HomeMy WebLinkAbout2009-009 CHANGE ORDER NO . 1 i goo 9 _ 0e� y DATE OF ISSUANCE : EFFECTIVE DATE : OWNER : Indian River County CONTRACTOR : OCEAN GATE GENERAL CONTRACTORS INC . Project: WABASSO BEACH PARK RESTORATION OWNER' s Bid No . 2008032 OWNER ' s Project No . 0612 ENGINEER : Indian River County You are directed to make the following changes in the Contract Documents : 1 . Description : Sidewalk Revisions : Reason : Revisions to the sidewalk from that required by the bid documents including relocation of the crosswalk , addition of required ADA truncated domes , changes in the maximum allowable slopes , elevations , and locations ADDITION to the Contract Price = $ 1 , 639 . 60 2 . Description : Additional Maintenance of Traffic at the A- 1 -A Park Entrance : Reason : This was a condition of the County right of way permit that was issued after the contract award , including cost for installing and maintenance of traffic control items . ADDITION to the Contract Price = $2 , 200 . 00 3 . Description : Furnish and Install Truncated domes at Park Entrance : Reason : These were not included in the original bid documents , and are an ADA required feature as per the right of way permits , work includes 200 square feet of domes . ADDITION to the Contract Price = $6 , 806 . 00 4 . Description : Revised Boardwalk Bench and Pickets : : Reason : The building permit required this item that was not included in the orginal bid documents . There are 4 benches on the boardwalk , the pickets are required for each to prevent a child from falling off the boardwalk . ADDITION to the Contract Price = $898 . 00 5 . Description : Revised Pavilion elevations : Reason : The change in sidewalk slopes and elevations from that required by the original bid documents required the change in elevation for the pavilions . This cost includes the addition survey and staking work require for the pavilion changes . ADDITION to the Contract Price = $345 . 00 6 . Description : Door and Frame Finish Revisions : Reason : The finish for the stainless steel doors and frames was revised and therefore created a credit for the less expensive finish . CREDIT to the Contract Price = $ 1 , 000 . 00 Wabasso Beach Park Restoration Change Order # 1 - Page 1 of 3 FAPublic Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #1 \Change Order form #1 .doc ._y CHANGE ORDER NO . 1 7 . Description : Extension of the FPL Service to the Lift Station : Reason : After the contract was awarded FPL revised the location of the required electrical service location that is to serve the lift station . This includes the addition of about 225 lineal feet of 2 " conduit , wiring , layout and survey work with related incidentals all as necessary to provide electrical service to the lift station . ADDITION to the Contract Price = $ 11 , 063 . 88 8 . Description : Furnish and Install an Attic Access Panel Reason : After the project was bid the building department permit issued required a 22 " X 30 " access panel to the attic that wasn 't included in the original award . ADDITION to the Contract Price = $735 . 20 9 . Description : Decorative Lightning Rod : Reason : Delete this non functional item . CREDIT to the Contract Price = $75 . 00 10 . Description : Substitute Toilet Partition Material : Reason : To provide a more graffiti resistant toilet partition than what was specified in the original bid documents . ADDITION to the Contract Price = $ 19605 . 70 11 . Description : Furnish and Install ADA Compliant Boardwalk Handrails : Reason : The original bid documents included a handrail that did not meet code requirements and therefore must be replaced with a compliant type . ADDITION to the Contract Price = $ 111933 . 20 12 . Description : Contractor' s Bond , Overhead , and Profit Costs : Reason : To provide an amount for the contractor' s overhead management and profit cost at 10 % and bond premium cost of 2 % ADDITION to the Contract Price = $4, 338 . 19 13 . Description : Time Extension : Thirty ( 30 ) calendar days . Reason : The above increased work requires addition time to complete The change in Contract Price is determined as follows : ( 1 ) DELETE . . . . . . . . . " . . " . . . N . . . . . . . . . . . . . . . . . . . . . . . I . . . . . . . . . . . . = ( $ 1 , 204 . 00) (2 ) ADD . . . . . . . . . . . . . . . . . . . . . . . . _ $41 . 693 . 77 DIFFERENCE _ $40 , 489 . 77 NET ADDITION to the Contract Price = $401489 . 77 Attachments : Contractor' s Work Sheets for Above Items Wabasso Beach Park Restoration Change Order # 1 - Page 2 of 3 R\Public Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #1 \Change Order form #1 .doc CHANGE ORDER NO . 1 CHANGE IN CONTRACT PRICE Description Amount Original Contract Price $ 8583200 . 44 Net Increase ( Decrease ) from previous -Change Orders No , N/A to N/A : None $0 . 00 Contract Price prior to this Change Order: $ 858200 , 44 Net increase of this Change Order: $40 , 489 , 77 Contract Price with all approved Change $ 898 , 690 . 21 Orders : CHANGE IN CONTRACT TIME Description Time Original Contract Time for Final Completion : 210 calendar days 4/20/2009 Net change from previous Change Orders No . N/A to N /A for Final Completion : 0 calendar days N/A Contract Time for Final Completion prior to this Change Order: 210 calendar days 4/20/2009 Net increase this Change Order for Final Completion : 30 calendar days ---- Contract Time for Final Completion with all approved Change Orders : 240calendar days 5/20/2009 ACCEPTED : RECOMMENDED : APP By ' By : 7 ( Igna ure ) OCEAN GATE ENGINEER ( Signature ) AR ( Signature ) GENERAL CONTRACTORS Michael P . Walther, P . E . , Anthony J . Donadio , AIA Coastal Technology Donadio and Associates P Corporation Architect ( N a and Title ) / Date : ns' Date : Lo � dI j Date : �✓ RECOMMENDED : APPROVED : B r4 ENG EER ( Signature ) OWNER ( Signature ) James Davis , P . E . , Indian River Wesley S . Davis County Director, Public Works Chairman , Board of CoLinty , Cor1m%fisSior1e1rS Date : January 13 , 2009 Date: . �Ianuar13 2009 Wabasso Beach Park Restoration Change Order # 1 - Page 3 of 3 FAPublic Works\Cliff Suthard\Wabasso Beach Park\CONSTRUCTION\CHANGE ORDERS\CHANGE ORDER #1 \Change Order form #1 .doc