Fax: 772-564-8143 Q Acknowledgement Required Information Federal Express In WIN I III I 1 11 1111111011 111 1 111 IM , III 1 ! ,Iiil ; ! 001 1 Drawings and Sheet: 1 -A1 .1 Building 1-First Floor Overall For Construction Specifications Revision 9 Dated:Floor Plan 7/12/2006 002 1 Drawings and Sheet: 1A1 .1 . 1 Building 1-First Floor Partial ' 2, 0 Lf L For Construction Specifications Revision 9 Dated:Floor Plan 0 7/12/2006 003 1 Drawings and Sheet: 1-A7 .2 Building 1-Second Floor 2 For Construction Specifications Revision 9 Dated:Overall Floor Plan 7/12/2006 004 1 Drawings and Sheet: 1 -At2. 1 Building 1-Second Floor - S For Construction Specifications Revision 9 Dated:Partial Floor Plan 7/12/2006 005 1 Drawings and Sheet: 1-A1 .2.2 Building 1-Second Floor For Construction Specifications Revision 9 Dated:Partiat Floor Plan De �� 7/12/2006 . - om 1 Drawings and Sheet' 2 A1: 1 .2 Building 2-First Floor Partial - 2A p 3 For Construction 5 j{J 3- Specifications Specifications Revision 9 Dated:Floor Plan Ike. 7J12/2006 - _ - a n It $ 1 C 007 1 Drawings and Sheet: 1-A3. 1 Building 1 -First Floor Overall For Construction Specifications Revision 9 Dated:Refected Ceiling Plan 7/12/2006 008 1 Drawings and Sheet 1-A3.1 .1 Building 1 -First Floor Partial G� For Construction Specifications Revision 9 Dated:Refelected Ceiling Play 45j 7/12/2006 - JLlI, 009 1 Drawings and Sheet: 1-A8.0.1 Building 1 -Door Schedules For Construction Specifications Revision 9 Dated: 7/12/2006 010 1 Drawings and Sheet: 1 A9.0. 1 Building 1 Material Finish For Construction Specifications Revision 9 Dated:Schedules 7/12/2006 - 011 1 Drawings and Sheet: 1 -1D1 . 1 .1 Building 1 -First Floor Partial For Construction Spermcations Revision 9 Dated: Interior Finishes Plan 7/14/2006 012 1 Drawings and Sheet: 1 -1 D1 . 1 .2 Building 1-First Floor Partial For Construction TCCO - Transmittal Cover Sheet.rptrQ '(4 ` � `2' ` j RPT Revised: 3l10f2006 v '9fjf (/I Page t of IRC New Admin Building Transmittal Project # 11531 heet, Detailed, Grouped by Each Transmittal Number] Specifications Revision 9 Dated: lnterior Finishes Plan August 07, 2006 7/14/2006 013 1 Drawings and Sheet: 2-1D1 .1 .1 Building 2- First Floor Partial For Construction Specifications Revision 9 Dated: lntedor Finishes Plan 7/14/2006 014 1 Drawings and Sheet: 2-1 D1 . 1 .2 Building 2- First Floor Partial For Construction Specifications Revision 9 Dated: Interior Finishes Plan 7/14/2006 015 1 Drawings and Sheet: 2-A1 . 1 . 1 Building 2-First Floor Partial For Construction Specifications Revision 9 Dated:Floor Plan 7/12/2006 Turner Construction Company File 407-210-2510 1 PGO-061 ; corn; transmittal files Please review the following documents and as applicable please provide pricing to Mike Dougherty on or before 8/16/2006. Please reference PCO-061 in all of your correspondence regarding this matter. 