HomeMy WebLinkAbout2008-144J,Z ,0009 - I•L14 CHANGE ORDER No. 2 PROJECT Vero Lake Estates Master Planned 12" Water Transmission Main DATE OF ISSUANCE November 20, 2007 EFFECTIVE DATE January 3, 2008 OWNER Sheltra & Son Construction Co., Inc. OWNER's Contract No. UCP #2958 SBS Work Order No. 4 CONTRACTOR Sheltra & Son Construction Co., Inc. ENGINEER Schulke. Bittle & Stoddard, LLC You are directed to make the following changes in the Contract Documents: Description: Additional lengths of bore Reason for change order: Additional 188 ft directional bore lengths to accommodate reverse Lap, due to inflexibility of 12" HDPE and a paved roadway as requested by IRCDUS field personnel Delete equivalent amount of PVC pipe asphalt overlay and sod Attachments: (See Attached Exhibit "A" RECOM EN `-APPRgyjrDi BY: B Engineer (Authorized Signature`) x., 4a4t!ure) Date: �IZI(�g —f Sandra l • Bxden .Chairman Date is a; EJCDC No. C-700 (2002 Edition) Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America. CHANGE IN CONTRACT PRICE CHANGE IN CONTRACT TIME Original Contract Price Original Contract Times $ 968.328.00 Substantial Completion: 240 Ready for final payment: Das or dates Net changes from previous Change Orders Net change from previous Change Orders No._ to No. 1 No. to No. 1 $ 103.248.00 30 davs Contract Price prior to this Change Order Contract Time prior to this Change Order $ 12071,576.00 Substantial Completion: 270 Ready for final payment: Days or dates Net Increase (decrease) in this Change Order Net Increase in this Change Order $ 10,949.60 0 days Contract Price with all approved Change Orders Contract Time with all approved Change Orders $ 1,082,525.60 Substantial Completion: 270 Ready for final payment: ` Days or dates RECOM EN `-APPRgyjrDi BY: B Engineer (Authorized Signature`) x., 4a4t!ure) Date: �IZI(�g —f Sandra l • Bxden .Chairman Date is a; EJCDC No. C-700 (2002 Edition) Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America. Exhibit "A" No. Location Bid New Change New Cost Less +++ Total Change Ft Ft Deducts Cost 1* 79+18 150' 170' 20' $1,880.00($540.00) $1,340.00 2** 102+23 70' 82' 12 $1,128.00 ($324.00) $ 804.00 3*** 108+89 68' 114' 46' $4,324.00 $1,242.00 $35082.00 4+ 839+72 60' 75' 15' $1,410.00 $405.00 $1,005.00 5 ++ 233+32 0' 95' 95' $8,930.00 ($4,211.40) $4,718.60 $17,672.00 ($65722.40) $10,949.60 • ` Additional footage due to inflexibility of 12" HDPE for depth of bore under drainage canal • *' Additional footage to carry beyond drainage pipe • "` Additional footage result of close drainage pipe, distance needed for bore machine and necessity to reverse tap at CR510 • + Additional footage necessary for reverse tap at CR512 ++ Additional bore necessary for recently paved road. +++ Deduction for PVC, sod and asphalt not installed due to change in pipe distance. VERO LAKE ESTATES 12" MASTER PLAN WATER MAIN 11-9-07 Phase I — Bid Opening 11-13-07 Amendment No. 1 to Work Order No. 4, SBS add additional fire protection mains on 87th 83`d 79th between 104th Ave and 105"' Ave, Approved BCC 11-20-07 Phase I —Award project to Sheltra and Sons, $968,328.00. Change Order No. 1 — (Amendment No. 1) fire protection mains Sheltra and Sons, $103,248.00 Contract Price $1,071,576.00 11-26-07 Public Works Change Order 2 for installation of 12" Water Main, 79th St. (106th Ave to 101St Ave) 87th St. (106th Ave to 102"d Ave) Lump Sum $124,358.00 1-3-08 Shetra and Sons - Notice to Proceed -240 days. Complete 9-2-08 1-10-08 Phase II — Bid Opening 1-14-08 Right of Way Permit issued Phase I 1-28-08 Phase II — Award project to Tim Rose Construction, $471,450.00 3-4-08 Tim Rose Contracting, Notice to Proceed -120 days. Complete 07-02-08 There are five directional bore changes for a total of 188'. Sta. 79+18 — 915` Ave at Drainage Canal, Additional 20' due to of 12" HDPE for depth of bore under drainage canal. Sta. 102+23 — 91 s'Ave at 85th Place, Additional 12' to carry beyond drainage pipe. Sta. 108+89 — 85th Place at CR 510, Additional 46' due to close drainage pipe, distance for set-up needed for bore machine and necessity to reverse tap at CR510. Sta. 839+72 — 104th Ave at CR 512, Additional 15' necessary for reverse tap at CR512. Sta. 233+32 — 79th Street at 101St Ave, Additional 95' necessary to avoid open cutting a paved road. 101St Ave is a paved road shown as dirt on the construction drawing.