CHANGE ORDER
No. 2
PROJECT Vero Lake Estates Master Planned 12" Water Transmission Main
DATE OF ISSUANCE November 20, 2007 EFFECTIVE DATE January 3, 2008
OWNER Sheltra & Son Construction Co., Inc.
OWNER's Contract No. UCP #2958 SBS Work Order No. 4
CONTRACTOR Sheltra & Son Construction Co., Inc. ENGINEER Schulke. Bittle & Stoddard, LLC
You are directed to make the following changes in the Contract Documents:
Description: Additional lengths of bore
Reason for change order: Additional 188 ft directional bore lengths to accommodate reverse Lap, due to
inflexibility of 12" HDPE and a paved roadway as requested by IRCDUS field personnel Delete
equivalent amount of PVC pipe asphalt overlay and sod
Attachments: (See Attached Exhibit "A"
RECOM EN `-APPRgyjrDi
BY: B
Engineer (Authorized Signature`) x., 4a4t!ure)
Date: �IZI(�g —f Sandra l • Bxden .Chairman
Date is a;
EJCDC No. C-700 (2002 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated
General Contractors of America.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIME
Original Contract Price
Original Contract Times
$
968.328.00
Substantial Completion: 240
Ready for final payment:
Das or dates
Net
changes from previous Change Orders
Net change from previous Change Orders
No._
to No. 1
No. to No. 1
$
103.248.00
30 davs
Contract Price prior to this Change Order
Contract Time prior to this Change Order
$
12071,576.00
Substantial Completion: 270
Ready for final payment:
Days or dates
Net
Increase (decrease) in this Change Order
Net Increase in this Change Order
$
10,949.60
0
days
Contract
Price with all approved Change Orders
Contract Time with all approved Change Orders
$
1,082,525.60
Substantial Completion: 270
Ready for final payment:
`
Days or dates
RECOM EN `-APPRgyjrDi
BY: B
Engineer (Authorized Signature`) x., 4a4t!ure)
Date: �IZI(�g —f Sandra l • Bxden .Chairman
Date is a;
EJCDC No. C-700 (2002 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated
General Contractors of America.
Exhibit "A"
No.
Location
Bid
New
Change
New Cost
Less +++
Total Change
Ft
Ft
Deducts
Cost
1*
79+18
150'
170'
20'
$1,880.00($540.00)
$1,340.00
2**
102+23
70'
82'
12
$1,128.00
($324.00)
$ 804.00
3***
108+89
68'
114'
46'
$4,324.00
$1,242.00
$35082.00
4+
839+72
60'
75'
15'
$1,410.00
$405.00
$1,005.00
5 ++
233+32
0'
95'
95'
$8,930.00
($4,211.40)
$4,718.60
$17,672.00
($65722.40)
$10,949.60
• ` Additional footage due to inflexibility of 12" HDPE for depth of bore under
drainage canal
• *' Additional footage to carry beyond drainage pipe
• "` Additional footage result of close drainage pipe, distance needed for bore
machine and necessity to reverse tap at CR510
• + Additional footage necessary for reverse tap at CR512
++ Additional bore necessary for recently paved road.
+++ Deduction for PVC, sod and asphalt not installed due to change in pipe
distance.
VERO LAKE ESTATES 12" MASTER PLAN WATER MAIN
11-9-07 Phase I — Bid Opening
11-13-07 Amendment No. 1 to Work Order No. 4, SBS add additional fire protection
mains on 87th 83`d 79th between 104th Ave and 105"' Ave, Approved BCC
11-20-07 Phase I —Award project to Sheltra and Sons, $968,328.00.
Change Order No. 1 — (Amendment No. 1) fire protection mains
Sheltra and Sons, $103,248.00
Contract Price $1,071,576.00
11-26-07 Public Works Change Order 2 for installation of 12" Water Main,
79th St. (106th Ave to 101St Ave)
87th St. (106th Ave to 102"d Ave) Lump Sum $124,358.00
1-3-08 Shetra and Sons - Notice to Proceed -240 days. Complete 9-2-08
1-10-08 Phase II — Bid Opening
1-14-08 Right of Way Permit issued Phase I
1-28-08 Phase II — Award project to Tim Rose Construction, $471,450.00
3-4-08 Tim Rose Contracting, Notice to Proceed -120 days. Complete 07-02-08
There are five directional bore changes for a total of 188'.
Sta. 79+18 — 915` Ave at Drainage Canal, Additional 20' due to of 12" HDPE for depth of
bore under drainage canal.
Sta. 102+23 — 91 s'Ave at 85th Place, Additional 12' to carry beyond drainage pipe.
Sta. 108+89 — 85th Place at CR 510, Additional 46' due to close drainage pipe, distance
for set-up needed for bore machine and necessity to reverse tap at CR510.
Sta. 839+72 — 104th Ave at CR 512, Additional 15' necessary for reverse tap at CR512.
Sta. 233+32 — 79th Street at 101St Ave, Additional 95' necessary to avoid open cutting a
paved road. 101St Ave is a paved road shown as dirt on the construction drawing.