17Signature lo � Signed Date TCCO - Transmittal Cover Sheet.rpt RPT Revised: 3/10/2006 Page 2 of 2 l� n �' a � J � � � � � �� N � � � �. �. .9 -� � � � r � a � N , . \ _ � _ , - _ _ _. � _ � � � � � __ ` � -- c � �-1 AEE�ACOUSTI www.A000STI .com NGINEERING SINCE 1946 COMPANY OF FLORIDA cc-CO20791 - INTERIOR CONSTRUCTION SYSTEMS - CEILINGS WALLS FLOORS 426 Gus Hipp Blvd. PH: (321 ) 636-4042 Rockledge, FL 32955 FAX: (321 ) 636-4087 Turner Construction Company 2625196i Avenue Vero Beach, FI 32960 Fax # (772)564-8143 ATTN : Mike Dougherty RE: Indian River Admin Subject: PCO-088 Change order request ( CCD 16 } , Mike, CC 0 - We are pleased to provide the following breakdown for PCO-0088 Wall changes. 1 . Demo 60 L. F. of wall ( see attached ) $3291 2 . Add 80 L. F. of New Wall ( see attached ) $7550 3. Add 4 Doors Frames & Openings ( see attached ) $638 Total Add $ 115479 Sincerely, ACOUSTI ENGINEERING COMPANY OF FLORIDA J��a Douglas R . Capps , III Branch Manager RECENED OCT 12 2006 TURNER CLEARWATER COCOA FT. MYERS GAINESVILLE JACKSONVILLE MIAMI ORLANDO PENSACOLA TALLAHASSEE TAMPA WEST PALM BEACH HOUSTON, TX NASHVILLE, TN CHARLOTTE, NO RALEIGH, NO Condition Detail IRC ADMIN Drywall Changes Bid No. 14 Condition No.: 13 Section Mat. Lab. Unit Total Name: Rev 11 : Demo Walls 9250 6.72 48.12 54.85 3,291 Type: Interior Walls Area: Building 1 Quantity 1: SOLF Quantity 2: 0 Quantity 3: 0 Height: 13' 0" Count: 0 Notes: No. Section hem Lab. Code Height OC Layers Oily UOM Size Mat Price Per Lab. Cost MatTotal LabTotai 1 9250 DEMO HANG2O 13' F 2.00 1 ,669 SF 4' x 12' 100.00 1 ,000 SF 0.916 167 11430 WALUSF 2 9250 DUMPST 1 EA 175.00 each 175 ER Combined Markup Totals Material Labor Total Net Totals 341.92 17429.74 19771.66 Stock 0.00 51 .63 51 .63 Clean 0.00 103.26 103.26 Supervision _ 160.77 160.77 Per Diem - 0.00 0.00 Escalation 0.00% 0.00 0.00% 0.00 0.00 Tax/Burden 7.00% 23.93 50.05% 873.57 897.50 SubTotals 365.85 29618.96 2,984.81 Overhead 5.00% 18.29 5.00% 130,95 149.24 Profit 5.00% 19.21 5.00% 137.50 156.70 Section Totals 403.35 2,687.40 39290.75 10/06/2006 4:49: 10 pm Page 1 Condition Detail IRC ADMIN Drywall Changes Bid No. 14 Condition No.: 12 Section Mat. Lab. Unit Total Name: Rev 11 : Added Walls 9250 23. 11 71 .26 94.37 7,550 Type: Interior Walls Area: Building 1 Quantity 1 : SOLF Quantity 2: 0 Quantity 3: O Height: 13' 0" Count: 0 Notes: No. Section Item Lab. Code Height OC Layers Qty UOM Size Mat. Price Per Lab. Cost MatTotal LabTotal 1 9250 TT35820 TOPTRACK20 1 .00 80 LF 10' 450.00 1,000 LF 2.000 36 160 2 9250 TTF 12 " 1 .00 88 EA 0.11 1 EA 10 3 9250 BT35820 BTRACK20 1 .00 80 LF 10' 300.00 1 ,000 LF 2.000 24 160 4 9250 FF314 61, 1 .00 176 FA 0. 15 1 EA 26 5 9250 S35820 STUDS20 13' 0" 16 " 1 .00 780 LF 13' 455.00 1 ,000 LF 0.350 355 273 6 9250 716PAN 16 " 4.00 272 EA 150.00 Box 3 7 9250 BI20 ICIW 1 .00 88 LF 20' 0.45 1 LF 0.250 40 20 8 9250 58FC20 HANG20 130" 2.00 2,226 SF 4 x 12' 400.00 1 ,000 SF 0.500 890 1 ,040 9 9250 TF-4 FINISH-4 13' 9' 2.00 21080 SF mixture 0.03 1 SF 0.500 58 1 ,040 10 9250114DWSS lag" 12 " 2.50 21600 EA 127.00 Box 41 D 11 9250 R11 SAB SABS 13' 0" 0.50 520 SF 2' x 8' 161 .60 1 ,000 SF 0.250 84 130 Combined Markup Totals Material Labor Total Net Totals 1,667.13 2,823.00 4,390.13 Stock 0.00 101 .94 101 .94203 � Clean 0.00 203.88 31743 Supervision - 317.43 Per Diem - 0.00 0.00 Escalation 0.00% 0.00 0.00% 0.00 0.00 Tax/Burden 7.00% 109.70 