HomeMy WebLinkAbout2004-136 t INDIAN RIVER COUNTY, FLORIDA
CHANGE ORDER NO. 1
PROJECT NO , 0386
ACCOUNT NO : 13617237 -066510-04018
PROJECT : Pelican Island National Wildlife Refuge Upland Restoration Project
CONTRACTOR NAME/ADDRESS : Sitewerks Inc .
4045 43rd Avenue
Vero Beach, FL 32960
DATE : June 2 , 2004
ITEM DESCRIPTION OF PRICE PRICE
NO , CHANGE INCREASE DECREASE
1 Lowering the target depth $259464 . 69
of the lakes and ponds by
0 . 6 feet
Total Increase/Decrease $ 25 ,464 . 69 0 . 00
NET CHANGE IN AMOUNT (+$25 ,464 . 69)
ORIGINAL CONTRACT PRICE $ 491 , 916 . 63 TIME 90 DAYS
BEGIN DATE 5/ 10/04
DATE OF SUBSTANTIAL COMPLETION 8/7/04
DATE OF FINAL COMPLETION 8/22/04
CURRENT CONTRACT PRICE $491 , 916 . 63 TIME 90 DAYS
BEGIN DATE 5 / 10/04
DATE OF SUBSTANTIAL COMPLETION 8/7/04
DATE OF FINAL COMPLETION 8/22/04
NET CHANGE PRICE/TIME FROM THIS CHANGE ORDER NO . 1 (+$25 ,464 . 69) 11 DAYS
NEW CONTRACT PRICE/TIME INCLUDING THIS CHANGE ORDER $ 517 , 381 . 32 101 DAYS
DATE OF SUBSTANTIAL COMPLETION 8/ 18/04
DATE OF FINAL COMPLETION 9/2/04
F : \Engineering\Capital Projects\0386-Pelican Island Upland Restoration\0386 CO # 1 -Sitewerks-06-02-04-mag . doc
Page 1 of 2
INDIAN RIVER COUNTY, FLORIDA
CHANGE ORDER NO. 1
PROJECT NO. 0386
APPROVAL
ENGINEERS RECOMMENDATION:
I have examined the above changes . They are necessary to satisfactorily complete the Contract . The price changes
are reasonable d I recommend that the changes be made .
- - D
Christophe . Ka
f740OTr. , P Date
County gineer
I agree to the amendment of the Pelican Island National Wildlife Refuge Upland Restoration Project Contract as
indicated on the attached ( 1 ) one page Change Order No . 1 . This Change Order shall become a part of the Pelican
Island National Wildlife Refuge Upland Restoration Project Contract and incorporated therein.
SITEWERKS , INC . INDIAN RIVER COUNTY, FLORIDA
(Nam nd Title of Signatory) Caroline D . Ginn, Chai an
Witnessed by: Approved by BCC June 8 , 2004
Attest :
Jeffrey K. Barton, Clerk of C=ircuit
4*0
' ` 4seMtiy dY14v i riM1r -.U..
V R Tr
ounty Attorney Deputy Clerk '
;. �
Approved as to Form and Legal Sufficiency
J epA
h . Baird,
ounty Administrator
F : \Engineering\Capital Projects\0386-Pelican Island Upland Restoration\0386 CO # 1 -Sitewerks-06-02-04-mag . doc
Page 2 of 2