INDIAN RIVER COUNTY PARKS MAINTENANCE COMPLEX
SUPPLEMENTAL No . 3 to WORK ORDER NO . 1
TO THE
PROFESSIONAL CIVIL ENGINEERING SERVICES AGREEMENT
WITH
CARTER ASSOCIATES , INC .
This Supplemental No . 3 to Work Order No . 1 is in accordance with the existing
AGREEMENT dated January 9 , 2007 and the extension thereof, between Carter
Associates , Inc . ( ENGINEER) and Indian River County (COUNTY) .
This Supplemental No . 3 to Work Order No . 1 amends the agreement as follows :
SECTION I — PROJECT LIMITS
Consultant services are required to design a fiber optic interconnect plan and for observation
of the installation of conduits and pull boxes for the new Indian River County Parks Maintenance
Complex .
SECTION II — SCOPE OF SERVICES
The Scope of Services for this Supplemental No . 3 to Work Order No . 1 is to perform the
following tasks as requested by the County :
Fiber Optic Interconnect Conduit :
• Revise the Utility Plan sheet ( U - 1 ) to add a fiber optic splice vault at the east side of the
proposed western driveway onto 77 `x' Street, and interconnect conduits running to the
west .
0 Revise the Water Details sheet ( U - 4 ) to include an interconnect plan showing conduits
and pull boxes from the project site to the 58 "' Avenue connection point .
• Add pull box and splice vault details on sheet ( U4 ) .
C :ADocuments and Settings\SeanklTocal SettingsV'Temporary Internet Files\OI X906\0701 Supplemental No 3 to WO No I Carter 06-
10-09 . doc
PAGE TWO
Supplemental No . 3 to Work Order No . I Carter Associates , Inc .
June 10 , 2009
SECTION III - TIME FOR COMPLETION
Supplemental design tasks shall be completed within 30 calendar days from the date of
execution of this Supplemental No . 3 to Work Order No . 1 and construction tasks shall
run concurrently with construction work for Indian River County Parks Maintenance
Complex .
SECTION V - COMPENSATION
The COUNTY agrees to pay , and the ENGINEER agrees to accept , a fee for services
rendered according to the " Scope of Services " and further identified in all the Sections
of this Supplemental No . 3 to Work Order No . 1 , a Lump Sum fee of $ 2 , 394 . 00 for
design services and hourly not - to - exceed $ 562 . 00 for construction related services for a
total of $ 2 , 956 . 00 .
All and/or any additional services not described hereon shall be pre - approved by the
COUNTY . Approved additional services shall be invoiced at the rates disclosed in the
approved fee schedule with the ENGINEER for the 2008 — 2009 contract year .
All invoicing and payments shall be in accordance with the original Professional Civil
Engineering Services Agreement with the COUNTY and as stated hereon . Invoices
shall include the work order and project number, invoice number related to this work
order , original contract amount, current billing amount and retainage amounts .
The AGREEMENT is hereby amended as specifically set forth herein . All remaining
sections of the AGREEMENT shall remain in full force and effect , and are incorporated
herein .
C :ADocuments and Settings\SeanM\Local SettingsUemporary Internet Piles\01, K90B\0701 Supplemental No 3 to WO No 1 Carter 06-
10-09. doc
PAGE THREE
Supplemental No . 3 to Work Order No . 1 Carter Associates , Inc .
June 10 , 2009
Attachment : Carter Associates Scope of Services (Exhibit A)
OWNER Carter Associates , Inc .