50.05% 11724.85 1 ,834.55 SubTotals 19676.83 6,171.11 6,847.94 Overhead 5.00% 83.84 5.00% 258.56 34240 Profit 5.00% 88.03 5.00% 271 .48 359.52 Section Totals 1,848.70 5,701.15 7,649.86 10106/2006 4:47:29 pm Pagel Condition Detail IRC ADMIN Drywall Changes Bid No. 14 Condition No.: 14 Section Mat. Lab, Unit Total Name: Rev 11 : Added Door Frames 9250 3.49 156.06 159.55 636 Type: Interior Walls Area: Building 1 Quantity 1: 4EA Quantity 2: 0 Quantity 3: 0 Height: 13' 0" Count: 0 Notes: No. Section Item Lab. Code Height OC Layers Qty UOM Size Mat. Price Per Lab. Cost MatTotal LabTotal 1 9250 HMF DOOR FRAME 4 EA 0.00 1 EA 75.000 0 300 2 9250 S35820 STUDS20 26 LF 13' 455.00 1 ,000 LF 0.350 12 9 Combined Markup Totals Material Labor Total Net Totals - - - - - - - _ - - - --1183- - - - _ _ ___ - 309.10._ _- --- --320.93 Stock11 .16 0.00 11 .16 Clean 0.00 22.32 22.32 Supervision _ 34.76 34.76 Per Diem _ 000 0.00 Escalation 0.00% 0.00 0.00% 0.00 0.00 Tax/Burden 7.00% 0.83 - 50.05% 186.86 189.69 SubTotals 12.66 666.20 578.86 Overhead 5.00% 0.63 5.00% 28.31 28.94 Profit 5.00% 0.66 5.00% 29.73 30.39 Section Totals 13.96 624.24 638.19 10/06/2006 4:48:45 pm Page 1 Tumor Building the Future IRC New Admin Building Transmittal Project # 11531 [Cover Sheet, Detailed, Grouped by Each Transmittal Number] 2625 19th Avenue Vero Beach , FL 32960 Telephone: 772.564 .8141 Fax: 772.564.8143 September 18, 2006 Date: rr . r Hf ... *f_��.t"`�„ [�F�f4t i3 r�+ 1. .�.s..°,`a.�na '' "�nv�� '��-:�£�`�,� .a • . ", .�.. Doug Capps Karen Berg Acousti Engineering Company of Florida Turner Construction Company 426 Gus Hipp Blvd. 2625 19th Avenue Rockledge, FL 32955 Vero Beach, FL 32960 Tel: 321 -636-4042 Tel : 772-564-8141 Fax: 321 -636-4087 Fax: 772-564-8143 Q Acknowledgement Required Review, Pricing as appropriate Federal Express 001 1 Drawings and Sheet: 1 -A1 .1 . 1 Building 1 -First Floor Partial For Construction Specifications Revision 11 Floor Plan Dated: 8/15/2006 002 1 Drawings and Sheet: 1 -A8.0. 1 Building 1 -Door Schedules For Construction Specifications Revision 11 Dated: 8/15/2006 003 1 Drawings and Sheet: 0-E1 .0 Electrical Site Plan For Construction Specifications Revision 12 Dated: 8/25/2006 004 1 Drawings and Sheet: O-E4. 1 .0 Electrical Riser Diagram For Construction Specifications Revision 12 Dated: 8/25/2006 005 1 Drawings and Sheet: O-E5. 1 .1 Schedules For Construction Specifications Revision 12 Dated: 825/2006 006 1 Drawings and Sheet: O-E5.1 .2 Schedules For Construction Specifications Revision 12 Dated: 825/2006 007 1 Drawings and Sheet: 0-E5.1 .3 Schedules For Construction Specifications Revision 12 Dated: 8/25/2006 008 1 Drawings and Sheet: 0-E5.1 .4 Schedules For Construction Specifications Revision 12 Dated: 8/252006 009 1 Drawings and Sheet: 0-E5.1 .5 Schedules For Construction Specifications Revision 12 Dated: 8/25/2006 010 1 Drawings and Sheet: 0-E5.1 .6 Schedules - Emergency For Construction Specifications Revision 12 Dated : 8/252006 D11 1 Drawings and Sheet: 0-E5. 1 .7 Schedules - Emergency For Construction Specifications Revision 12 Dated: 8/25/2006 012 1 Drawings and Sheet: 0-E5. 