HomeMy WebLinkAbout2009-009 CHANGE ORDER NO . 1 i goo 9 _ 0e� y
DATE OF ISSUANCE : EFFECTIVE DATE :
OWNER : Indian River County
CONTRACTOR : OCEAN GATE GENERAL CONTRACTORS INC .
Project: WABASSO BEACH PARK RESTORATION
OWNER' s Bid No . 2008032 OWNER ' s Project No . 0612
ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents :
1 . Description : Sidewalk Revisions :
Reason : Revisions to the sidewalk from that required by the bid documents including
relocation of the crosswalk , addition of required ADA truncated domes , changes in the
maximum allowable slopes , elevations , and locations
ADDITION to the Contract Price = $ 1 , 639 . 60
2 . Description : Additional Maintenance of Traffic at the A- 1 -A Park Entrance :
Reason : This was a condition of the County right of way permit that was issued after the
contract award , including cost for installing and maintenance of traffic control items .
ADDITION to the Contract Price = $2 , 200 . 00
3 . Description : Furnish and Install Truncated domes at Park Entrance :
Reason : These were not included in the original bid documents , and are an ADA required
feature as per the right of way permits , work includes 200 square feet of domes .
ADDITION to the Contract Price = $6 , 806 . 00
4 . Description : Revised Boardwalk Bench and Pickets : :
Reason : The building permit required this item that was not included in the orginal bid
documents . There are 4 benches on the boardwalk , the pickets are required for each to
prevent a child from falling off the boardwalk .
ADDITION to the Contract Price = $898 . 00
5 . Description : Revised Pavilion elevations :
Reason : The change in sidewalk slopes and elevations from that required by the original
bid documents required the change in elevation for the pavilions . This cost includes the
addition survey and staking work require for the pavilion changes .
ADDITION to the Contract Price = $345 . 00
6 . Description : Door and Frame Finish Revisions :
Reason : The finish for the stainless steel doors and frames was revised and therefore
created a credit for the less expensive finish .
CREDIT to the Contract Price = $ 1 , 000 . 00
Wabasso Beach Park Restoration
Change Order # 1 - Page 1 of 3
FAPublic Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #1 \Change Order
form #1 .doc
._y
CHANGE ORDER NO . 1
7 . Description : Extension of the FPL Service to the Lift Station :
Reason : After the contract was awarded FPL revised the location of the required electrical
service location that is to serve the lift station . This includes the addition of about 225 lineal
feet of 2 " conduit , wiring , layout and survey work with related incidentals all as necessary to
provide electrical service to the lift station .
ADDITION to the Contract Price = $ 11 , 063 . 88
8 . Description : Furnish and Install an Attic Access Panel
Reason : After the project was bid the building department permit issued required a 22 " X
30 " access panel to the attic that wasn 't included in the original award .
ADDITION to the Contract Price = $735 . 20
9 . Description : Decorative Lightning Rod :
Reason : Delete this non functional item .
CREDIT to the Contract Price = $75 . 00
10 . Description : Substitute Toilet Partition Material :
Reason : To provide a more graffiti resistant toilet partition than what was specified in the
original bid documents .
ADDITION to the Contract Price = $ 19605 . 70
11 . Description : Furnish and Install ADA Compliant Boardwalk Handrails :
Reason : The original bid documents included a handrail that did not meet code
requirements and therefore must be replaced with a compliant type .
ADDITION to the Contract Price = $ 111933 . 20
12 . Description : Contractor' s Bond , Overhead , and Profit Costs :
Reason : To provide an amount for the contractor' s overhead management and profit cost at
10 % and bond premium cost of 2 %
ADDITION to the Contract Price = $4, 338 . 19
13 . Description : Time Extension : Thirty ( 30 ) calendar days .
Reason : The above increased work requires addition time to complete
The change in Contract Price is determined as follows :
( 1 ) DELETE . . . . . . . . . " . . " . . . N . . . . . . . . . . . . . . . . . . . . . . . I . . . .
. . . . . . . . = ( $ 1 , 204 . 00)
(2 ) ADD . . . . . . . . . . . . . . . . . . . . . . . . _ $41 . 693 . 77
DIFFERENCE _ $40 , 489 . 77
NET ADDITION to the Contract Price = $401489 . 77
Attachments : Contractor' s Work Sheets for Above Items
Wabasso Beach Park Restoration
Change Order # 1 - Page 2 of 3
R\Public Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #1 \Change Order
form #1 .doc
CHANGE ORDER NO . 1
CHANGE IN CONTRACT PRICE
Description Amount
Original Contract Price $ 8583200 . 44
Net Increase ( Decrease ) from previous
-Change Orders No , N/A to N/A : None $0 . 00
Contract Price prior to this Change Order: $ 858200 , 44
Net increase of this Change Order: $40 , 489 , 77
Contract Price with all approved Change $ 898 , 690 . 21
Orders :
CHANGE IN CONTRACT TIME
Description Time
Original Contract Time for Final Completion : 210 calendar days 4/20/2009
Net change from previous Change Orders
No . N/A to N /A for Final Completion : 0 calendar days N/A
Contract Time for Final Completion prior to
this Change Order: 210 calendar days 4/20/2009
Net increase this Change Order for Final
Completion : 30 calendar days ----
Contract Time for Final Completion with
all approved Change Orders : 240calendar days 5/20/2009
ACCEPTED : RECOMMENDED : APP
By ' By : 7
( Igna ure ) OCEAN GATE ENGINEER ( Signature ) AR ( Signature )
GENERAL CONTRACTORS Michael P . Walther, P . E . , Anthony J . Donadio , AIA
Coastal Technology Donadio and Associates
P Corporation Architect
( N a and Title ) /
Date : ns' Date : Lo � dI j Date : �✓
RECOMMENDED : APPROVED :
B r4
ENG EER ( Signature ) OWNER ( Signature )
James Davis , P . E . , Indian River Wesley S . Davis
County Director, Public Works Chairman , Board of CoLinty ,
Cor1m%fisSior1e1rS
Date : January 13 , 2009 Date: . �Ianuar13 2009
Wabasso Beach Park Restoration
Change Order # 1 - Page 3 of 3
FAPublic Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #1 \Change Order
form #1 .doc