BOARD OF COUNTY COMMISSIONERS
INDIAN RIVER COUNTY, FLORIDA
zztpw OW
.� 2- Z <•1
(Signature) (Signature)
Wesley S . Davis , Chairman (-) (fC/ aCti �'
(Printed name and title)
Approved by BCC JrzANANAAAAD.c2 2 0 0 9
ATTEST:
Jeffrey K. Barton , Clerk of Circuit Court Witn ed bye (Carter Associates , Inc )
ANN �
Deputy C:Ierk inted n me) it il, S
Approved as to For and gal Sufficiency :
William . Co has I , COUNTY Attorneyseph A. aird , COUNTY
ministrator
C :ADocuments and Settings\SeanM\Local Settings\Temporary Internet Files\OLK9013\0701 Supplemental No 3 to WO No I Carter 06 -
10-09 . doe
June 8 , 2009
JUN 0 9 / 00 "
Mr . Christopher J . Kafer, Jr. , P . E . , County Engineer
Indian River County Engineering Division
1801 27`h Street
Vero Beach, FL 32960
Re : Indian River County Parks Maintenance Complex (CAI Project No . 05 -60E)
Supplemental No . 3 to Work order No . 1 to the Professional Civil Engineering Services Agreement
Dear Chris :
We are pleased to present this proposal for additional services relative to designing a fiber optic interconnect
plan and observing the installation of conduits and pull boxes from the existing fiber optic splice vault at the
north-east corner of 58 `h Ave and 77"' Street to the project site . The proposed interconnect conduit is needed
to accommodate the County ' s fiber optic service installation to the new Parks Maintenance Division office
building . The fiber optic facilities along 58`h Ave were only recently constructed and it is at the direction of
the County ' s Telecommunications Division that the proposed off-site utility extension be included in this
project ' s scope of work.
All provisions of the original Work Order No . 1 to the Professional Civil Engineering Services Agreement
(dated 1 /9/07), as well as Supplemental No . 1 (dated 6/5 /07) and Supplemental No . 2 (dated 9/9/08) ,
shall
remain in full force and effect, unless otherwise specifically modified herein . A man-hour fee estimate
is
attached as Exhibit "A" for your use . The following describes our proposed scope of services and terms of
agreement between Carter Associates, Inc . (Engineer) and Indian River County (County) :
Fiber Optic Interconnect Conduit :
In general , the design plans will be extended and revised to add two 2 " PVC conduits with pull boxes every
3004eet, connecting from the existing fiber optic splice vault at the north-east corner of 58t1' Ave and 77`
'
Street and ending at a new splice vault at the project frontage on 77 `h Street . The project documents will be
modified as follows :
• Revise the Utility Plan sheet (U4 ) to add a fiber optic splice vault at the east side of the proposed
western driveway onto 77`h Street, and interconnect conduits running to the west .
• Revise the Water Details sheet (U4) to include an interconnect plan showing conduits and pull
boxes from the project site to the 58 `h Ave connection point.
• Add pull box and splice vault details on sheet U4 .
Assumptions •
In developing this proposal, the following assumptions have been made and deviation from these
assumptions may require additional expenditures on behalf of the County to the Engineer .
• Construction administration is limited to reviewing the contractor ' s shop drawing submittals for
conduits and pull/splice boxes and observing the installation of the proposed fiber optic conduits .
Engineer shall notify the County if lack of contractor cooperation or other causes prevent Engineer
from performing the specified construction phase services .
Compensation :
Supplemental No . 3 fees will be invoiced on a percent complete lump sum basis . The total amount to be
billed shall not exceed $2 ,956 .00 unless authorized by an additional written agreement, as follows :
Revise Design Plans $2, 394. 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Construction Phase Services .$562. 00
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ffiffiffi
TOTAL PROFESSIONAL SERVICES $2, 956. 00
Please call on me should you have any questions or concerns regarding our proposed scope of work or terms
of agreement .
Sincerely,
G . Sean McGuire , P . E .
Project Manager
Attachments - Exhibit "A" (man -hour fee estimate)
N : \GSM \P\05 -60E IRC Parks Complex\Agreements\Proposal6- 8-09 . doc f
Exhibit " A "
Indian River County
Parks Maintenance Complex
Supplemental No . 3 (Add interconnect conduit for fiber optic services)
Fee Estimate (rate schedule as per CAI continuing services agreement with IRC)
6/8/2009
$ 140 . 00 $ 110 . 00 $ 85 . 00 $ 57 . 00
Eng . I ,Prin . Eng . II , P . E . End . Tech. Inspector Subtotal
Patrick ISean Domenic Bryan
Fiber Optic Interconnect Conduit
Research existing splice box location 1 2 $224 . 00
Plan Revisions 5 8 $ 1 ,230 . 00
Coord/Meetings/Incidentals 2 6 $ 940000
Construction Phase Services 2 6 $ 562 . 00
Total = $ 2 ,956 . 00