1 .8 Schedules - Emergency For Construction TCCO - Transmittal Cover Sheetrpt RPT Revised: 3/10/2006 Page 1 of 3 IRC New Admin Building Transmittal Project # 11531 heet, Detailed , Grouped by Each Transmittal Number] September 18, 2006 Specifications Revision 12 Dated: 8/25 06 013 1 Drawings and - 1 . 1 . 1 Building 1 -First Floor Partial For Construction Specifications Revision 12 Power Plan Dated: 8/25/2006 014 1 Drawings and Sheet: 1 -E1 .1 .2 Building 1 -First Floor Partial For Construction Specifications Revision 12 Power Plan Dated: 8/25/2006 015 1 Drawings and Sheet: 1 -E1 .2.2 Building 1- Second Floor For Construction Specifications Revision 12 Partial Power Plan Dated: 8/25/2006 016 1 Drawings and Sheet: 1 -E2.1 . 1 Building 1 - First Floor Partial For Construction Specifications Revision 12 Lighting Plan Dated: 8/25/2006 017 1 Drawings and Sheet: 1-E2.1 .2 Building 1 - First Floor Partial For Construction Specifications Revision 12 Lighting Plan Dated: 8/25/2006 018 1 Drawings and Sheet: 1 -E2.2. 1 Building 1 -Second Floor For Construction Specifications Revision 12 Partial Lighting Plan Dated: 8/25/2006 019 1 Drawings and Sheet: 1 -E22.2 Building 1 -Second Floor For Construction Specifications Revision 12 Partial Lighting Plan Dated: 8/25/2006 020 1 Drawings and Sheet: 2-E1 .1 . 1 Building 2- First Floor Partial For Construction Specifications Revision 12 Power Plan Dated: 8/25/2006 021 1 Drawings and Sheet: 2-E1 .1 .2 Building 2- First Floor Partial For Construction - Specifications Revision 12 Power Plan Dated: 8/25/2006 022 1 Drawings and Sheet: 2-E1 .2. 1 Building 2- Second Floor For Construction Specifications Revision 12 Partial Power Plan Dated: 8/25/2006 023 1 Drawings and Sheet: 2-E1 .2.2 Building 2- Second Floor For Construction Specifications Revision 12 Partial Power Plan Dated: 8/25/2006 024 1 Drawings and Sheet: 1 -T1 . 1 . 1 Building 1 First Floor Partial For Construction Specifications Revision 10 Voice/Data Plan Dated : 7/24/2006 025 1 Drawings and Sheet: 1 -T1 . 1 .2 Building 1 First Floor Partial For Construction Specifications Revision 10 Voice/Data Plan Dated: 7/24/2006 026 1 Drawings and Sheet: 1 -T1 .2. 1 Building 1 - Second Floor For Construction Specifications Revision 10 Partial Voice/Data Plan Dated: 7/24/2006 027 1 Drawings and Sheet: 1 -T1 .2.2 Building 1 - Second Floor For Construction Specifications Revision 10 Partial Voice/Data Plan Dated: 7/24/2006 028 1 Drawings and Sheet: 2-T1 . 1 .1 Building 2- First Floor Partial For Construction Specifications Revision 10 Voice/Data Plan Dated: 7/24/2006 029 1 Drawings and Sheet: 2-T1 . 1 .2 Building 2- First Floor Partial For Construction Specifications Revision 10 Voice/Data Plan Dated: 7/24/2006 030 1 Drawings and Sheet: 2-T1 .2.1 Building 2- Second Floor For Construction Specifications Revision 10 Partial Voice/Data Plan Dated: 7/24/2006 031 1 Drawings and Sheet: 2-T1 .2.2 Building 2- Second Floor For Construction Specifications Revision 10 Partial Voice/Data Plan Dated: 7/24/2006 TCCO - Transmittal Cover Sheet.rpt RPT Revised: 3110/2006 Page 2 of 3 IRC New Admin Building Transmittal Project # 11531 heet, Detailed, Groupe b ch Tran ittal Number] Septe ber18 2006 Turner Construction Company File 407-210-2510 1 _ PCO-088 ; corr c�EF�t13G�C. :. ;�,� a,s"'�„n =tom s. .'