ATTACHMENT # 1 3a
GIANNETTI CONTRACTING
Main Office CORPORATION Florida Office
6340 Sims Dr. 2660 N .W. 150 Court, Ste. 108
Sterling Heights, Michigan 4831 $ Pompano Beach, Florida 33069
Phone : (586) 268-2090 Phone: (954) 972-8104
Fax: (586) 268.7099 Fax: (954) 972-8108
Lic.# CB-CO57979 BVILDING • DEVELOPMENT • INFRASTRUCTURE Lia# CU-CO56976
August 3, 2007
Eckler Engineering
4700 Riverside Dr. Suite 110
Coral Springs, FL 33067
ATTN: Evan Kennedy
RE: Mitigated Sewer Rockridge Subdivision Indian River County project # UCP 2521
Dear Mr. Kennedy,
Please find listed below additional casts for the work as described below, as requested by the owner.
Item # 1 Clear and grub canal banks and easement and sod @ treatment facility.
Bahia sod restoration 900000 SF $ 0.20 $ 16,000.00
Trucking off debris and excess soil 600 CY $ 5.00 $ 4,000, 00
Labor and equipment for grading and excavation 10000 SY S 2.00 $ 20,000.00
Total for Item # 1 $ 42,000.00
Item # 2 Remove existing culverts and replace with 12" ADS pipe @ driveways crossings on vacuum sewer side
esirlwalind 49 1 r nor driveways = approximately 3,100 LF,
12" ADS pipe materials 3100 S 5.83 $ 18,073.00
12" ADS Couplings 104 EA $ 5.83 $ 606.32
Remove and dispose ex culverts $ 2. 00 $ 6,200.00
Lahar and equipment 3100 LF 10.00 $ 31 ,0091
Estimated Total for 7t (!!
$ 55,879.32
Price per 2 $ 18.03
Item ##33 remove ex CMP drainage culvert @ roadways crossings and replace with hardie pipe.
Remove anAai+'pOca-er culvert 446 LF $ 2. 00 $ 87.00
Connect new CMP to ex structures 16 EA $ 500.00 S✓9'Q , 00
Labor and equipment to install 12" - 16" hardle pipe 446 LF .00 S 4,460.00
12" hardie pipe materials only $ 12,99 $ 2,078.40
15" hardle pipe materials only S 12.99 $ 2,675.94
15" hardie pipe materials only 80 LF 14. 31 $ 1 , 144.80
Asphalt restoration ( at prices) 250 LF $ $ 26,00D.00
Sidewalk r n at contract unit prices) 5 LF $ 44. 00 000l
Total for item # 3 $ 483471 .14 pg
Connect now CMP to ex structures includes removing ox GMP from invert and making new connection to ex structure,
and cementing new CMP to inlet.
Item # 4 provide electronic ball markers at all fittings on vacuum sewer.
Material costs only no charge for labor, 439 markers @ $ 11 .70 each
Total for Item # 4 S 61136.30
Item S 6 increaaod ARV from 2" to 4" in size as per previous request. S 2,726,07
Quantities are estimated and to be billed on actual measurements installed.
Thank you and lease call should you have an
y p y y questions.
Sincerely
Ricky L Glannetti
Project Manager
CC: Larry Brown IRC
File
ATTACHMENT
SECTION 00450
CHANGE ORDER FORM
CHANGE ORDER NO. 01
DATE: September 6. 2007 CONTRACTOR : Giannetti contractors Coro
OWNER: INDIAN RIVER COUNTY AGREEMENT DATE : May 1 2007
PROJECT NAME: Rockridge Subdivision Mitigated Sewer Replacement
The following changes are hereby made:
1 ) Item # 1 Clear, stabilize and sod 161h St. canal.
2) Add 439 ball markers.
3) Change 2" ARV to 4" ARV.
Original CONTRACT PRICE $ 5. 782. 621 00
Current CONTRACT PRICE ADJUSTED by previous CHANGE ORDER $ N/A
Net Increase (Decrease) Resulting from this CHANGE ORDER $ 49.861 . 37
The current CONTRACT PRICE including this CHANGE ORDER $ 5.832.482 37
ORIGINAL CONTRACT TIME : March 16 2009 No. Days 630
Current CONTRACT TIME adjusted by previous CHANGE ORDER No. Days N/A
Net Increase (Decrease) Resulting from this CHANGE ORDER No. Days 0
Current CONTRACT TIME Including this CHANGE ORDER No. Days 630
CHANGES ORDERED :
I . GENERAL
Misc. additions to contract. .
II . REQUIRED CHANGES
Items # 1 .4 and 5 of Attachment 1
III . JUSTIFICATION
The change order is necessary to improve street drainage to reduce construction delays
due to standing water in streets .
IV. WAIVER
This Change Order constitutes full and mutual accord and satisfaction for the adjustment
in contract price or time as a result of increases or decreases in costs and/or time of
performance caused directly and indirectly from the change .
Change Order Fonn
00 - - I -
PftUrilitics�UTILITY - EMPLOYEE FOLDERS\Larry 9rown,AA - ppysp . Change Order NoI
- ARachmcnt2Gianncni RocAridye.dw
This Change Order represents an equitable adjustment to the contract and
CONTRACTOR hereby waives all rights to file a claim on this Change Order after it is
properly executed .
V. APPROVAL AND CHANGE AUTHORIZATION
Acknowledgements:
The aforementioned change, and work affected thereby, is subject to all provisions of the
original contract not specifically changed by this Change Order; and,
It is expressly understood and agreed that the approval of the Change Order shall have
no effect on the original contract other than matters expressly provided herein .
Change Order Request By: L . R . Brown Department of Utility Services,
Indian
''River
.C{//o rit�y, Floriiiia
Approved By: Michael C. Hotchkiss ` 1 Yd
Capital Projects Mgr. Signature
Approval By: W . Erik Olson
Director of Utility Services Signa ure
APPROVED BY; Giannetti Contractors Corp. .
Contra r
4NDIAN RIVER COUNTY, FLORIDA Signature and Date
G_ VC . Wheeler, Chairman , Board of County Commissioners
END OF SECTION * "
00450 - 2 - Change Order Form