HomeMy WebLinkAbout2009-046 CHANGE ORDER NO . 3
DATE OF ISSUANCE : EFFECTIVE DATE :
OWNER : Indian River County
CONTRACTOR : OCEAN GATE GENERAL CONTRACTORS INC .
Project : WABASSO BEACH PARK RESTORATION
OWNER ' s Bid No . 2008032 OWNER ' s Project No . 0612
ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents :
1 . Description : Relocate and Repair Existing Life Guard Station Including Stairs , Electrical ,
and Phone Service :
Reason : The project was originally bid including the relocation of the existing lifeguard station
to a position that was determined based upon permit conditions and design of the restored
park facilities . With the first move the station needed repairs . Subsequently the Recreation
Department requested an alternate location . This second move further resulted in the need for
additional repairs . Consequently the determination to relocate the station and the necessity to
make the repairs was made after the contract was awarded , which accordingly requires this
change order.
ADDITION to the Contract Price = $ 99550 . 57
2 . Description : Contractor' s Bond , Overhead , and Profit Costs :
Reason : To provide an amount for the contractor' s overhead management and profit cost at
10 % and bond premium cost of 2 %
ADDITION to the Contract Price = $ 1 , 146 . 07
The summary change in Contract Price is :
Item1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . $ 9 , 550 . 57
1 , 146 . 07
Item 2 . . . . . . . . . . . . . . . . . . . . $
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
NET ADDITION to the Contract Price . . . . . . . . . . . . . . . . . . . . . $ 10 , 696 . 64
Attachments : Contractor' s Work Sheets for Above Items
CHANGE IN CONTRACT PRICE
Descri tion Amount
Ori inal Contract Price $ 858 , 200944
Net Increase from previous $ 55 , 928 . 97
Chan e Order No . 1 & 2
Contract Price prior to this Chan a Order: $ 9143129041
Net increase of this Change Order : $ 10 , 696 . 64
Contract Price with all approved Change $924._
Orders :
Wabasso Beach Park Restoration
Change Order #3 - Page 1 of 2
FAPublic Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #3\Change Order
Form #3 . doc
CHANGE ORDER NO . 3
CHANGE /N CONTRACT TIME
Description Time Date
Original Contract Time for Final Completion : 210 calendar days 4/20/2009
Net change from previous
Change Order No . 1 & No . 2 30 calendar days N /A
Contract Time for Final Completion prior to
this Change Order: 240 calendar days 5/20/2009
Net increase this Change Order for Final
Completion : NONE ----
Contract Time for Final Completion with
all approved Change Orders : 240calendar days 5/20/2009
ACCEPTED : RECOMMENDED : '
B
B �f�i .
( Ig re OCE N ATE G NEER ( Signature )
GENERAL CONTRACTORS Michael P . Walther, P . E . ,
Coastal Technology
Corporation
( Name and Title )
Date : Date :
RECOMMENDED : APPR D :
By : By
ENGINEER ( Signature ) OWNER ( Signature )
James Davis , P . E . , Indian River Wesley S . Davis
County Director , Public Works Chairman , Board of County
Commissioners
Date : " " ; - t'OCA Date : February 17 , 2009
Wabasso Beach Park Restoration
Change Order #3 - Page 2 of 2
F :\Public Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #3\Change Order