�SS�",r .��,'� ?ssas -x:�' s - r � .7y. ,�� ,� a �"" �.. ?:, = a- -- —�'_'.�� .. ,.,.,,,;••� .... ,� Please review the attached documents and provide pricing as appropriate to Mike Doughtery on or 01 10ICI, Signature Signed Date TCCO - Transmittal Cover sheetrpt RPT Revised: 3/10/2006 Page 3 of 3 1 I 119800 D O N A D I O & Associates, Architects, P.A. Indian River County Administration Complex CCD 16 Narrative September 05, 2006 Project No. 2102.16.2 The following narrative is a description of the Architectural and Electrical drawing revisions/changes for CCD 16. Revision I1. consists ofthe following L Provide full height privacy walls, each with a new door, at the ends of the Community Development Customer Service counter, 1 . 1 -405. 2. Delete millwork from Staging Area 1 . 1 -406. 3. Revise Work Room 1 . 1 -421 to delete free standing counter and include countertops in the southeast comer of this area. 4. Revisedoorschedule to include two (2) additional doors, 1 . 1405A and 1 . 1405B, at the Community Development Customer Service counter. Items 1 thru 4 are Owner directed changes to the project Revision 72 consists of the following• 1 . Provide flagpole lighting. 2. Provide separate power sources for County data room and Clerk of Court data room. 3. Provide UPS reconfiguration to include one 15 KW UPS for Commission Chambers (Bldg 1), one 50 KW UPS for Clerk of Court (Bldg 1), one 50 KW UPS for County data (Bldg.l ), one 130 KW UPS for Building 2 computer systems. 4. Reconfigure power at all workstations to separate UPS and non-UPS power. 5. Reconfigure Public Works conference room lighting to accommodate projector. 6. Reconfigure furniture in Community Development plan review room 7. Reconfigure furniture in Community Development Lobby. 8. Reconfigure caf6 for final layout. 9. Reconfigure tax collector waiting/reception are& 10. Miscellaneous coordination revisions. Items 1 thin 9 are Owner directed changes to the project. Item 10 is based on coordination of field conditions with Turner. 609 I7' Sweet Vero Beach, Florida 32960 Phone 772 794 2929 Fax 772 562 8600 RECEIVED Email daagdonadio-arch_com License No- AA0002238 - - SEP 14 2906 Indian River County Administration Complex CCD 16 Narrative September 05, 2006 Project No. 2102. 16.2 Page 2 Specific drawing changes include - 1 -ALLI Provide two (2) full height privacy walls, each with a new door, at the ends of the Community Development Customer Service counter, 1. 1-405. Delete millwork from Staging Area I . 1 -406. Revise Work Room 1 . 1 -42 to delete free standing counter and include countertops in the southeast corner of this area, along East and South walls. 1 -A8.0. 1 Revise door schedule to include two (2) additional doors, 1 .1405A and 1 .1405B, at the Community Development Customer Service counter 1 . 1-405. 0-ELO Add lighting and circuits for flagpole. 0-E4. 1 .0 Revise single line diagram to add additional panels and UPS 's. O-E5. 1 . 1 ; 0-E5. 12, 0-E5. 1 .37 0-E5. 