CHANGE ORDER NO . 001 �5 - () 1 ;5
DATE OF ISSUANCE : November 29 , 2004
EFFECTIVE DATE : November 29 , 2004
OWNER: Indian River County
CONTRACTOR : OKLAWAHA FARMS , INC
Project : HARMONY OAKS MITIGATION PROJECT
OWNER's Project No . 6045
OWNER/ENGINEER : Indian River County
You are directed to make the following changes in the Contract Documents :
1 . Description : Delete 12 Red Bays and add 12 Laurel Oaks in Planting Zone B .
Reason : Red Bay trees are not available .
The change in Contract Price is determined as follows:
Deduct 12 Red Bays ( Bid Item No . 3 . 02B ) = ( 12 each )($80 each ) = ($ 960 )
Add 12 Laurel Oaks ( Bid Item 3 . 02A) = ( 12 each )($ 119 each ) _ $ 1 ,428
ADDITION to the Contract Price = $ 1 ,428 = $960 = $468 . 00
2 . Description : Deduct 64 Red Bays and add 32 Laurel Oaks and 32 Red Maples in
Planting Zone C .
Reason : Red Bay trees are not available .
The change in Contract Price is determined as follows:
Deduct 64 Red Bays (Bid Item No . 3 . 038 ) = (64 each )($70 each ) = ($4 ,480 )
Add 32 Laurel Oaks (Bid Item 3 . 03C ) = (32 each )($ 119 each ) = $ 3 , 808
Add 32 Red Maples (Bid Item 3 . 03A) = (32 each )($ 119 each ) = $ 3 , 808
ADDITION to the Contract Price = $39808 + $3 , 808 - $4,480 = $3 , 136 . 00
3 . Description : Deduct 93 Chain Ferns and add 93 Swamp Ferns in Planting Zone B .
Reason : Chain Ferns are not available .
The change in Contract Price is determined as follows:
Deduct 93 Chain Ferns (Bid Item No . 3 . 02E ) = (93 each )($3 . 20 each ) = ($297 . 60 )
Add 93 Swamp Ferns (Bid Item 3 . 02D ) _ (93 each )($2 . 80 each ) = $260 .40
DEDUCTION from the Contract Price = $260 .40 - $297 . 60 = ($37 .20)
4 . Description : Deduct 531 Chain Ferns and add 531 Swamp Ferns in Planting Zone
C .
Reason : Chain Ferns are not available .
The change in Contract Price is determined as follows:
Deduct 531 Chain Ferns (Bid Item No . 3 . 03F ) = (531 each )($ 3 . 70 each ) = ($ 1 , 964 . 70 )
Add 531 Swamp Ferns (Bid Item 3 . 03E ) = (531 each )($2 . 80 each ) =$ 1 ,486 . 80
DEDUCTION from the Contract Price = $ 1 ,486 .80 = $ 1 ,964. 70 = ($477 .90)
Change Order #001
Change Order = 1
F :\PublicWorks\KeithM\Stormwater Projects\Harmony Oaks Mitigation Project\Change Order #001 .doc Last revised 9/27/01
r
k '
5 . Description : Closeout Bid Item No . 4 . 01 , Construction Contingency , to reflect the
unused portion .
Reason : All of the construction contingency was not used .
The change in the contract price is determined as follows:
Original amount of Construction Contingency ( Bid Item No . 4 . 01 ) _ $20 , 000
Amount of Construction Contingency actually used = ($ 3 , 500 )
DEDUCTION from the Contract Price = $20 ,000 - $3 , 500 = ($ 169500 . 00)
Attachments : (List documents supporting change )
None
CHANGE IN CONTRACT PRICE For Part 1 of the Contract) :
Description Amount
Original Contract Price for Part 1 $ 1199194 . 94
Net Increase ( Decrease ) from previous
Change Orders No . N/A to N/A : $-0-
Contract Price prior to this Change Order: $ 119 , 194 . 94
Net DECREASE by this Change Order: $ 139411 . 10
Contract Price with all approved Change
Orders . $ 1050783 . 84
CHANGE IN CONTRACT TIMES For Part 1 of the Contract
Description Time
Original Contract Time ( Final Completion ) July 28 , 2004 ( 120
calendar days )
Net change from previous Change Orders
No . N/A to N/A : -0- days
Contract Time prior to this Change Order: 120 calendar days
Net increase decrease this Change Order: 34 calendar days
Contract Time for Part 1 of the Contract September 1 , 2004
with all approved Change Orders : 154 calendar da s
ACCEPTED : RECOMMENDED :
firi G
By. By
"Jill
dF
CT nature) EN NEER (Signature) i' nathre v
Keith McCully, P . E . , Indian �� firman ,
IQ River County Stormwater d;.0 ty C91sioners
li �, �s r Engineer `/ 'o
(Name and Title) ` � !! ' ' " " ' p���
Date : Lill 1l' - Z fes- - Dafi j - 5
Change Order #001
Change Order 2
FAPublic Works\KeithM\Stormwater Projects\Harmony Oaks Mitigation Projpct\Change Order #001 .doc Last revised 9/27/01