1 .4, 0-E5. 1 .57 O-E5. 1 .6, 0-E5. 1 .7 and 0-E5. 1 .8 Revise panel schedules to match revised circuiting and added additional panels. 1 -ELLI , 1-E1 . 1 .2and I-E1 .2.2 Revise circuiting to add TX boxes, revise UPS/non-ups circuits. I -E2.1 . 1 , 1 E2. 1 .2 and I -E2.2.1 Revise lighting in Owner areas for Owner requested changes. 2-E1 . 1 .1 , 2-E1 . 1 .2, 2 E1 .2.1 and 2-E1.2.2 Revise circuiting to add TX boxes, revise UPS/non-ups circuits. 1 -TI . l . l , 1-T1. 12, 1-T1 .2.1 and 1-T1.22 Revise data outlet locations for Owner requested changes. 2-TLI . l , 2-TI .1 .2, 2-TI .2. 1 and 2-TI .2.2 Revise data outlet locations for Owner requested changes. End of CCD 16 Narrative D O N A D 1 0 & Associates, Architects, P.A_ 4 ' S5 � � ' - � , I �'. r� CO '.ISIi Ik - . rl C 'C C coo coustl Engineering Conapaily of Florida — WestPaiaatSeash Br atnch •°°^ - 590O .Australian Ave . S :,i1 9 Y'Jast Palm 3e _ri1 F�334 4t Fd ' ate332 atm AUCM.'A ?a 3ON 1:+1 Ar Jw-M'JLtA NrXSO." :i ?u. XX a4J nt aw?a:.?:,) wccacLs c ; !Ia xxA,vswarta xC'wYr.�)ii i'ER PAKIS 1E.-Nit 312G1*11: ihx �4P.:=.419 Y'0.1 e,l}; a137r•d:'L LLQ6lA5 - Y(: )+altP IerlH ?T. OR A: Y.-0.SW,.' ryWLCY 23i5}'A!,1 f.3r. AC i:Syx-1:0? 1�C'V3,:'L^uf Ld5 fil5 :W'i x: ��. ACac:33saW_ t3:rJ S'MC Pr:ti 'M-+pa:V Milt ILEAMA?ER P.M FOX 4i i . A7,OI=1 FA.0 454=1 i5 };_c5) }AA.-di�i * C LIY^13. P.Y 214 GN0.(ipAirl: ✓; AC 01'-'1it.£fi2 T("�2j� § :Lx+ ?ii\: ^t. {.,�92,-it$6fG ?iF::0.'A) iix ':i-1ai-.n 3+2'.1 TAX61iY2!-9 'Ll.F 3WIl JPS P.O nOk .:)! .l ?SP1t. 1GiP fXitn.STO P.O. eQx cKtlsS .ti ar-:;x.r.r' rw:,L rt ?0. 5XJX R;o-?) AX,t '.R Eovt - :AC `�¢ 2.a 1•:113:% +4r.I. dSt^. :.YGory FAX,t H(4'&I"A ,T.' a,Q, y-yx lE'(A \C ?iJ4AUz.' rL. itpLc P�, 3pX L4J 0.0 AiC3FT.Sc GV„Ct'[µr,`05YASH i1M. AJsTW.V VAS .a^561561f_: MX Piil;AV:) $:SSrtt?(➢ [Y.S R:i-.141:'ri :il4P SIFT? p PHC 501.15}+Jgp 1 rz Tamer Construction ar�veresrnar2 Febrt4,;y 26, 2CT-7 27551EnAve arae;Hy; IndiaTl RivaP.dm:nis+atzQn t;a;rr5lex 1 Vero Beach, Fl. 32956 tavtxr: fndian R-Ner Couaty, F'. i PA. (772) W-6141 ArreAa9. FaxA 564-6143 ,o;,M A!tention: Mike RivNed On: '.1t?s is a proposal to furnish alb naterlals and labor as herein de;aibed (or the above nzmed project as per your recuev and conditions herein: PROPOSAL aHae a Bentley Ehy+sian Tip in lieu of specified carpet @ ;12,227, 00 c. Room # 1 .2-503, 564,505,506,507,5L8,509,810, 511 a. 4 ) - 1DSl /_2— log 0 J SEERACE 2,,,2G A�'jgrwED 4eoo® s:4ae:rs; fin ; �Yifi�tions t0$;tl_, lid Installed: . ,. . .. ____ � �.._.-" 1ie. wlln TZX Indus" NO Soho Lndude2 1 i I 1 'Rwi s -anitmais 5: None Rti ehQHntfl uSn� Addc.,�*-.i1a121^i: ane Ir Purchasers acceptance of .ha invent of *bis c:oposal whether by this form or othermse, incorporates all conditions of this proposal shown on this and the reverse side. All subje" to p+.'rcieser's acceptance by an authorized of$cer Or ayenr„ with:^. RM days f:-,M tha dare hereof. j 1FYOUa, CG+47R.ACTFGFAr IS NOTPFG'vfRF_D, ,Reapectfuily 3ubn3 ttad, l KINVO%, GNANDDATE 7H'5 F?019RSES1D5 ACOUSTI Engineering Compgny of Florida To S(CX1FY ACCEPTANCE THANX, YOU, 'jilt, 1?9fzrkf0)n STATE SALES TAX fJO71,4GLUJcOOM1' PMTFRALSA ES mrxaaun --eey sr,aer H^ee relrerse sTe hr [ony,L�p>; andasraotanx; 1 Mb7 PAG: f RECEIVED FEB 2. 6 2007 T1 MKIED Page 1 of 2 Dougherty , Michael J - (ORL) From: Lynn Van Duyne [Ivanduyne@songandassociates. com] Sent: Monday, February 19, 2007 3 : 32 PM To : Dougherty, Michael J - (ORL) 00 Cc: Steve Blum ; ADONADIO@aol. com Subject: FW: IRC- change carpet Please see final forwarded e-mail below. As I stated this morning , items 4 and 5 are the rooms getting the ALTERNATE CPT-8. Items 2 and 3 get the regular CPT-8. Item 1 gets CPT-7 . Tony , the the carpet change letter I received today does not have item 5 from this e-mail . Please call if anyone has more questions. Thanks , Lynn Song + Associates, Inc. P�vw Sfr1A5$'102 From : Lynn Van Duyne Sent: Wednesday, February 07, 2007 4 : 06 PM To: 'adonadio@aol .com' Subject: FW: IRC- change carpet Tony , Here is the info. Song + Associates, Inc. Lynn Van Dgne hnviortw4w 14a,xac Str#S;:d'£3• t : �St.G35,taR'. From : Lynn Van Duyne [mailto: Ivanduyne@songandassociates.com] Sent: Wednesday, October 25, 2006 9 : 39 AM To: Mike Dougherty Cc: Steve Blum ; Kathy Swanson ; Jeanne Kenaston ; anthony@donadio-arch .com . 3/12/2007 Page 2 of 2 Subject: IRC- change carpet Mike , Per our meeting on Monday October 23, 2006 the following offices will have their carpet changed as outlined below; These are the standard CPT-8 ; 1 . Joined offices 1 .2 . 205 , 1 .2 . 203 will have now have CPT-7. PNT-1 will be on all walls and soffits. (clerk of the court) 2 . Office 2 . 1 .216 will now have CPT-8. (tax collector) 3. Office 2 . 1 .615 will now have CPT-8. (Prop. appraiser) These offices will also have upgraded wood furniture and office 1 . 2 . 203 will have a 16 foot conference table. Remember ONLY these areas are called CPT-8 ALTERNATE, which is Bentley, elysian tip, color vestal 887944 ; 4. Commissioners office and assistants area-Building 1 .2 - 50335045505, 506, 507, 508, 5099510, 51 1 . All paint in these areas to be PNT-1 , including soffits . 5 . Building 1 .2 - 105 , 511 , 108 no borders, all PNT- 1 . Thank you , L nn Van Duyne LI L IY. lv W 3/ 12/2007 Page 1 of 1 Dougherty, Michael J - (ORL) From : Lynn Van Duyne [Ivanduyne@songandassociates. com] Sent: Wednesday, October 25, 2006 9 : 39 AM To: Dougherty , Michael J - (ORL) Cc: Steve Blum; Kathy Swanson ; Jeanne Kenaston ; anthony@donadio-arch . com . Subject: IRC- change carpet Mike , Per our meeting on Monday October 23 , 2006 the following offices will have their carpet changed as outlined below; 1 . Joined offices 1 .2 . 205 , 1 . 2 . 203 will have now have CPT-7. PNT- 1 will be on all walls and soffits. (clerk of the court) 2 . Office 2 . 1 .216 will now have CPT-8. (tax collector) 3. Office 2 . 1 .615 will now have CPT-8. (Prop. appraiser) These offices will also have upgraded wood furniture and office 1 .2 .203 will have a 16 foot conference table. Thank you , Lynn Van Duyne 0 Lynn Van Duyne Song & Associates Interior Designer 400 Australian Avenue South 6th Floor West Palm Beach, FL 33401 Ivanduyne@songandassociates.com tel: (561) 655-2423 w .songandassociates.com fax: (561) 655-1482 3/ 12/2007